. • The installation of the silencers commenced on 24 June 2025, which will be followed by the installation of the funnel tops in time for dry dock. • The dry dock scope has been finalised for 17 July 2025, with numbers now agreed with Dales Marine. • Our contractor (TTS) has been on site carrying out preliminary works for the mezzanine deck wire installati...