- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what assessment it has made of the suitability of GFG Alliance as the long-term owner of Scotland’s last plate mill, and what evidence underpins its position.
Answer
The Scottish Government is not responsible for the regulation of companies in the United Kingdom and does not have statutory powers to determine the suitability of owners of privately owned businesses.
- Asked by: Monica Lennon, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 21 September 2026
-
Current Status:
Answered by Siobhian Brown on 29 September 2026
To ask the Scottish Government what estimate it has made of the number of families with twins or other multiple births who are currently unable to access funded early learning and childcare for their children from the age of two solely because multiple-birth status is not an eligibility criterion, and what estimate it has made of the number of additional children who would become eligible if such a criterion was introduced.
Answer
As set out in answer to S7W-03483 on 29 September 2026, a definitive assessment of scope or costs of any new policy position has not been undertaken. Some limited consideration was given previously and released as part of a Freedom of Information request in May 2026. It can be found in the following document (document 33): FOI+202600511271+-+Information+Released+-+Attachment+3.pdf.
This included an estimate of the number of additional children who would become eligible although this was for illustrative purposes only.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what discussions it has had with the UK Government and British Steel regarding a secure supply of slab to Dalzell, and whether it considers reliance on imported slab from Kazakhstan to be a sustainable basis for the operation of Scotland’s last plate mill.
Answer
Liberty Steel Dalzell is a privately owned business and matters relating to the sourcing of feedstocks are the responsibility of the Directors.
- Asked by: Stephen Kerr, MSP for Mid Scotland and Fife, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 18 September 2026
-
Current Status:
Answered by Simita Kumar on 29 September 2026
To ask the Scottish Government when it expects the Anti-Racism Observatory for Scotland to become an established organisation.
Answer
The Anti-Racism Observatory for Scotland (AROS) is currently considering options for its long-term organisational model, ahead of the conclusion of the current hosting contract in December 2027. A decision on the preferred future arrangement is expected to be made in early 2027.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what estimate it has made of the economic impact on Motherwell, Cambuslang and the wider Lanarkshire supply chain should the Dalzell plate mill close permanently.
Answer
This government is committed to maintaining Scotland's domestic steel capacity and fully appreciates the economic importance of Dalzell to the local area. The priority of the Scottish Government is to see the plant operational.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 15 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what its position is on using public acquisition, a public-interest transfer or a joint vehicle with the UK Government to secure the long-term future of Dalzell Plate Mill in Motherwell, in light of reports that the UK Government will take British Steel and Speciality Steel UK into public ownership.
Answer
The Scottish Government has no plans to acquire the Dalzell plate mill.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what assessment it has made of Dalzell’s role in UK and Scottish defence, shipbuilding and infrastructure supply chains, and what discussions it has had with the UK Government regarding the designation of the mill as a public-interest steel asset under the Steel Industry (Nationalisation) Act 2026.
Answer
Scottish Government engages with the UK Government regularly on the steel industry. Our priority is to see the plant operational.
- Asked by: James Adams, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government how much of the £254 million that was committed under its 2016 Memorandum of Understanding with Aberdeenshire Council and Aberdeen City Council for additional investment in housing, transport and digital infrastructure in the Aberdeen City Region, has been spent to date.
Answer
To date, £51.8 million related to the Memorandum of Understanding has been spent. Future expenditure against the remaining commitment will be reported in the usual way.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what its response is to the ASLEF Dignity for Drivers Report 2024 regarding the lack of access to toilet facilities for train drivers.
Answer
I refer the member to the answer to question S6W-31539 on 6 December 2024. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 15 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what information it has regarding the current status of GFG Alliance’s consideration of a sale of Clydebridge, whether the site is being actively marketed, and whether it has discussed, or plans to discuss, any conditions related to environmental remediation, employment or future industrial use with any prospective purchaser.
Answer
Liberty Steel Dalzell is a privately owned business and issues relating to the potential sale of the Clydebridge site are matters for the company.