Good morning, colleagues. I welcome members, the press and the public to the 20th meeting in 2004 of the Finance Committee. As usual, I remind members to switch off all pagers and mobile phones. We have received apologies from Kate Maclean; I am expecting Gordon Jackson to attend as a committee substitute for the Labour Party. Margo MacDonald is in attendance, although she has popped out for a second. Agenda item 1 was to have been an opportunity for Gordon Jackson to declare any relevant interests. However, as he is not here yet, I will ask him to do so when he joins us and before he asks any questions.
The Presiding Officer says in his letter:
I suggest to members that we leave questions about the future reporting arrangements to the end and deal first with this month's key points, particularly migration, which is an issue that the committee wanted to take forward. I kick off by asking the panel about point 2 in the report, on the movement from the risk and programme reserve into construction commitment. Last time we took evidence, you talked about a limited number of major projects having a continuing aspect of risk—from memory, I think that you indicated that there was continuing risk in relation to five major projects. Has that threshold moved? Is the number of projects that have a risk factor decreasing?
Are you talking about the construction contracts?
Yes.
Our understanding of the Parliament's financial exposure is that there is significantly less risk. The cost consultants have had fairly detailed discussions with the principal contractors—the large contracts clearly pose more financial risk—and those discussions have brought them to a deeper understanding of what the final overall cost of the contracts is likely to be. At the Holyrood progress group's most recent meeting, it was reported that the costs are within the sums that were anticipated last time the budget was reviewed. Although sums will continue to be drawn down against individual packages on a monthly basis as valuations are agreed, there is much less uncertainty about the remaining risk than there was before.
Are there any completion issues that will affect other completion issues? The light well was obviously a barrier to the continuation of work. Are you saying that that problem has been overcome and that there are no similar problems?
The specific issue that you raise has been discussed with the cost consultants. Even the areas in which people may have been held up are understood and accounted for in the existing moneys—the overall completion date is not affected. We are quite relaxed about the matter.
Presumably, the number of people employed on construction-specific aspects of the project will be run down and an increasing number of people will be involved with maintenance and service issues.
Precisely.
Do you have an indication of the rate of rundown of construction-related staff?
I know that at the moment the number of men on site is hovering at around 1,000. That figure will probably run down to about 200 in August, when the bulk of the snagging work will take place, prior to members and the public using the building. We hope that that work will tail off fairly significantly in September, but I do not have figures with me that indicate what the precise ratio of construction-related staff to staff involved with maintenance and service issues will be.
Presumably, the cranes that are on site will move off site soon.
That is right. Either one or two mobile cranes are on site at the moment. One is continuing to work in the Canongate light well area, where scaffolding has still to come off the final tower, and it will be the last crane to go. That will happen within the planned programme.
I have a question about snagging. Can you comment on problems with water entering certain of the roof areas, as I have noticed on a number of occasions when visiting the site? When I was last there, there appeared to be leaks and water on the concrete stairs that lead up to members' accommodation. I know that there have always been fears that the roof in that area, which has a lot of angles, will create many potential difficulties with water. Can you confirm that there have been problems of the kind that I have described? Are they included in the snagging to which you refer?
Any water ingress at this point will be dealt with as part of snagging. In one or two areas around the site, water has come in, especially when there have been heavy rainstorms. However, the problems have not been particularly serious and adjustments to roofs have not been required. It is expected that all the problems will be picked up by the time of occupation in August. I am not aware of anything that is likely to be an on-going problem.
Given that we heard that water might be a problem, it is a little disconcerting to discover that even before the building is opened some difficulties with water are being experienced.
I am not aware of anything that is a serious on-going problem. Currently, all the problems that fall into the category to which you refer are being treated as snagging items. If more severe problems are identified, they will be looked into and followed up with the relevant contractors.
Can you give us a clearer picture of the effects of the recent fire? I note that nine large concrete panels were damaged. How serious was the damage? Will the panels have to be replaced, or can they be fixed?
The damage was spalling to the surface of the concrete. Although the fire was quite small, damage was done to an extensive area because the substance that was burning created intense heat. We are awaiting a full report, but we know for certain from the structural engineers that there is no structural damage. I am sure that in the long run the Parliament will want to consider whether to replace the panels. We are awaiting advice on how a cosmetic job could be done, which would involve laser-treating and painting the surface. Until the first winter in the building has passed, we will not know the extent to which the repair might be affected by frost, for example. Replacement of the panels would be a major logistical exercise, but that does not mean that it could not be done. The corporate body may want to consider the issue next year, once we have more information about how good the repair was and everyone has had a chance to see what it looks like.
What would be the likely cost of replacing nine huge concrete panels?
We have not yet received an assessment of the total cost. However, we know that any cost should be covered fully by the insurance policy.
My question is about the work that will remain to be done after we have all moved in. Yesterday, reports in the media seemed to indicate that work will still be on-going at the time of the official opening, which gave the impression of the Queen arriving in a hard hat. Presumably, that is not the situation. Has there been a further delay in the final work—the landscaping and so on—or have you anticipated for some time that that work will take a bit longer than the time required for migration?
There has been no further delay. Clearly, there is an appropriate time for planting of trees. Since we decided on the end date and focused on achieving it, everyone on the team has been determined to see the project through to completion by that date. Some works are taking a little longer than we would have liked, but the plan is to have the building ready for occupation. We are on target to do that, allowing for the snagging that is inevitable in any project of this nature. As much as possible of the landscaping work will be done within the time available. It is a tall order, but we are making good progress. Thank goodness that the weather is fairly good.
Do you have an idea of when the landscaping will be complete? Might it not be complete until next year, given the times that are appropriate for planting?
Planting of trees will take place in November. The trees will be planted at the end of the landscape tails, where the landscaping meets Queen's Drive and the park. The planting should be the last part of the landscaping to be completed. It will probably take a full season for the trees to become established, but all the works should be done by the end of November this year.
With any new building, there is a period during which it is necessary to look out for problems such as water coming in—that is in no way unique to this building. For how long do you anticipate that minor snagging will continue? When will we be able to say that it is done and dusted?
The work will probably proceed in phases. There will be an intense period of snagging from the beginning of August, when staff move in, ahead of the main occupation of the building by members and the public. I am certain that snagging will still be on-going in September and October. We should bear it in mind that until we start to use the building in the fullest sense—with members of the public, members of Parliament, staff and contractors—we will not pick up some snags. We are not talking just about occasional water ingress, but about the basic use of the building. In the first month or two, there will be an intense period of snagging. For the first 12 months, there are retentions against the principal contract. It is quite normal for there to be some snags in a building, but I hope that many fewer will be uncovered months after occupation. Snagging will be concentrated in the first couple of months. Although we anticipate that it will continue for some time thereafter, it should do so at a much lower level.
What sums are involved in the retentions?
Three per cent of the total. Unusually, that sum will be held for all contractors for a year from practical completion of the building, rather than completion of their work. There is a significant incentive from August and September 2004 through to 2005 for contractors to remedy any defects that may emerge.
I have three brief questions. The first relates to the occupation certificate and health and safety. The letter from the Presiding Officer states:
It is important to recognise that we are not dealing with an external building certificate in the usual sense, because of the building's Crown status. The certificate is produced by our specialists. Paul Grice will provide the committee with details.
The date for which we need the occupation certificate is the beginning of August, when staff will move in. The certificate is expected to cover the whole site, but it is quite likely that at the beginning of August works will be taking place in the odd area. I understand that normally such areas are exempted from the provisions of occupation certificates. If work needs to be done on a stair or a walk, that area will be exempted, the inspector will return a week later and, if the area is clear, we can proceed. However, the target for the principal occupation certificate is the beginning of August, to allow staff to move in.
My second question is about snagging defects and completion of works. I am totally uninterested in the timing of the planting of trees, but as a potential occupant of the chamber I am interested in the completion of works there. The letter states:
The wording is slightly misleading. The work will be carried out in an area below the chamber—below the public foyer. That has been in the programme since February and the last revision. There are two points to make: first, it was thought much easier not to put on the screens as part of the current programme of work; and, secondly, there was the question whether the staff occupants would want the louvered screens in that area because of the light levels. Leaving the screens off gives the staff an opportunity to see what the area is like before committing to additional screening from the public areas.
Snagging is inevitable, but I want clarification about the completion of trade packages, although you might want to give us the details of that in writing. It would be helpful if you could indicate how many of the trade packages were envisaged to be completed by the occupation date in the original programme and how many trade packages are now anticipated to be completed by the occupation date. The current programme will reflect the slippage in trade packages, but what was the anticipated position one year or six months ago? As I recall, there were about 90 trade packages.
It would probably be easier to provide that clarification in writing. The second part of the question is comparatively easy, although I will have to go away and check how many trade packages will be completed by the occupation date. It is easier to say how many of them will be on-going at that time. We also have to ask whether "completed" means that the contractors are no longer working on site or whether we have signed off a final certificate for the packages. It is harder to comment on a point in the original programme, but we can probably say how much of the work will still be live from the programme in which we envisaged completion this summer. Practically, there should not be too many packages going on other than the snagging work.
It would be helpful to clarify that. I take your point—I am looking for a completion date not for the final haggling over the minutiae of payment, but for the packages that will involve live work on site.
Will any proportion of the snagging be work that is newly started? Will that work include the start of any new initiatives?
It should not. The management team has carefully distinguished between snagging and anything that people decide, once they have moved into the building, that they would like to have differently for whatever reason—that is not snagging. If anything emerged that required new work, it would be dealt with separately.
Do you expect any elements of snagging to have a negative impact on migration to the new building?
No, we hope not. The migration people are working closely with the project team to understand where contractors will be working. A permit-to-work system will be operated so that people who are doing snagging work do not crash into areas where people are unpacking their boxes. Snagging should follow the business of moving in as much as possible.
About a year ago, we asked for and got a schedule of cost movement on trade packages. That seems to have fallen into disuse. I understand that to a certain extent, given that we are now in a steadier state and the costs are firming up. However, I would like a commitment that a final version of that schedule will be produced at the end of the project.
That is the intention.
I add one question to those raised by Wendy Alexander. Can we have an explanation of the differences between what was anticipated—at the start of the summer, for example—and the current situation? I do not just want a list of differences; I would like some analysis of why there should be slippage.
Of course there is a plan for all remaining works; landscaping is just another package and no different in that respect. We receive a fortnightly progress update through the Holyrood progress group. A lot of people are working on a lot of packages at the same time and sometimes there is slippage as they get on with the job. That is then fed back in, reprogrammed and considered.
I am interested in quantity, not quality.
The quantity has been fixed for a long time—there are a reasonable number of toilets. As have I explained previously, we have been working extremely closely with other main attractions down in that area, most notably Holyrood palace and Our Dynamic Earth—all the evidence is that people who visit that end of the Royal Mile, especially those who come on tour buses, will be interested in visiting the Parliament building and we will be doing a lot of joint work with those organisations so that people who come to the area have a good visitor experience that includes the Parliament. That is the avenue that we are pursuing.
Do you mean that they will have to go to the toilet in Our Dynamic Earth?
If someone visits three buildings, they do not necessarily need to go to the toilet in every building.
Not everyone will.
Some people might wish to do that and I do not want to imply that there are no toilets in the Parliament; of course there are. However, it makes a lot of sense to work with other attractions in the area. We have great co-operation with Holyrood palace and Our Dynamic Earth and we will continue to develop that co-operation through survey work. However, we will not know the results until people start arriving. Much of our strategy has been about having a plan to start out with. We have to be flexible and adaptable to meet the needs of visitors and that is exactly the approach that we are adopting.
We are doing that to some degree with the catering facilities, about which we have spoken before.
We are not making a new point—there will be exactly the same number of toilets as planned last time anybody asked.
That is the concern—that there are not enough of them.
You assert that, but we will just have to wait and see how we go.
When the building comes into use by MSPs on 8 September, will it also be in use by members of the public? I want to be abundantly clear about that.
Yes. There are two key target dates. One is 8 September, which is the first day of business—that is a hugely important day for us all. The second is 9 October, when the Queen comes to open the Parliament formally. Those are the two dates towards which we are working.
Members of the public who would normally be able to enter the Parliament will be able to observe parliamentary sessions and committee meetings from 8 September.
The public will be able to observe parliamentary sessions from 8 September and any other parliamentary business in that week. If committee meetings take place in that week, we expect the public to be able to attend those as normal and we expect them to have access to all the building's other facilities. The building will have a considerably greater public area and more space for public exhibition.
Will catering and other services be operational?
Yes.
I am sorry that I was not present at the beginning of the meeting; another matter detained me. However, I can state that I am not lavatorially obsessed, as other members appear to be, so I will ask about another subject that arises from the section on migration and occupation in the Presiding Officer's report. I will ask about the plans that are in place for the smooth management of visitors.
I think that we will hear the views of one panel member—Robert Brown.
I will kick off. I am sorry that Fergus Ewing sees fit to cast aspersions on the previous Presiding Officer. The building plans on the matter that he raises have pretty much been there from the beginning, subject to the changes in the chamber's size that the corporate body made when it took over. In the gallery, 225 seats will be available, together with seats for the media. I admit that that figure is not as big as the figure in the Assembly Hall, but it is significantly bigger than the number of seats in Westminster.
It is much bigger than the figure in Westminster.
Are those 225 seats for the public?
I am talking about the public. It is a substantial—
Are those seats for the general public as opposed to the distinguished public?
I ask Fergus Ewing to let the witness answer.
The seats are for the public, which gives potential for substantial attendance, to which is added the considerable amount of space in the committee rooms. The matter relates to a slightly different issue from the 700,000 expected visitors, because the building will have a series of facilities other than just the chamber. It is wrong to say that only 150 seats will be available. There will be 225 spaces, plus spaces for the media. I ask Paul Grice to elaborate.
I am happy to pick that up and I am grateful to Fergus Ewing for having raised some of the matters with me. I think that 225 seats are available for the public and that 277 is the total number of seats when the media and the guest gallery are included. That figure is substantial but is not as big as the current number.
I know that Paul Grice is making much effort. I have had the opportunity to discuss with him in private some matters and they are all right as far as they go, but I think that I am right in saying that Lord Steel gave an undertaking that 250 seats would be available for the public and that that will not be the figure. That is a matter of record, but I stand to be corrected by Mr Brown if he wants to contradict me—it is just a matter of looking out the press release.
I am delighted to hear that Fergus Ewing has become an enthusiast for the Holyrood Parliament building—that seemed to be what he was saying earlier.
I echo that. The figure of 700,000 visitors was arrived at on the basis of survey reports and assessments by experts; nevertheless, the figure is only a prediction. We do not know how many of those visitors will want to go into the chamber, attend a committee meeting, have a cup of tea or go to the toilet.
The prediction is that 2,000 people will visit the building every day—
In the first year.
That is approximately ten times the capacity. I did not suggest, as John Home Robertson implied, that the layout be changed; I suggested that seats be installed at the back of the chamber. I was pleased that Robert Brown, at least, did not appear to rule that out. In all seriousness, I hope that the matter will be considered now, rather than after we move into the building.
From experience in another Parliament, I can say that not everyone who visits the Parliament building will want to go into the public gallery. It would be sensible to wait and see. If there is pressure on space in the gallery, it might be possible to consider ways of tweaking it, but anything that would require an extension to the scale of the building would be another story altogether.
I will put Fergus Ewing's mind at rest. If an overflow is needed, visitors will be able to go to Our Dynamic Earth or somewhere else.
Margo MacDonald makes an extremely good point. I understand that screens will be in place at various points in the building. To be honest, it would not necessarily be a bad thing if there were to be demand to get into the building and the chamber because there was a sense of excitement about Scotland's democratic forum.
Whoever the new leader of the Opposition is.
However, the visitor numbers are only predictions at this stage.
Of course, there will be different types of visitors, including citizens of this country, people from the United Kingdom outside Scotland and people from abroad, who will have different expectations. In addition, there will not be an even pattern of visits throughout the year. Fergus Ewing's sums strike me as being about right in one context but, ironically, a lot more people will visit during the summer recess when there is no parliamentary business, and visits to the gallery will be less of an issue at such times.
I make two brief points. First, I am definitely not lavatorially obsessed, but I follow up Margo MacDonald's point. When I raised the matter of tendering for the provision of toilet facilities, Sarah Davidson provided me with a fairly full explanation, for which I was grateful. However, I remember that I also drew the committee's attention to the fact that the cost of the toilets had escalated to three times the original estimate. I think that at that time John Home Robertson mentioned that an investigation was going on into why the cost of the toilets had tripled. Can he tell us whether there has been any progress on that?
The Holyrood progress group received an interesting paper that went into some detail about the evolution of those costs. I do not have a copy with me, but we found the paper quite alarming.
The final paragraph of the letter that I sent to the convener on 6 May summarises the paper to which John Home Robertson referred. The paper provided a breakdown of the escalation in the costs throughout that package, but it did not answer all the questions, because obviously there was a big escalation in time-related costs. As I think that I said at the time, the auditors have been examining that package as part of their on-going work and we expect to receive their comments on the matter in due course.
My second point is more general. We know that Sarah Davidson has been under a huge amount of pressure and I am sure that she is looking forward to a rewarding break, away from all of it. Have all the necessary steps been taken to enable a deputy to take over who will have full knowledge of everything that has been going on? I assume that that is the case.
I should deal with that. The short answer is yes. The new head of the Holyrood project team will be Paul Curran, who has been the senior project manager for the past four years and has deep experience of the project. Obviously, Sarah Davidson's departure will pretty much coincide with the completion of the building and there would have been a restructuring at that stage in any event. We do not need to keep on the same project team, just as is the case for the Holyrood progress group, which will wind up at the end of September or beginning of October. Paul Curran will head up a follow-on Holyrood project team—if I can call it that—the principal function of which will be to deal with matters such as the settlement of claims or defects. He will lead a strong core of professionals and a much smaller administrative team. The Presiding Officer mentioned in his letter that we will also keep on some senior expert advisers who will advise me and Paul Curran. The new Holyrood project team will be part of the technology and facilities management directorate, where it will be able to link into the implementation team and to facilities management and information technology—that is exactly where it should be. The restructuring would have happened in any event, but that is the position and the new arrangement will kick in in a week or two from now.
Constituents who have difficulty gaining access to the public gallery in the chamber or elsewhere will be welcome to watch the proceedings on the large, extravagant, wide-screen televisions that will be installed in every MSP's office.
There are approximately 70 seats each in the two large committee rooms and about half that number in each of the four smaller rooms: that is about 280 in total, which more than doubles the overall capacity.
Given the expected visitor numbers and the fact that the majority of visitors will not spend a long time either in committee rooms or in the galleries, I would have thought that many people will be at the public entrance where the shop and cafe will be. A large number of people will be in one part of the building and will not go through to take part in the democratic process. How will that be managed? What security measures will be in place? Will you appear before the committee again to outline additional expenditure for different facilities in that area?
We have examined that closely, too, and we have brought in people with practical experience of managing major tourist attractions. It is all about visitor flows. There is a lot for people to do in that area. There will be an exhibition about the Parliament and, as Jeremy Purvis says, there will be a substantial television screen. Many people will be happy just to observe what is going on in the chamber. Many people might not even come into the building, as they might just be interested in coming to look around the outside of the building—that is quite common.
Will those be ready by 8 September?
Yes. The target date is the first day of public business, which is 8 September.
Margo MacDonald should be one of the tour guides.
I have looked my wee hat out.
No.
I do not mean to be negative. I am flagging the issue up, as I have done before. I would have thought that having all those visitors would affect maintenance costs. With such a large number of people traipsing through the place, the carpets might not last as long as has been planned. Somebody should look ahead and say, "If we have that traffic through the Parliament, there will be greater wear and tear. Greater wear and tear means that more people will be needed to service the Parliament, and that will be done at greater cost."
If the people of Scotland wear out the carpets, I can see that only as being a good thing.
Such issues have all been taken into account. We have had survey work on visitor numbers for more than a year; the latest figures are an update to a previous survey. Margo MacDonald will know that in the major public areas the flooring is Caithness stone, which is well known for its durability. The cleaning plans and planned maintenance will have to take footfall into account, as there is no denying that it is a key issue; it has been factored into all the maintenance and cleaning contracts. We will have to see how it goes. Another key point is that flexibility is built into the contracts as some areas may require more cleaning and maintenance than others. However, the building is made of extremely durable materials, such as oak, sycamore, granite and Caithness slab, which are designed to cope with a high footfall. By and large, we have avoided carpets, for the reasons that Margo MacDonald mentions. The floor materials in particular are very durable and I would expect them to last for a very long time.
If the roof does not leak, I am sure that the Caithness stone will be perfect, but if it leaks, you should think about the compensation claims.
If the roof leaks, we will have to fix the leak.
I start by congratulating the people present on nearly reaching the conclusion of the project, which I imagine has been a harrowing project for all of them—their application to it is to be commended. We must put on record the fact that, without George Reid, we could have been waiting for another year—perhaps if he had become Presiding Officer a year earlier we would have been in the building by now.
Among other places, there are appropriate quotes from our national bard on the Canongate wall.
Are they low-profile or high-profile?
They could not be more public.
At the edge of the Parliament that backs on to the Canongate, coming down from Queensberry House, there is what is called the Canongate wall—I think that it is a remarkable piece of architecture and design. There are quotes on it and Robert Burns features prominently.
Margo MacDonald and I were victims of the lifts. As far as I can remember, there was no ventilation in the lift. Can Margo MacDonald remember there being any?
No.
Eight of us were in a lift that is designed to take 21 people—if 21 people had been in there for 20 minutes or half an hour, some of them could have expired. Will you please look into ventilation in the lifts? I will be using the stairs.
Honestly, I was not responsible for that—although I know various people who might have been tempted, knowing who was in the lift. No, I am sorry.
I will obviously look into that.
I will not go back in that lift unless there is a man in a boiler suit with a spanner standing beside it.
On the positive front, you did a helpful piece of snagging for us.
I hope that the quotation from Robert Burns that is displayed in the Parliament will be:
I think that that is the quote.
Oh, that I had such influence over other parts of the project.
Not yet, is the answer.
I am pleased with that answer, which was not entirely unexpected.
I am sure that the committee supports the chief executive's efforts to secure a rational and sensible solution.
I will answer your second question and Sarah Davidson will deal with the point about disabled access.
The clear plan is that by 8 September, when the public will start to use the building, everything should be complete so there should be no particular issue with disabled access. We are aware that on-going snagging in certain areas has the potential to raise hazards that might pose a problem for people whose mobility is impaired, but a regime is in place whereby the Parliament's health and safety manager will monitor that to ensure that there is no impact on people who use the building. Those matters are all well in hand.
Finally, on future reporting arrangements, the progress report suggests that
I have already given some thought on how that system should be put together. The process of settling final accounts will probably start in earnest from next month. Although our cost consultants have been in continual discussion with package contractors, only about £26 million of work has been finally signed off at project team level. Over the coming months, that figure will ramp up considerably. As that happens and as works are completed on site, all the remaining allocations of risk to individual packages will be made and the sums that are currently in construction commitment will become firm. In other words, moneys in construction commitment are anticipated sums and only when the Parliament has given its final signature do they become the final cost for any given package.
Am I right in thinking that the Auditor General's report on the Holyrood project is now available?
No. It is not finished, although a draft of the report is being circulated. I understand that the Auditor General intends to publish the report shortly.
Am I correct in my understanding that you have already seen a copy of that draft?
As is normal, I have.
Are you happy with its contents so far?
I imagine that I will discuss that matter with the Audit Committee in due course.
Under the heading "Other post-completion matters", the Presiding Officer's progress report states that the Holyrood progress group will hold its last meeting on 29 September and will be formally wound up on the date of the official opening. The Presiding Officer goes on to state:
Yes. If I may, I will take the opportunity to explain in a little more detail what the Presiding Officer was driving at in the last paragraph of his letter. Paul Curran will head up the team that forms part of the executive chain of command that flows through me. We need expertise of the type to which Fergus Ewing referred. The advice that I have received, which I intend to follow, is that, rather than ask a claims expert to sit on the advisory group, we should bring that person into Paul Curran's team.
As Paul Grice touched on, it is not the job of the corporate body to manage all the work, nor is it our job to be involved in the details of claims and so forth. At the same time, we are keen to ensure that there is a bearing down. Among other things, we want to ensure that claims are not settled unnecessarily for the sake of a quiet life.
I am broadly satisfied with both answers, for which I thank Robert Brown and Paul Grice. I was relieved to hear Robert Brown say that there is no question that any claims would be settled for "the sake of a quiet life". Some members have taken a particular interest in aspects of the project and, obviously, the SPCB has had the job of being financially responsible for the project. It will now have—it cannot shed—financial responsibility for dealing with any claims and legal actions that arise from the process. Frankly, I would be astonished if a number of claims are not made.
The corporate body is a statutory creation that was established to manage the affairs of the Parliament on behalf of the Parliament. It is, of course, subject to instructions from the Parliament—should it seek to give such instructions—on the way in which the SPCB manages its affairs. For example, the establishment of the Holyrood progress group was the result of a parliamentary decision. As a result of that decision, a number of issues arose, which I think were managed at the time. I think that the arrangement has worked out well; certainly, it has worked out better than I anticipated at the time. There has been a good spirit between the members of the corporate body and the progress group.
I am anxious to bring this evidence session to a close, but I will take a brief question from Margo MacDonald.
Fergus Ewing's question highlights the fact that the corporate body is insufficiently accountable. As has been asked before, how can a member ask questions about the corporate body? Rather than establish another body to monitor what the corporate body is doing, members who have particular concerns should be able to ask questions. Our procedures are lacking in that respect. It might help everybody if the Procedures Committee were to take up this issue as a case study. Fergus is asking for assurance that correct decisions are being taken. Whom do we ask about that?
The answer to that question lies in the reports that are made to the Finance Committee. If a process is in place to ensure that this committee receives regular reports, it will be open to members of the committee to pursue any issues that arise. Other MSPs can come along to our meetings—as you have done this morning, Margo—to ask precisely the questions that they want to ask. A mechanism is therefore already in place.
I agree that a mechanism is in place, but a belt-and-braces solution might be better. Members sometimes feel frustrated because they know that time could be saved by short-circuiting that mechanism and asking questions directly. However, it is difficult to get answers quickly.
There is a facility for parliamentary questions, although I accept that written replies can be limited. We should also consider the relationship between the Finance Committee and the Audit Committee. We are at a final stage and are looking backwards as well as continuing to move forwards, so we should consider the most effective way in which those two committees can relate to each other.
There is hassle, let me tell you.
I thank the witnesses for coming along today. I particularly thank Sarah Davidson and John Home Robertson, who I suspect are unlikely to come before the committee again if we are moving on to consider financial monitoring. The Finance Committee has performed its scrutiny function, although I know that that is not always comfortable for the people being scrutinised. I thank you for your forbearance.
Thank you, convener. You have done your job and we are trying to do ours. I would like to say that Sarah Davidson has done her job very well indeed. She has been a very good servant to the Parliament.