- Asked by: Laura Mitchell, MSP for Moray, Scottish National Party
-
Date lodged: Monday, 18 May 2026
-
Current Status:
Answered by Stephen Gethins on 29 May 2026
To ask the Scottish Government whether an environmental impact assessment will be required to be carried out by the developers of the proposed Moray FLOW-Park.
Answer
Yes. Scottish Ministers adopted and published on its website an Environmental Impact Assessment (EIA) screening opinion on 7 April 2026 which requires the project to undertake an EIA in line with relevant legislation.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 14 May 2026
-
Current Status:
Answered by Stephen Gethins on 29 May 2026
To ask the Scottish Government whether it will provide an update on its position on the proposed Moray FLOW-Park development.
Answer
On 7 April 2026, the Scottish Government adopted an Environmental Impact Assessment (EIA) screening opinion in relation to Moray Floating Offshore Wind (FLOW)-Park. This screening opinion requires that the project must undertake an EIA and comply with requirements set out in the Marine Works (Environmental Impact Assessment) (Scotland) Regulations 2017.
To date, no marine licence application has been submitted by Offshore Solutions Group for Moray FLOW-Park.
- Asked by: Stephen Kerr, MSP for Mid Scotland and Fife, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 26 May 2026
-
Current Status:
Answered by Jim Fairlie on 29 May 2026
To ask the Scottish Government what action it is taking to increase domestic food production, and reduce dependence on imported food, fertiliser and agricultural inputs.
Answer
The Scottish Government is absolutely committed to supporting active farming and sustainable food production through direct payments, regardless of choices made elsewhere. The 2026 payments strategy aims to maintain the recent years payment timings for Direct Payments and Scottish Rural Development Plan (SRDP) funding.
Scottish Ministers have committed in the Rural Support Plan to providing certainty, investment, and preparation through to 2030, delivering direct support to provide the industry with reassurance and boost confidence in long-term investment. Stability does not mean no change – we are committed to our ongoing programme of reform designed and delivered in partnership with our rural communities and valued stakeholders.
- Asked by: Mark Ruskell, MSP for Mid Scotland and Fife, Scottish Green Party
-
Date lodged: Tuesday, 26 May 2026
-
Current Status:
Answered by Gillian Martin on 29 May 2026
To ask the Scottish Government what legislative amendments are being made to establish a functioning Border Control Post that can enable freight to use the proposed Rosyth-Dunkirk ferry service.
Answer
I can confirm that the Scottish Government has recently amended the Minimum Requirements for the Location of a Border Control Post through The Official Controls (Location of Border Control Posts) (Scotland) Regulations 2026.
This amendment came into force on 21 March 2026. This amendment allows goods to arrive at a point of entry and then transit to an appropriately designated Border Control Post (BCP), provided that both the point of entry and the BCP are located within the same Scottish Green Freeport zone or within the outer boundary of that Freeport.
- Asked by: Kate Nevens, MSP for Edinburgh and Lothians East, Scottish Green Party
-
Date lodged: Wednesday, 20 May 2026
-
Current Status:
Answered by Gillian Martin on 29 May 2026
To ask the Scottish Government what guidance is available for local authorities when managing noise complaints as a public health issue.
Answer
The Guidance to Accompany the Statutory Nuisance Provisions of the Public Health etc (Scotland) Act 2008 is available on the Scottish Government website. This guidance was published to support local authorities investigate and manage issues relating to noise complaints. Should the noise complaint involve antisocial behaviours the Antisocial Behaviour etc. (Scotland) Act 2004: noise nuisance guidance is also available.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 15 May 2026
-
Current Status:
Answered by Ivan McKee on 28 May 2026
To ask the Scottish Government how many officials in the Energy Consents Unit are currently assigned to determining major electricity transmission infrastructure applications.
Answer
Scottish Ministers determine applications made under Section 37 of the Electricity Act 1989 for major electricity transmission infrastructure. The Energy Consents Unit administer these applications on their behalf and there are currently 14 officials directly undertaking this work.
- Asked by: Mark Ruskell, MSP for Mid Scotland and Fife, Scottish Green Party
-
Date lodged: Friday, 15 May 2026
-
Current Status:
Answered by Stephen Flynn on 28 May 2026
To ask the Scottish Government what progress has been made with the roll-out of 20mph speed limits on roads managed by Transport Scotland
Answer
The Scottish Government committed to implement 20mph speed limits on those roads where it is appropriate to do so across Scotland. Assessment criteria were prepared in conjunction with the Society of Chief Officers of Transportation in Scotland (SCOTS), Police Scotland, Transport Scotland and various local authorities to identify which roads can be considered as ‘appropriate’
A total of 104 locations were assessed by Transport Scotland for introduction of 20mph speed limits in line with the assessment criteria. Of the 104 locations, 75 were identified as being suitable for a 20mph speed limit. It has been agreed that implementation of one of the two sections of 20mph speed limit on the A78 in Greenock will be delayed until completion of major roadworks in the area.
Of the remaining 74 locations, all are currently operating with a 20mph speed limit in place.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 21 May 2026
-
Current Status:
Answered by Jim Fairlie on 28 May 2026
To ask the Scottish Government whether the Scottish Bracken Working Group has conducted any analysis on the growth of bracken following the decision not to authorise the use of Asulox in 2023.
Answer
The Scottish Government has pursued two approaches to assess Scottish bracken area since the HSE decision not to authorise the emergency use of Asulox in 2023. The first was to commission the creation of a Scottish bracken map to provide a baseline from which future changes in coverage can be assessed. The second was to conduct a survey of upland hill farmers, gathering information on current bracken coverage and impact, change over time and treatment. Both outputs are due to be published in summer 2026.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 21 May 2026
-
Current Status:
Answered by Jim Fairlie on 28 May 2026
To ask the Scottish Government whether it will provide an update on the status of the Scottish Bracken Mapping Project.
Answer
The last update was provided to the Rural Affairs and Islands Committee in late February 2026. An external contractor, funded by the Scottish Government, has completed the creation and validation of the Scottish Bracken Map and the project is now in the final stages of reporting, knowledge, and data transfer to Scottish Government geospatial analysts. The mapping layer is expected to be available for general use during summer 2026.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 21 May 2026
-
Current Status:
Answered by Jim Fairlie on 28 May 2026
To ask the Scottish Government when the Scottish Bracken Working Group will next meet, and how frequently it plans to meet during this parliamentary session.
Answer
The Scottish Bracken Working Group will next meet on the 22 June 2026. The frequency of the meetings varies; it is dependent on the actions being pursued and the need for input from the group as well as availability of members.