Questions and Answers Date answered: 26 March 2020

S5W-28074

There has been some speculation around a potential delay to the launch date as a result of legislation laid before the Scottish Parliament on 20 March 2020.
Questions and Answers Date answered: 2 May 2019

S5W-22749

We are also working with the UK Government on necessary changes to UK legislation. No date is set for restitution orders becoming operational.
Questions and Answers Date answered: 22 January 2019

S5W-20875

To ask the Scottish Government, further to the answer to question S5W-20597 by Humza Yousaf on 7 January 2019, whether it will confirm when in 2017 the then justice secretary confirmed that a phased approach would be taken in respect of the five community custody units, and by what date it expects each unit to be fully (a) planned and (b) operational.
Questions and Answers Date answered: 20 December 2018

S5W-20701

We cannot and will not contemplate releasing payments for this structure without these critical assurances. In terms of an opening date for this section, although ARL are forecasting January 2019, they have been unable to provide a definitive date.
Questions and Answers Date answered: 26 November 2018

S5W-19888

As Cabinet Secretary for Culture, Tourism and External Affairs, I chaired meetings of the group on 3 October and 14 November 2018 and no date has yet been set for publication.
Questions and Answers Date answered: 22 November 2018

S5W-19798

Neither my officials nor I have received any correspondence dated 23 October 2018. As confirmed in my statement, I was disappointed to receive a letter from Peter Truscott, CEO of Galliford Try, on 31 October 2018, suggesting Aberdeen Roads Limited (ARL) had yet to agree with its lenders the contractual variation.
Questions and Answers Date answered: 12 June 2018

S5W-16952

When it became clear that provisional dates for these events would not achieve that aim, JPB partners took a collective decision to seek alternatives.
Questions and Answers Date answered: 12 April 2018

S5W-15548

Following discussion, on 8 March, with sector representatives which included FPS, there was agreement that there would be a relaxation on the date for the submission of Asset Improvement Plans from the previously stated 9 months to 12 months from the date of issue of the licence.
Questions and Answers Date answered: 28 February 2018

S5W-14301

Network Rail has therefore confirmed that the a) cost and b) scheduled completion date of the i) the remaining platform extension works and ii) the platform 10 & 11 crossover commissioning at Waverley station remain under commercial review.
Questions and Answers Date answered: 3 January 2018

S5W-13518

We are currently engaging with local partners, as well as young people, to develop the detail of the Grant and we will announce a date for implementation in due course.