I welcome members to the 15th meeting of the Finance Committee in the second session of Parliament. I also welcome members of the press and public and I remind everyone to switch off all pagers and mobile phones.
Thank you, convener. This time round, I have little to say on the finances; no substantial changes in costs have been reported since our previous appearance before the Finance Committee. The committee will know that the final cost is closely related to completion within the current time frame of the plans. The completion of the MSP block and of Queensberry House, expected in the next week or two, is significant. Much as I enjoy appearing before the committee, I think that I can now say that, if we are not yet at the end of the process, we are certainly at the beginning of the end.
I will pose two questions to start off with. The November report says:
As the report says, there is slippage in the work in a number of building areas. For example, there is slippage in the tower areas, where delays in the installation of windows have meant that work on internal finishings has not proceeded as fast as we had hoped. Some of the delays run concurrently, so we cannot add up all the delays to get a total figure. There are delays of between two and six weeks in different areas. Bovis Lend Lease Ltd is examining ways in which work can be resequenced in those areas so that the overall completion date can be held to. As we have explained to the committee before, there is a degree of scope for resequencing within individual packages. Once the externals have been completely sealed, there will be a good deal of scope for using acceleration measures to fast-track the internals. We have seen that being done very effectively in the past few weeks in the MSP block and Queensberry House.
Have you identified the key barriers to achieving the July completion date? Has Bovis given you further information on its degree of confidence that the July date will be achieved?
As the report indicates, there are major targets in the critical path that will have to be met, such as progress in the chamber and in the light well. Bovis has made it clear that completing external works to a degree that allows it to proceed safely with internal works will be key. It has not indicated that we have hit an insurmountable barrier or a brick wall; it is still examining the situation and has told us that it believes that the completion date is still achievable. It will report to us again in mid-January when it has carefully scrutinised how successful the measures that it has been implementing have been. We will review the situation again then. However, at the moment, Bovis is making it clear that it is still working towards the summer date.
One of the cusp points mentioned in the report seems to be the taking down of the crash deck in the chamber. The date given is mid-January. I presume that, by mid-January, Bovis should be able either to give you firm information on whether that has been achieved, or to indicate the possible implications if it has not been achieved.
Absolutely. The scope for working over the Christmas period is being explored in order to give greater confidence of meeting that date.
The report includes information about times in order to show the key targets that we have to meet if we are to keep the critical path not critical—if that is the right way to put it.
The report says that towers 3 and 4 are well advanced. In September, you expressed confidence that they would be finished by the end of February. Are they still on target?
I do not have the figures with me, but my recollection is that work on internal finishings in the towers has slipped by about three weeks. The completion date will depend on what, if any, acceleration measures are worth adopting. As we have discussed with the committee before, judgments have to be made all along about when and where it is worth accelerating work on an area. If the completion of the towers is not critical to the overall completion, there will be no particular advantage in working hard to pick up those two or three weeks. That is a matter of judgment. However, the partitioning and creation of individual offices is well advanced.
The report mentions crucial milestones that have to be reached in order to meet the completion date that we all hope you will be able to achieve. Are you confident that those milestones will be reached by the middle of January?
I have no reason to think that they will not be reached. Bovis has told us the dates that it is working to and those dates are shown in the programme of works.
Bovis still thinks that the dates are achievable.
Absolutely.
I want to be absolutely sure about this. If you do not achieve the mid-January date for the removal of the crash deck, will you be unable to hit the July date?
We cannot say that for certain, although we can say that it would be a great deal harder to do so. Part of what Bovis does, as construction managers, is to programme and sequence works. That is both a fine art and a high science. It is Bovis's job to work out how we can get past problems. There is no doubt that, for the currently planned sequence of events to roll out as expected, the deck will have to come down by mid-January. However, Bovis has not said that the whole game will be off if the crash deck does not come down by then. We can be absolutely certain that, if there are delays in that respect, Bovis would consider very carefully how it would be possible to recoup that time.
I have a question for Robert Brown based on information that went into the public domain last week in response to a question from John Swinburne. As we know, the estimated cost of the building is just over £400 million. We have also been told that approximately £100 million has been spent on proofing the building against bomb blasts. That indicates recognition of a possible threat—indeed, there was publicity about that in The Scotsman yesterday. However, it emerged last week that the building is uninsured. Does it not seem somewhat contradictory that we spend £100 million on proofing the building against bomb blasts and yet the Scottish Parliamentary Corporate Body has apparently decided that the building does not require to be insured?
I think that Fergus Ewing is well aware that Government policy is to self-insure on such matters. In fact, I think that that is also the policy of several councils. That is nothing to do with the building's being uninsurable or insurable; it relates to the fact that the Government has resource across the board to deal with such matters instead of paying premiums to insurance companies. The practice is commonplace and is applied in other parts of the Government in Westminster and in Scotland.
That may be the case for normal buildings, but no one would call the new Scottish Parliament building normal. As we have spent a quarter of the total cost on bomb proofing, it is odd—if not reckless—not to insure the building. Is the House of Commons insured?
I do not know, but I think that it is probably dealt with on the same basis as the new Scottish Parliament building.
Might the corporate body wish to examine that urgently?
I have no difficulty with our doing that. The answer is probably fairly easy to obtain. However, I repeat that for a series of valuable buildings in the Government domain in Westminster and in Scotland, the policy is one of self-insurance, for good reasons.
I understand the general point, but there is a difference between a building that houses the ministry for paper-clips and a building that the authorities have overtly acknowledged could be a target. In these febrile times, one recognises that thinking.
I reiterate the point in my letter that such articles are a huge blow to the highly dedicated work force on the site. It is deeply regrettable that much of the reporting, which was largely of anecdote and hearsay, was presented in an unhelpful way. We expect the people in the work force to work extremely hard to complete the building. That is an important point.
You are saying that the allegations are without foundation.
That is what Bovis told us and I have no reason to disagree. I tend to take more seriously the advice of professional project managers than that of undercover journalists. I am not sure what the journalist's construction experience was. We sought and received reassurance from Bovis.
Obviously, we accept that. We all welcome the fact that the work force raised a substantial amount of money from a charity football match for a local school.
What counts is what has implications for the Parliament and the corporate body. Contracts are in place under which contractors deliver bits of work, for which they are paid if the work is done right and not paid if the work is not done right. A goodly bit of the Daily Mail article related to matters that were between subcontractors and their people. As Paul Grice said, when work has had to be redone on the odd occasion—I understand that that has not happened often—if the fault lies with the contractor or with workmanship that is within its control, that work is undertaken at the contractor's cost. The Parliament need not make a detailed investigation of all the press reports on such matters.
I am interested in the schedule of trade packages in Paul Grice's letter, which shows cost-plan allowances and current trade contract values. The data are all present, but my criticism is that they are not very comprehensible. Earlier, I produced a schedule that totalled the figures and drew out the variances and other matters. It would be more helpful to have something that showed running totals and allowed us to make a proper comparison.
We talked about exactly that issue before we came to the committee this morning. We recognise that the table at annex B to Paul Grice's letter grew out of something that was required for a different purpose. Robert Brown asked this morning to what extent we could tie in the table with the model of reporting regularly to this committee. We will examine that. It is hoped that the next full report will contain something that is much more comprehensive and on which the read-across from annex A to the Presiding Officer's letter to the trade packages is clear.
I had a discussion with the convener before the meeting started. I could not remember whether we had been given explanations of why certain costs had escalated to the extent that they have. I am talking about matters such as the cost of windows in the MSP block. Although it was pointed out to me that we have had some oral or anecdotal evidence on the matter, it would be extremely useful if you could remind the committee why some items have more than doubled in cost and why we have got to this stage. That would save us coming back and constantly asking you for information that we should probably have remembered from an earlier meeting.
What I thought we might do when we redraft the table, which could be done more quickly than a package-by-package analysis, is to show broad areas where there has been an increase—we would indicate where a certain package has been particularly affected by time or bomb blast, for example, so that members could tell at a glance where such issues have had an impact. If members then want further, more detailed information on individual packages, we could provide that on an ad hoc basis.
That would be helpful.
You have helpfully given us part of the timetable and the deadlines for the remainder of the project. Assuming that each of those deadlines is met, we will be on course for the July target. However, what steps will be taken if targets such as that for the removal of the crash deck in the chamber are not met? Will the contractors reorganise and accelerate the work or would the failure to meet the targets be seen as a major breach of contract? Would the moneys involved have to be recouped down the line through legal action? When will such decisions be made?
Those issues are dealt with on a case-by-case basis. On the example that you have given of the crash deck in the chamber, the project team would expect to receive a report from Bovis after the Christmas recess, which is about when that work should be complete, indicating whether the work has gone to programme or whether there has been a delay. If the work has gone to programme, we assume that the programmes that we have from Bovis will roll out as planned; if there has been a delay, Bovis's contractual responsibility as our programmer is to make proposals to us on the ways in which that time might be recouped or the ways in which the processes that follow on from the delay can be replanned, resequenced or remanaged. As I said, it is for Bovis to come to us and set that out. It may be that the proposals would involve a measure of acceleration in some places. If that acceleration has additional costs attached to it, it is for the client to decide whether it wants to commit those costs.
What I am getting at is that, although we hear the language of targets that have to be met, the explanation that we hear subsequently is that a target does not have to be met, because there is no agreement with either the managers of the project or the contractors to meet that target and the work can be accelerated or rescheduled. We have also heard in the past that those targets have to be achieved if we are to meet a subsequent deadline, which is now set at July, but that there may be reasons why we cannot meet the deadline. My difficulty is that, although we hear determined language about meeting targets, nothing backs you up in enforcing that.
You are right. What you eloquently describe is the nature of construction management. Something that both the committee and those of us at the official end are constantly wrestling with is that, although Bovis is on our side and is working with us to try to achieve targets, it has no contractual obligation to meet a certain date. That is the nature of our contract with Bovis.
Have you received any legal advice that extra contractual agreements can be reached with any companies so that July is a deadline and, if that deadline is not reached, there will be significant penalties? Have you had discussions with the chairmen of each of the contracting companies or have you had legal advice that further agreements can be made? What confidence can we have now—other than the percentage confidences that you used to give us about completion—that you will focus everybody's mind on paper? I do not know whether such agreements are possible. Have you received advice on that?
The way in which the contracts are established means that each individual contractor works for the Parliament rather than for Bovis, so that the contractual relationship is between us and the individual contractor. Were we to wish to give Bovis the power, as it were, to ensure a completion date, we would have to change completely the basis of all the contractual relationships so that the contractors worked for Bovis. There is no doubt that that would come at a very high cost. Our view is that the way in which Bovis is managing the package contractors towards completion on a highly complex building is the best way of achieving the targets that we are aiming at. We have not asked for any specific legal advice on whether we should change the basis of those contracts. The professional advice of the project team that we are working with is that we should not seek to do that.
It is obviously a little late in the day to seek to renegotiate such contracts. The timetable points that Jeremy Purvis mentioned are very much in the minds of members of the progress group. We receive reports when we meet every fortnight. If there is evidence that a contractor is having difficulties and things are running late, we interrogate and investigate ways in which the work can be accelerated and how other contractors might be able to help. That is our job; we are examining the matter constantly.
Have there been discussions with the people who managed the millennium dome? They set a deadline that had to be achieved.
Please do not compare the Scottish Parliament building with the millennium dome.
Unfortunately, almost all of my constituents do. The relevance of the dome is that a deadline was set for its completion. I do not know whether you have had discussions with those in government who had a relationship with the contractors on the dome project.
The trouble is that, once the construction contract method has been put in place, it rules the way in which we go. If we were starting the project again, we might well not go down that track because of the experiences that we have had, but we must face the issues within the current context.
We hope that, by the end of January, when we get to the next stage in the process relating to the key points that have been identified, you will be in a position to show us that the range of uncertainty has significantly diminished and indicate how much further you expect it to diminish month by month until we get to July. That is the essence of what the committee is looking for.
For all sorts of reasons, including the public interest, there is considerable pressure—both public pressure and other pressures—on everybody who is involved in the project to get on with it and finish it as quickly as possible. Everything is in place, in that Bovis and the contractors are working hard to reach the dates in question and, as a result of the professional advice that we have received, we do not think that any different contractual arrangement would improve matters.
We are currently discussing with Bovis proposals for incentivising particular contractors for completion, arrangements for the release of potential and so on. We are very much alive to such issues.
With hindsight, everyone in the country is well aware of the total naivety of politicians and civil servants in awarding a contract without time-scale limitations and penalty clauses. However, I will put that aside and accept that it is water under the bridge. When will the building ultimately be complete? Is there any possibility that the completion date will be brought forward and that all of us will be given a tremendous lift and surprise by your beating your own deadline?
We cannot make such a promise at the moment. The Presiding Officer's letter makes it clear that we have discussed January as a key date for taking down the crash deck. Beyond that, the next key date is March, when the back of the chamber will effectively be completed. If we hit that critical target, which is right on the critical path, people can get inside it and begin to work fast on the fit-out. We have seen what Bovis can achieve in the MSP block and Queensberry House when it can work in that way. If we reach that milestone, I expect that we will be able to talk in very confident terms if we come to a committee meeting in March. If we do not reach it, we will obviously report in different terms.
What is the worst scenario? How much later would the very worst scenario be beyond the date when you all plan to put on your jackets and go home? What is your final date?
We have always worked on the basis of the information that Bovis has given us and I have not been given a worst-case scenario. My speculating on such matters would not be particularly helpful.
On behalf of the committee, I welcome Mr Zaluszky and the delegation from the National Council of the Slovak Republic, who are here to observe the Finance Committee in operation. [Applause.]
I wonder whether a Parliament building is being built in Slovakia.
It is always gratifying when we are visited by colleagues from a newly independent country.
The construction management contract does not contain a date by which the building must be complete. Bovis is required to give the best programme advice to the client and to programme the works, but the contract does not say that the building must be delivered by a specific date.
My recollection is that the completion date for the building was originally specified as some time in 2001. From the outset, a date was specified as to when the building would be complete. Why was that date not put into the contract? Why were the construction managers not under a legal obligation in the contract to procure trade packages that would be completed in accordance with a timetable and schedule of works that enabled them to ensure that the work was completed on time?
Before someone answers that question, it should be remembered that there are issues that fall within the responsibility and remit of the Finance Committee and others that fall within the responsibility and remit of the Audit Committee. Perhaps some of the issues in Fergus Ewing's questions fall into the latter category.
Most of the issues that Fergus Ewing has asked about are not matters for which the Parliament has responsibility. As he is well aware, the initial contracts on arrangements with Bovis, construction methods and so on were set up by the Scottish Office.
I am sorry, but that is wrong. I will take a step back to demonstrate that that is simply incorrect. Following representations that I made at some length to the Presiding Officer that the contracts between the Parliament and the contractors should be made public, which culminated in a meeting at the end of June, the Presiding Officer agreed that they should be. Incidentally, I would be grateful if we could be told when we can see those contracts. I understand that we will be able to see them when amendments to the contract dealing with fee adjustments have been completed, but I would have expected those to have been completed by now.
I am saying that the binding letter of intent was in place prior to the Parliament's taking over the matter. For what it is worth, we have said that that letter will be made public.
It will be made public at the same time as the contracts for the minutes of variation—I think that I have already made that clear in a letter.
Formalities to complete the finalised formal contract might have been completed later, but the key issue is that the contract was entered into by the Scottish Office before the formation of the Parliament. However, the convener is right. The matter is one for the Audit Committee. The rights and wrongs of that matter do not affect the issue that we must consider at this point.
The convener did not interrupt Sarah Davidson when she gave evidence about features of construction management, so it is germane to probe assertions that have been made. I simply ask whether it is really being put to us that an inherent defect of construction management contracts that cannot be remedied is that deadlines cannot be inserted into them. I find that hard to swallow.
Construction management involves a variety of pros and cons in respect of the terms on which it is taken on board. We have previously discussed such matters. Many of us who have had to live with the matter are well aware of the difficulties that we face. Whether we would face such difficulties under another form of construction management agreement is another matter.
With respect, my question was fairly simple. Is it impossible to insert into construction management contracts deadlines that require work to be completed within a schedule?
The point goes back to the nature of the construction management approach. A series of contracts is involved. In this case, we have a contract with Bovis, which is the construction manager, and separate contracts with the design team, the cost consultants and, crucially, a range of package contractors. There is no single contract, as there would be if we had a single contractor. Each contract contains terms and conditions for the delivery of its various parts, whether that means pouring concrete or providing professional advice. Where appropriate, timelines will be agreed with the individual trade package contractors, but that is not the case with consultants such as Bovis and EMBT/RMJM because the contracts with them that we inherited are for the provision of professional advice and other services.
I am grateful that Mr Grice has at least clarified that the trade package contracts contained deadlines. My question is fairly simple: have any of the trade contractors breached their deadlines and, if so, have they coughed up for any extra costs resultant therefrom?
The question goes back to a point that we have discussed a number of times with the committee, which is that the packages are complex and interrelated. Even in this meeting, Sarah Davidson has answered the question. If it can be shown that a trade package contractor has failed to perform and if that is the fault of the trade package contractor alone, it is clear that offset or the recovery of moneys would be pursued. If, as is more often the case, the failure to perform is the result of a much more complex set of circumstances, it is enormously difficult to prove that that is the fault of one trade package contractor.
The line of questioning is interesting and I am not convinced that we have discussed this specific issue before. Mr Grice, given that you have advised us that you and your colleagues are
Bovis's responsibility is to manage the whole contract on our behalf. The cost consultants' responsibility is to examine cost, which includes, as I said, the settlement of final accounts. The approach is not to look for failure, but to finish the building.
On a point of order, convener—
Can I answer the question please, Mr Ewing?
That is what I am hoping for. I asked a specific question.
I am attempting to answer your question. If you would do me the courtesy of allowing me to answer, that would be helpful.
You have already given us a written response on some of those issues.
I have indeed.
I seek more explanation from Sarah Davidson. When talking about possible methods of catching up with slippage, you mentioned incentivisation, which usually means overtime or extra money being spent somewhere. We talked earlier about the work force's morale; I can think of few things that would improve morale more than the prospect of a fair bit of overtime between now and March. Is there provision for such extra expenditure in the figures that you have given us today?
If overtime is used, it will be as part of a strategy for completion and not as a bung for workers.
I did not suggest that it would be a bung.
If overtime has to be used, it will not be as part of an incentive strategy, but as part of a completion strategy. That is an important distinction. The figures that have been reported to the committee in the past contain a contingency sum that includes—from memory—around £5 million that could be used for targeted acceleration. For example, in the past few weeks, Bovis found that too many workers were working in one place at the same time in Queensberry House, so a period of 24-hour working was adopted, which meant that people worked at different times during the day. That cost additional money, but the money had already been identified and set aside.
The ultimate bottom line with incentives is that there are usually extra costs somewhere along the line. You have identified around £5 million that might be available for that, but the cost could be higher.
Extra costs would not necessarily be involved; we might release retention moneys early rather than give additional money. Bovis is exploring those matters, but in a public sector atmosphere rather than in a commercial atmosphere, which means that any additional expenditure would have to be fully justified.
Migration has been mentioned in passing, but we have not spoken about how the planning for migration is going. If we assume that the crucial deadlines will be met and that the building will be ready in July, how confident are you that we will be ready to start operating from the beginning of September?
If we hit the deadlines that are set out in programme 7A, I am confident that we can migrate successfully. That means moving on to the site the entire parliamentary operation, including the technical systems, the data equipment and, crucially, the people who are required to support parliamentary work. The deadlines in programme 7A are for completion in June—one or two of them slip into July but, fundamentally, the buildings will be finished in June.
Has there been any shift in the anticipated cost of migration?
There has been no shift since I reported to you last.
What is the position on the building's rateable value?
Again, there has been no shift on that since we reported to the committee previously.
The previous Finance Committee raised the issue of the opening ceremony, but there was nothing on that in the SPCB budget. Can you give us any further information about anticipated costs?
I believe that there is something in the contingency for that. That is my understanding but, as I reported to you previously, no decisions have been made yet on the nature of the opening ceremony and therefore what the budget implications would be. I will check, and, if we have not included a sum for that in the contingency, I will write to make that clear. However, I am pretty confident that we have and I therefore do not expect any additional expenditure above the budget for 2004-05 to cope with an opening ceremony. Ultimately, decisions about the nature of the opening ceremony will be taken at a high level, and, if we need to revisit the matter, we will report back to the Finance Committee.
I hope that you will report back before hard and fast decisions are made.
There is money to cope with an opening ceremony in the general contingency—I will double check that and write back to you if I am wrong—so I do not expect at the moment that we will have to come back and ask for any more money in the global running costs to cope with it. If the position is different, I will write quickly to correct that statement. Also, if an opening ceremony that could not be afforded within that contingency was planned, I would take forward what you say about coming to the committee in good time.
I thank the witnesses for giving evidence this morning. I am sure that we will see them again.
I look forward to that with pleasure, convener.