- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 01 November 2021
-
Current Status:
Answered by Michael Matheson on 15 November 2021
To ask the Scottish Government whether strategic consideration has been given to how the decommissioning of wind turbines can be conducted to ensure that materials (a) remain in Scotland and (b) are recycled.
Answer
The Scottish Government launched a consultation for a refreshed Onshore Wind Policy Statement on 28th October 2021 which sets out our ambition for an additional 8-12 gigawatts of installed capacity by 2030. The policy statement also references the potential for refurbishment and recycling of wind turbines, supporting the recent Zero Waste Scotland report 'The Future of Onshore Wind Decommissioning in Scotland'. The Scottish Government are fully supportive of this work and its alignment with our zero waste policies.
- Asked by: Rachael Hamilton, MSP for Ettrick, Roxburgh and Berwickshire, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 01 November 2021
-
Current Status:
Answered by Patrick Harvie on 15 November 2021
To ask the Scottish Government whether it will work with the UK Government on the delivery of low-carbon alternatives to gas boilers, such as heat pumps.
Answer
The Scottish Government is already working with the UK Government across a number of policies to support delivery of low-carbon alternatives to gas boilers. This includes engagement in relation to the UK Government’s proposed market-based mechanism for low carbon heat. Further details on our work with the UK Government are set out in chapter 10 of our Heat in Buildings Strategy.
Scottish Government Heat in Buildings Strategy – https://www.gov.scot/publications/heat-buildings-strategy-achieving-net-zero-emissions-scotlands-buildings/
- Asked by: Rachael Hamilton, MSP for Ettrick, Roxburgh and Berwickshire, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 01 November 2021
-
Current Status:
Answered by Patrick Harvie on 15 November 2021
To ask the Scottish Government how much it plans to invest in the installation of heat pumps in homes as a replacement for gas boilers.
Answer
The Scottish Government has committed to invest at least £1.8 billion over the course of this parliament to support energy efficiency and zero emissions heat. Final spending to support households replacing gas boilers with heat pumps over this period will depend on various factors, including the balance of demand between households currently using gas boilers or other heating systems, and support for other technologies such as heat networks.
- Asked by: Beatrice Wishart, MSP for Shetland Islands, Scottish Liberal Democrats
-
Date lodged: Monday, 01 November 2021
-
Current Status:
Answered by Patrick Harvie on 15 November 2021
To ask the Scottish Government how many pupils completed cycling proficiency training courses in each year since 2018-19, and how many are expected to do so in the 2021-22.
Answer
| | Level 1 | Level 2 | Level 3 |
2018-19 | 20,201 | 21,671 | 180 |
2019-20 | 9,300 | 6,678 | 111 |
2020-21 | 21,158 | 19,140 | 48 |
Participation data for 2021-22 will be available in September 2022.
- Asked by: Stephen Kerr, MSP for Central Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 01 November 2021
-
Current Status:
Answered by Lorna Slater on 15 November 2021
To ask the Scottish Government by what date it plans to introduce a deposit return scheme.
Answer
I refer the member to the answer to question S6W-03193 on 4 October 2021. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Richard Leonard, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Tuesday, 26 October 2021
-
Current Status:
Answered by Graeme Dey on 15 November 2021
To ask the Scottish Government whether it will specify any Scottish rail infrastructure and enhancements works identified for Control Period 6 that will (a) now not be carried out and (b) be scaled back.
Answer
Responsibility for delivery of rail infrastructure renewal works rests with Network Rail as overseen by the Office of Rail and Road. The Scottish Government is aware that there have been some delays in the delivery of some parts of this renewal programme in Control Period 6 to date. Enquiries concerning this should be addressed to Network Rail or the Office of Rail and Road.
- Asked by: Richard Leonard, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Tuesday, 26 October 2021
-
Current Status:
Answered by Graeme Dey on 15 November 2021
To ask the Scottish Government whether the budget for Scottish rail infrastructure renewals and enhancements for Control Period 6 has been reduced, and, if so, by how much.
Answer
There has been no reduction in Control Period 6 budget for rail infrastructure renewals and enhancements activities in Scotland.
- Asked by: Paul McLennan, MSP for East Lothian, Scottish National Party
-
Date lodged: Thursday, 21 October 2021
-
Current Status:
Answered by Tom Arthur on 15 November 2021
To ask the Scottish Government how it plans to strengthen policy on ancient woodland and veteran tree protection in National Planning Framework 4.
Answer
Our draft National Planning Framework 4 (NPF4) sets out how our approach to planning and development will help to achieve a net zero, sustainable Scotland by 2045. This includes draft planning policy on Trees, Woodland and Forestry, which states that development proposals should not be supported where they would result in; any loss of ancient woodlands, ancient and veteran trees, or adverse impact on their ecological condition.
Views are currently being invited on the draft NPF4 alongside parliamentary scrutiny, following which we anticipate producing a final version for approval and adoption around summer 2022.
The draft NPF4 is available to view on the Scottish Government website at: Scotland 2045 - fourth National Planning Framework: draft - gov.scot (www.gov.scot) .
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Thursday, 21 October 2021
-
Current Status:
Answered by Patrick Harvie on 15 November 2021
To ask the Scottish Government, in view of the high level of service requirements of Cycling By Design, published on 17 September 2021, which Overseeing Organisations are responsible for reviewing and approving designs, and how it will ensure that these organisations assess designs equally and fairly.
Answer
The organisation promoting the scheme is responsible for reviewing and approving designs. Cycling by Design advocates a high level of service whereby schemes will be suitable for most users, including new and less confident users. Where a high level of service cannot be achieved the reasons for this should be documented in the ‘Design Review’ process as recommended in the guidance.
- Asked by: Neil Bibby, MSP for West Scotland, Scottish Labour
-
Date lodged: Wednesday, 13 October 2021
-
Current Status:
Answered by Graeme Dey on 15 November 2021
To ask the Scottish Government how much of the funding allocated to the East Kilbride line electrification and upgrade project will be reallocated, in light of its reported decision not to proceed with double-tracking between Busby and East Kilbride railway stations.
Answer
I am pleased to confirm that, notwithstanding the severe financial pressures caused by the Covid Pandemic, sufficient funding can be made available to complete fully the preferred option for the electrification and significant enhancement of both the East Kilbride and Barrhead routes.
This preferred option was recommended by and agreed with rail industry partners Network Rail and ScotRail following detailed consideration of a wide range of options, the business case appraisal of which has followed appropriate Scottish Government processes