At that point, the cost consultant indicated that when he saw the new programme, he would have to look again at the remaining risk moneys to assess whether they would be sufficient to meet all that would be required to deliver the new programme.Because of delays, the programme was not produced until 7 May, which was when the cost consultant's review process began.