Onshore proposals over 50MW:Onshore wind – 33 monthsBattery Energy Storage System (BESS) – 14 monthsHybrid (Solar and BESS) – 13 monthsHydro – 18 monthsOffshore proposals:Offshore wind - 11 monthsWave & Tidal - 24 months It should be noted that these timeframes include the time taken for Public Local Inquiries, should they be necessary, and also any delays caused by missing or additional application information being required from developers, such as that under EIA legislation. S6W...