A decision from Transport Scotland torelease funds is expected shortly.A breakdown from thePromoter of the forecasted £32.7 million spend can be summarised as followed:Pre-Construction Costs(April 2006 to December 2006) (£ Million) Project management costs £3.2 Design, modelling, technical support services, early operator involvement £16.24 Legal, financial, communications, marketing and service integration planning costs £2.9 Utilities diversion preparation* £6.26 Land and property, insurance, other £1.09 Contingency (10%) £2.97 Total £32.7 Note: *Includes a refundable£5million deposit.