I welcome members of the press and public, and Mr Fergus Ewing and Ms Margo MacDonald, who have joined us for item 4.
The convener has laid out the background, but it is probably worth reminding people that the December meeting was out of sync, as it were, because it came when we were awaiting the outcome of the risk review and so were not able to be as precise as we would have liked to be about the current state of play.
I like the idea of being on the home straight of a coalface.
I appreciate those comments.
That is quite understandable.
The letter that we received spoke about the completion date of the project, and said that
I think that the boundary walls will not be completed, rather than the chamber walls.
The letter says that it is unlikely that the chamber walls and the boundary walls, which are two separate elements, will be complete by October.
Thank you. That is helpful.
You are saying that you are setting a target date between the end of August and the end of October, which is a fairly lengthy period. You are, however, suddenly able to move from that uncertainty to a position of confidence in which you can say that the whole shebang will be finished a month later. How, logically, does that work?
I will ask Sarah Davidson to deal with that. The project has many different elements, as you know.
The Parliament complex is made up of a number of buildings and progress on construction throughout the process has been from the west side to the east side. The project completion dates for the various parts of the complex have always been different. Therefore, the earliest parts of the complex that will be completed—the MSP block and Queensberry House—are intended to be entirely complete, to all intents and purposes, by late spring or early summer 2003.
About which bits is he not highly confident, if any?
He is highly confident about the dates that he has given us as completion dates for each part of the complex from the end of May until the end of November. In other words, we have for the completion of each part a date about which he is highly confident.
I do not want to put words in his mouth or in yours, but are you saying that he is highly confident about everything?
He is highly confident about the dates that he has given us. He is as confident that he can deliver the debating chamber and the boundary walls at the end of November as he is that he can deliver the MSP block four or five months earlier than that.
The building will be handed over in its entirety in November 2003, but we are also talking about the earliest completion date. Are the dates that you are talking about the same as the dates on which the buildings will be ready for occupation? If not, when will the buildings be ready for occupation?
The construction completion date is when Bovis Lend Lease (Scotland) Ltd and the other contractors will be finished on the site. The place will have to be fitted out and tested after that.
The decision that will have to be made at that point is how we, as an organisation, move into the building. We had some discussion about this the last time I came before the committee. Everything—the equipment and so on—will be in place, but there is the question of how long we want to test the set-up for. Furthermore, we need to think of a way in which we can move the Parliament down the road with the minimum of disruption to parliamentary business.
We will be at the same stage of completion as could be expected if we were moving to a new house.
I think so.
Many of the systems to which Paul Grice referred will have been installed by the construction handover date. The client and their specialist consultants have access prior to the handover date to enable them to install broadcasting systems, sound systems and so on. The contract includes carpeting the whole place, for example. Given that parts of the complex will be finished quite a bit earlier than the handover date, the Parliament might well decide to move furniture in. The client's involvement in making the building fit for their purpose does not start on the handover date. However, the process of moving people from the present site to Holyrood cannot begin until we have responsibility for the building.
Your most optimistic estimate for the earliest date at which occupation would be possible is January 2004.
That would be my judgment. Although it is possible that it could be done just before Christmas, there are many things to weigh up. We need to consider how fast we would be prepared to move, what the parliamentary business will be at that time and whether we would want to move over Christmas and the new year. A move at that time raises many issues. It would be feasible to move in by January 2004. Although we might be able to move in a bit sooner, we might decide, because of parliamentary business, that we want a few more weeks beyond that.
It would also be a mistake to give the impression that the building will be ready in November, given that, according to you, the earliest realistic date is Christmas.
I do not think that we have suggested that it will be ready by then.
The building will be fit to use only once it is kitted out and ready. The construction phase might well be complete by November—I will not dispute that—but I am concerned that the public might be misled by a suggestion that the building could be finished by October or November, even though it will not be ready for occupation until some time after that. Unless we give realistic dates and costs to the public, there will be further criticism. That is why I am asking questions.
I am equally concerned about the number of delays to the project, every one of which has been regretted. However, we should not move into the territory of ignoring the practicalities of life in such situations. Holyrood is a major complex. Our job is to determine when the building will be handed over to the parliamentary authorities and what they will do with it—that is what we are trying to establish.
I thought that I said that clearly in my introduction. I talked about construction and completion, as we have at recent meetings when that has been an issue. At our previous meeting, I explained in some detail the difference between the two, the gap of time and how that would be organised. There should be no public uncertainty.
In the interests of absolute clarity—there is still some uncertainty on our side about where we are at—I ask what the difference is between being "highly confident" and totally confident. What are the construction factors that your advisers have told you would make that difference? It is obvious that some uncertainty remains about the completion of construction. What variable might go off balance?
The central point is that we are past the major design and contract-letting risks, such as blast-proofing, with which we have had problems. The major risks are behind us. There are little risks, as with any project as it proceeds. For example, the weather might be horrible. All sorts of things might happen. The advice that we have is that the risks ahead of us are small and manageable and should not cause such difficulties as we had with earlier risks. Perhaps Sarah Davidson can give a flavour of the situation.
That is along the lines of what I would say. The process that we are following involves individual contractors either working through the final detailed design to get it ready for manufacture or, post-manufacture, addressing buildability and installation issues on site.
I asked simply what factors are causing that little bit of lack of confidence. The weather could be one, but in general terms, you are talking about construction. The blocks, brickwork and beams are in. Are you talking about the commissioning of what is to be installed, such as artwork and kitchens?
Commissioning is not causing delay. Certainly, co-ordinating the final services provision with the building is important. When commissioning starts in such a project, it is not unusual to find at this stage some places that do not have cabling exactly where it is needed, but those are little wrinkles, rather than big problems.
Are those wrinkles built into the dates that you have given?
They are things that Bovis fully expects to happen, so they are encompassed in the dates for completion.
Another issue is the consequential costs of not entering the building at the predicted time. We rent the present buildings for committee chambers, parliamentary headquarters and the debating chamber. Until when will that lease be kept? Do we know the precise dates or do you have a let-out clause?
We have sufficient flexibility on all the contracts to accommodate the situation.
What are the £900,000 of migration costs in the current financial year for? Does that represent rental?
The cost is principally in staffing and other matters. Clearly, we must put in an enormous effort. Something like 70 service contracts, for example, have to be let at Holyrood; we must re-let all our service contracts.
That cost is about £1 million. Is that for staff costs?
Yes; that has been our principal spending so far.
Therefore our staff, who may be temporary or contract—
All of those projects are co-ordinated by an implementation team that not only co-ordinates them, but links them to the building project. Of course, that has been quite a challenge. I have tried sometimes to release some of the experienced staff to help get projects right and backfill them, for example. In other cases we have kept the permanent staff on their existing jobs and brought in temporary staff—there has been a mixture. Sometimes it means drawing on contractors where we have call-off contracts to bring people in. We have done a range of things to give us the extra capacity to get over this hump of activity.
Do the builders move out at the end of November? Does the management of the building then move away to a large extent from the project management team that is building it? The management will then fall to you, because it is beginning to be run as the parliamentary complex.
That is a good way to express the situation.
Since December, an additional necessary £14 million has been identified as being required, of which £6.9 million relates to the increase in site running costs and fees. We have been told that the additional cost of running the site is about £100,000 a month. I presume that the bulk of the £6.9 million relates to fees. What are the total fees that are related to the project? What proportion of those costs go to the construction manager? Will the fees be restricted in the light of the criticism that Audit Scotland made about the construction manager in relation to Flour City?
I do not have a breakdown of fees to hand. We have given the global running total of fees to the committee in the past, and we can do so again.
Before the £6.9 million was mentioned, I recall that the total was £42 million. The increase in the running costs on the site is £100,000 a month, but not many months have been added; therefore, the bulk of that £6.9 million must be fees, unless there are other reasons.
It costs £600,000 a month to keep that site running.
It costs £600,000 a month? Even then, considering that there are still not many additional months, the bulk of the £6.9 million must be fees. In the light of the disappointment—I put that as mildly as I can—with the project management, it seems to me to be inappropriate that we reward failure by racking up the level of fees. What steps have been taken to restrict those fees, in particular in the light of the criticisms of the Auditor General for Scotland on the Flour City contract?
We are beginning to stray into areas on which I am reluctant to give detailed answers, particularly as we do not have the detailed figures available today. This is more of an audit issue for afterwards. The committee can rest assured that the Scottish Parliamentary Corporate Body, the progress group and our advisors are conscious of any legal issues that might arise from the project. They will do the necessary with regard to that, but it is not particularly helpful to pick over the bones of the project in the middle before we are actually finished with it, especially as we are trying to put the emphasis on finishing it and having everybody work together and all the rest of it.
It is reasonable for the committee to want to know what the fees are. It is a simple, straightforward question: what are the fees? Figures such as the £6.9 million have been packaged together for us, but I am asking you quite simply: how much of that figure is fees? How much of the £42 million on top of whatever proportion of the £6.9 million has gone to the construction manager? There is nothing inappropriate about that question, although I understand your reluctance to address any potential redress that you might seek from the construction manager. I also accept that you might not be able to answer the question at this point and that the Audit Committee might deal with the matter. However, the amount of money that is being paid to the construction manager in fees is relevant. You are accountable to the Parliament for spending the money and, as representatives of the public, we want to know how much you have spent on fees and, in particular, what the construction manager has received.
I believe that Ms Davidson said that she has already supplied those figures and that she is happy to update them. Will she do that at the earliest opportunity?
Yes.
I have a supplementary question, although I will perhaps not go down exactly the same route as Brian Adam did. The sentence in the letter of 16 January is technically simple—the £6.9 million is away. How many months of site running costs and what other elements are included in that £6.9 million?
When I get back to the committee with the global fee figure, I will confirm this, but I think that the six-month extension from May to November is included in the sum. The figure also includes two separate elements of fees, one of which is the fees that are payable under the individual agreements with each consultant. Those fees are constantly revisited with the consultants as the construction period lengthens and the construction cost increases—as the committee is aware, the fees are a percentage of the construction cost. The other element is fees for work done by consultants that is over and above the contractual work, which is time charged to the project. Sometimes architects or engineers do additional work that is not covered by the percentage fee agreement. I see no problem in breaking down that information and making it available to the committee when I come back with the global sum.
So the consultants get it both ways: if the price of the construction goes up, they get a percentage; and if they have to do extra work to justify whatever has caused the price to go up, they get more money for that, too.
That is the nature of the contract.
Okay, but I wanted to be clear about that—it is a win-win situation for the consultants.
As I understand it, the contract is not unusual. That is the normal way in which fees for architects and others are dealt with.
If the committee could suggest a way out of the situation, we would be interested.
I think that I joined the wrong profession.
Members might say that on an awful lot of occasions.
In the letter of 5 February, the second paragraph under the heading "Capital Expenditure" mentions
Will you clarify which letter you are talking about?
The letter from 5 February.
It is from 6 February.
No, it is from 5 February.
Who is it from?
David Steel.
The letter from David Steel is from 16 January.
The letter that I have is from 5 February. It is about the SPCB's financial performance for the six months to 30 September 2002.
That letter is the SPCB's monthly report, on which we are not taking evidence at the moment.
I was going to ask about technical issues. I understand why the landscaping money is not being spent—that is a result of delays in other contract work—but have there been any changes to the IT exercise?
I do not think that the witnesses are prepared for questions on that letter. As it is not on the agenda, it is not fair to ask the witnesses about it.
If David Davidson writes to me about why the technical refresh has slipped, I will be more than happy to respond—there are reasons for that.
My question was also about changes to costings as a result of the slippage.
If David Davidson lets me know in writing, I will be happy to give a full reply.
It is unfair to spring questions on witnesses when they have not had prior notice.
To clarify, the letter refers to increased underspends. The sentence states:
That is either because we are spending less in total, or because the cost has slipped into next year.
We are into the territory of saving money, now.
It is end-year flexibility.
We are not spending more, anyway.
The letter of 16 January states:
There has been no change in that budget.
So, it is still about £14 million.
Yes.
Ms MacDonald has been waiting for some time. I am sorry about that. Would you like to ask a question?
Do not worry, convener; it is always a pleasure.
Thank you very much. You have made my day.
I did not say that you were a pleasure; I said that it is always a pleasure.
In fairness to the witnesses, I do not think that anyone said that when somebody makes a mistake, they will get paid for putting it right. It was not expressed in that way. However, I leave it to the officials to answer the question.
I ask Paul Grice to deal with the first couple of points, and Sarah Davidson will pick up on the other ones.
I, personally, have not been negotiating with the Church of Scotland, but I have not made any approach to it suggesting that it will not have the assembly hall back for next May. I hope that that is helpful to you.
Bingo!
I am not quite sure what else you would expect.
The £7.8 million that has been identified for contingency is not envisaged as being required to deal with delays. The money that would be required for anticipated delays is allocated against individual packages. It would be too much to say that there is an expectation that that money will be spent, but it is anticipated that it will be required, given where the individual packages are at the moment.
However, it might be used for security if you have to stay there longer.
At the previous meeting on this issue in December, we did not have the benefit of the Auditor General's report. It was published separately at the end of last month and indicates his views on the Flour City matter. Some serious questions have to be asked, and I have given notice of them to Mr Grice and Ms Davidson. Indeed, I have had some correspondence with Mr Grice on the matter.
That is appreciated.
Paragraph 22 of the Auditor General's report says:
On a point of order, convener. I think that we are getting into very difficult territory here. I am not entirely convinced that the terms of Mr Ewing's questions are the immediate business of the Finance Committee as opposed to that of the Audit Committee. I request guidance on the extent to which the Finance Committee will seek answers to the sort of questions that Mr Ewing is asking.
I will hear what Mr Ewing has to say and come back to you before anyone has the chance to answer.
Thank you, convener. We are here today because the public are concerned about the cost of the Parliament building. My aim is to try to recover £4 million of that money and to cut costs by that amount. I believe that mistakes were made that have resulted in the Parliament incurring an additional liability that is currently estimated at £3.85 million. I want that money to be recovered for the taxpayer. Mistakes are made by individuals—by me and by everyone else in the room. This is not a witch hunt or an exercise in seeking scalps. Instead, it is an exercise in recovering £4 million for the Scottish taxpayer, which is something that the Finance Committee is very directly concerned with.
Before Mr Grice and Ms Davidson answer that, will they confirm whether they have received any legal advice on whether discussing such matters at this time would prejudice the Parliament's position in any recovery action that might be under way or that might take place in the future?
To be honest, we are in an awkward position. Robert Brown gave the committee an important assurance. I entirely respect Fergus Ewing's motives. Nobody would be happier than the corporate body or I would be to recover any moneys that are missing—Fergus Ewing is not the only person who would be happy about that. Indeed, the corporate body has a duty and a responsibility in that respect and we will pursue that duty where we can.
I am in the same position as you are, Mr Grice. I do not have a lawyer at my shoulder either, and I would prefer to adopt the precautionary principle. However, the information that is sought should be in the public domain at some point. You have been asked a perfectly legitimate question. The issue is whether this is the right time to ask it. Can you assure the committee that you fully expect that we will reach a point at which the answers to Mr Ewing's question can be given and can be placed in the public domain?
The issue is really about timing and the appropriate way of dealing with the matter. Mr Ewing has made a number of stark observations and has asked questions that need to be looked into. However, if I may say so, I think that they would be most satisfactorily looked into in retrospect, through the Parliament's audit procedures, rather than in the Finance Committee.
So you expect that information will be provided at some point that can answer Mr Ewing's questions.
Absolutely. I am certain that people will be crawling all over the project in great detail when it is finished—there are no two ways about that.
That includes us.
Absolutely.
I do not swallow the argument that we should not consider anything retrospectively and that we should only consider future matters, which seems to be what Robert Brown suggests. The Auditor General's report is already in the public domain, so if any legal action were to be prejudiced by the information, it has already been prejudiced. Can we give Mr Ewing a chance to rephrase his questions in such a way that the respondents might feel that their answers would not prejudice the outcome of any legal action?
That might be helpful to the committee. As Mr Ewing will acknowledge, he has lodged a large number of parliamentary questions on the matter and has written to the Presiding Officer and others. We have attempted to answer an awful lot of questions and have put an awful lot of information in the public domain. Mr Ewing had the good courtesy to write to me at the end of last week with two or three of his points. We will of course endeavour to answer anything that can be answered at this stage.
I will clarify the audit process. As deputy convener of the Audit Committee, I discussed yesterday with that committee's convener its likely role in the Parliament project. We both came to the view that we had to see the building completed and accounts produced. However, we felt that the Audit Committee would not be tied merely to examining the numbers, but would also examine the management of the project—the outcomes and governance.
Thank you very much.
We are discussing a public document that the Auditor General published. I believe that it is unusual for the Auditor General to publish a separate report, but he did so under section 22 of the Public Finance and Accountability (Scotland) Act 2000. As Mr Morgan says, the information comprises not allegations that I am making, but the Auditor General's findings of fact in a carefully produced report.
I do not think that I want an answer to that question at the moment. It might cause prejudice. I do not think that the question is appropriate.
I will move on to another question then, if I may.
You are in danger of some kind of double standard, Mr Ewing. You have made it clear that you are keen to pursue some sort of recovery from people who have defaulted on the project. The very nature of pursuing that recovery will incur other expenditure. You are also a member of the legal profession and know that it is usually fairly expensive. You are in danger of facing both ways at once.
It is the first time that we have had free legal advice.
I never charged £44,000 for not recovering a debt. I might charge £100. The point is fairly serious. Why have we spent all that money and not raised a court action? Perhaps Mr Brown can tell us why a court action has not been raised. We have had advice from Shepherd and Wedderburn, and their American agents. Will there be a court action or not?
I am sorry to be difficult—I do not want to appear to be unhelpful in any sense of the word. As Mr Ewing is well aware, the corporate body has taken legal advice on the matter, is continuing to take legal advice and will pursue such remedies as are possible. That is really all I am prepared to say on the matter at this time.
I do not consider that you have been in any way unreasonable, Mr Brown.
I will raise one final point and then stop, because this is the final opportunity we have in the session to pursue these matters.
Mr Ewing, you are making the same point. I have already said that I do not expect the people giving evidence to answer that.
I am not a lawyer but I recall telling the project group right at the outset that Flour City did not have any money so why not just go after Bovis. I think that you will find that in the Official Report.
We are not in the business of steps for a hint, but it would be appropriate for Mr Brown to assure us that where there is such a facility, the matter will be pursued vigorously.
The relationship between the various contractors, the construction manager, the client and others is hugely complex. We are taking all steps to minimise the cost of the building and to recover if there are legitimate claims open to us. That is common to building contracts generally. I hope that it does not need to be said that that is being done; it is being done.
I hope that the convener will indulge me in one final question about finance, as this is the last meeting on the subject. I assume that the modifications to the original design will impact on the operation of the working building. For example, very little light now enters through the wee windows of the MSP offices. I am informed that artificial light rather than daylight will now provide the bulk of the lighting. Have that and other design and construction changes had a measurable impact on the anticipated maintenance and running costs for the project?
It is my understanding that the balance of natural and artificial light has not changed in the MSPs' rooms. It was always envisaged that there would be a lot of natural light. In fact, from memory, a lot of natural light comes in, not through those windows but from the glazed corridor on the other side.
I return to a couple of points that were made at the beginning of the session, because they could be misinterpreted, and we run a slight risk of suggesting that the new building will not be ready until some time into the new year. There are risks—the weather is a factor; the site is crowded, with about 1,000 people working on it; and the interfaces between different buildings, trades and contractors could cause problems. However, it is important to reiterate that both the Holyrood progress group and the SPCB have interrogated the construction manager closely and he has reported that, notwithstanding those risks, he has a high expectation—indeed, he is confident—that the building will be handed over, carpets down and paint dry, ready to begin the migration process in November.
I do not think that the committee is of the view that there has been any material change to the information that was supplied previously.
It is also open to members of the Finance Committee to have a look round the building before the end of the parliamentary session, if they want to see what they are getting for the committee's money.
It is the taxpayers' money, of course.
We very much want to take up that invitation. Thank you for extending it, and for attending this afternoon.
Previous
Outcome BudgetingNext
Invitation