The Committee seeks detail of— • A detailed explanation of the tender process; • The criteria used to select the winning bid, including the weight attached to each criteria; • The process for developing, confirming and signing off the design of the ferries, including engagement with relevant parties such as local communities and operational staff, and how their contributions impacted the final design; • Overall cost agreed at the outset for each ship and an overview of the staged payment process, including how many payments are due to be made, the amount of each payment, the criteria that must be met before a payment is released, who is responsible for checking the work completed before a payment is made and the process for resolving any dispute between CMAL and the shipyard about the release of a staged payments; • Dates...