- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 30 July 2026
-
Current Status:
Answered by Stephen Gethins on 17 August 2026
To ask the Scottish Government what steps it is taking to ensure that local communities are consulted and given an opportunity to bid for leases on publicly owned land where existing wind farms are due to be repowered and the associated land leases are due for renewal.
Answer
In 2025, the Scottish Government and Forestry and Land Scotland (FLS) announced a pilot to give communities priority access to renewable energy assets on public land due for repowering.
The pilot provides a protected window for local groups to make an asset transfer request to lease FLS sites due for repowering and gives advance notification of upcoming lease opportunities so communities have time to prepare asset transfer requests before sites go to market.
These measures will apply to projects with a maximum generation capacity of 50MW, and ten FLS sites have been identified to be part of the pilot. Communities can access support to enable them to take up these opportunities through the Community and Renewable Energy Scheme (CARES).
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Friday, 17 July 2026
-
Current Status:
Answered by Stephen Gethins on 7 August 2026
To ask the Scottish Government whether it will set out the process by which the Strategic Spatial Energy Plan (SSEP), which it is co-sponsoring with the UK Government, will be approved, and when it expects that process to be concluded.
Answer
The process for the development and approval of the SSEP is set out in the Commissioning letter and the SSEP methodology both of which are publicly available. The decision on the initial pathway for the SSEP will be made by the Secretary of State in autumn 2026, following input from Scottish and Welsh Governments. The finalised Pathway Options Report prepared by NESO will be issued to UK, Scottish and Welsh Government at the end of August. It is expected that the chosen pathway will go out for public consultation in early 2027 with the final SSEP agreed in Autumn 2027.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 30 July 2026
-
Current Status:
Answer expected on 27 August 2026
To ask the Scottish Government what community consultation took place prior to the renewal of the lease for Whitelee Windfarm and whether any opportunities were provided for local community organisations to bid for the lease and, if so, what those opportunities were.
Answer
Answer expected on 27 August 2026
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 30 July 2026
-
Current Status:
Answer expected on 27 August 2026
To ask the Scottish Government what steps it is taking to ensure that opportunities for community ownership are maximised as part of the repowering of Whitelee Windfarm.
Answer
Answer expected on 27 August 2026
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 28 July 2026
To ask the Scottish Government what progress has been made in taking forward legislative options to allow the escorting of abnormal loads for onshore wind projects by an agency other than Police Scotland or Transport Scotland, and what timeline it is working to for bringing forward any such legislation.
Answer
The Scottish Government recognises the continued pressures facing Police Scotland’s ability to support abnormal load movement requirements for the energy industry and continues to meet regularly with Police Scotland and industry.
The escorting of abnormal loads often requires traffic to be stopped and directed and in Scotland such action can only be undertaken by police officers. The legislation which underpins this requirement is reserved to the UK Government.
The Scottish Government is working closely with the UK Government to identify workable solutions. However, any legislative change in this area would require action by Westminster.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Ivan McKee on 28 July 2026
To ask the Scottish Government what action it is taking to uphold the commitments of the 2023 Scottish Onshore Wind Sector Deal, including the 12-month and 24-month determination targets, and how many applications have (a) met and (b) missed these targets since the sector deal was agreed.
Answer
In recent years, the Energy Consents Unit (ECU) has undergone significant recruitment and training to bolster the workforce and match the rising demand in applications. In addition, the Planning and Infrastructure Act 2025 provided Scottish Ministers with new regulation-making powers that seek to streamline the consenting process. We will consult later this year on how we intend to use these powers, with findings informing secondary legislation. Taken together, these actions will help Ministers meet our ambitions for faster decision-making timescales of onshore wind applications.
The Onshore Wind Sector Deal included the ambition that from 2025 we would aim to determine section 36 applications for new sites and for the re-powering of existing operational sites within 12 months, or 24 months if there is a Public Local Inquiry (PLI). We remain committed to this ambition, ensuring that the energy consenting process delivers timely results and takes a pragmatic approach.
Between January 2025 and June 2026, the ECU received 46 onshore wind applications. By 14 July 2026, at the time of answering:
- none of these applications have been determined
- 27 applications can no longer meet the 12 month determination timescale
- 19 applications remain within 12 month determination timescale
- all applications still remain within the 24 month determination timescale (where a PLI may be required)
This summer, the ECU will publish an Annual Report for the first time which will include data and performance monitoring associated with their work. The report will provide further analysis relating to the factors which impact determination timescales.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 20 July 2026
To ask the Scottish Government what progress it has made towards its target of 20GW of operational onshore wind capacity by 2030, and what assessment it has made of whether current consenting rates are sufficient to meet that target.
Answer
As of the end of Q1 2026, there was 10.7GW of onshore wind installed capacity with an additional 5.9GW awaiting construction and 2.1GW under construction. This gives a total of 18.7GW consented onshore wind capacity across these categories. These figures are taken from publications released by the Department of Energy Security and Net Zero (DESNZ).
It is vital to note that achieving consent is only one of several factors that determine deliverability. Grid availability and a route to market through Contracts for Difference are key factors outwith the Scottish Government’s control.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 20 July 2026
To ask the Scottish Government what role it anticipates the repowering and extension of existing onshore wind sites will play in meeting its target of 20GW of operational onshore wind by 2030, and whether it plans to bring forward enhanced policy support for repowering.
Answer
The Scottish Government recognises the important role that repowering will play in delivering on our onshore wind ambitions.
Scotland’s long-standing support for onshore wind, sustained even when deployment elsewhere in Great Britain stalled, means that most initial repowering opportunities will be in Scotland.
We will continue to consider what additional measures might further support onshore wind deployment in Scotland, including repowering, as we work with industry to deliver our shared ambitions.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 20 July 2026
To ask the Scottish Government what engagement it has had with the UK Government and the National Energy System Operator to ensure that Scotland's onshore wind potential, including the role of future repowering and site extension capacity, is appropriately reflected in the Strategic Spatial Energy Plan.
Answer
The Scottish Government engages regularly with the UK Government and the National Energy System Operator on development of the Strategic Spatial Energy Plan (SSEP) through formal governance groups and bilateral meetings. Through that engagement the Scottish Government is seeking to ensure that Scotland’s onshore wind potential is appropriately reflected in the future SSEP.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 11 June 2026
-
Current Status:
Answered by Jenny Gilruth on 22 June 2026
To ask the Scottish Government which cabinet secretary is accountable for the delivery of the major infrastructure projects.
Answer
Each Cabinet Secretary is responsible for delivery of major infrastructure projects within their portfolio, with collective oversight through Cabinet to ensure alignment with the Scottish Government’s overall infrastructure priorities.