There will be additional workforce shift patterns added to assist with schedule compliance, and to deliver to the previously advised date of end September 2025. After the delivery of Glen Sannox a week long “lessons learned” exercise will be scheduled with key personnel from all three sides of the triangle (FMPG, CMAL and CalMac) will be in attendance.