To ask the Scottish Executive, further to the ministerial statement on 26 June 2002 by the Minister for Finance and Public Services on budget revision, Official Report, col. 13041, which road schemes in 2001-02 were delayed by the impact of the foot-and-mouth disease outbreak; by how long, and with what resultant budget carry forward in each case. The following table shows which road schemes were delayed by the impact of the foot-and-mouth disease outbreak, by how long and the resultant budget carry forward in each case:Name of schemeThe length of delay (approx.)Budget carry forward£ million (approx.)A1 Bowerhouse-Spott3 months0.050A1 Haddington-Dunbar3 months3.000A1 Howburn-Houndwood6 months3.120A75 Cairntop-Barlae3 months0.028A8 Baillieston-Newhouse3 months0.225M77 Fenwick-Malletsheugh3 months0.550A90 Glendoick2 months0.033A90 Inchmichael3 months0.156A90 Inchture3 months0.320A90 Kinfauns2 months0.043Total S1W-27159