Inability to secure grid capacity for a connection this decade adds significant risk to the development progress of a project and may delay investment decisions Example 1: A 100MW project in Argyll, which was recently submitted for planning, has received a new grid offer with a 2034 connection date, due to the need for a new subsea interconnector to North Wales.