Retrieved from <a href="https://www.gov.scot/binaries/content/documents/govscot/publications/progress-report/2020/08/ferguson-marine-vessel-programme-progress-report-august-2020/documents/ferguson-marine-vessel-programme-update---august-2020/ferguson-marine-vessel-programme-update---august-2020/govscot%3Adocument/Ferguson%2BMarine%2Bvessel%2Bprogramme%2B-%2Bprogress%2Breport%2B-%2BAugust%2B2020.pdf" target="_blank">https://www.gov.scot/binaries/content/documents/govscot/publications/progress-report/2020/08/ferguson-marine-vessel-programme-progress-report-august-2020/documents/ferguson-marine-vessel-programme-update---august-2020/ferguson-marine-vessel-programme-update---august-2020/govscot%3Adocument/Ferguson%2BMarine%2Bvessel%2Bprogramme%2B-%2Bprogress%2Breport%2B-%2BAugust%2B2020.pdf</a>
Assuming no further increase in costs or slippage in delivery dates:
Compared to an original fixed price budget of £97 million, this takes the total estimated cost for the design and build of vessels 801 and 802 to between £192.8 million and £196.8 million;
Compared to the original contractually agreed delivery dates for the vessels, delivery of vessel 801 will have been delayed by between 47 and 49 months and delivery of vessel 802 will have been delayed by between 53 and 55 months.