JirFERGUSON , martnE Following my appointment, the team has now determined a more focussed approach to the completion of the vessel, separately identifying four critical elements as follows • Completion of all activities not affected by LNG, by the start of May 2024; • Completion of installation of LNG systems, by the start of May 2024; • and Completion of LNG system 'set to work', by mid to end of July 2024; • Sign off the vessel by MCA and Lloyds, by the end of July 2024. st So, to confirm, our targeted date for handover to CMAL is now 31 July 2024. appreciate and fully understand that there will be disappointment in all quarters, and particularly in We Arran, for this further delay.