Construction of the final section to beupgraded, from Arisaig to Loch nan Uamh, will begin this summer and is due to becompleted in 2008.Records of the constructioncosts of the earlier schemes are no longer kept, but for those sections forwhich records are still held, the cost of upgrading the road in 2006 prices isas follows: Scheme Length (Km) Year of Completion Actual Cost (£ Million) Cost at 2006 Prices (£ Million) Mallaig-Kinsadel 2.3 1988 4.8 8.6 Polnish-Lochailort 1.7 1988 3.6 6.4 Lochan Doilead-Kinsadel (Morar Bypass) 3.0 1994 9.0 12.2 Loch nan Uamh-Polnish Bridge 3.3 1998 6.0 7.3 Kinsadel-Arisaig 7.0 2003 11.6 12.5 Arisaig-Loch nan Uamh 7.0 2008* 19.4* 18.4* Totals 54.4 65.4 Note:*Estimated costs andcompletion date.Transport Scotland...