In the meantime, we want to emphasise that the PAC could make a difference in the immediate future by including in its recommendations something on the following lines: 1) that HIE produce a revised budget for the funicular, by updating the full business case for the recent repairs, as approved by the Scottish Government, to take account of the need for increased monitoring and maintenance etc) and by being far more transparent about the assumptions/data on which it is based; b) that HIE also produce business cases for each of the various diversification projects in the pipeline alongside a business case for two new chairlifts in the lower half of Coire Cas (between the Day Lodge and Shieling and to replace the Day Lodge Poma) so the costs and potential benefits can be compared...