- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 28 July 2026
-
Current Status:
Answered by Neil Gray on 24 August 2026
To ask the Scottish Government whether the ALLIANCE provided a report on the consultation events held by the Scottish Fire and Rescue Service as part of its Strategic Services Review Programme, including a report on the Helensburgh consultation event.
Answer
ALLIANCE compiled a report of all the public meetings their staff facilitated as part of the Scottish Fire and Rescue Service, Service Delivery Review (SDR) public consultation.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 28 July 2026
-
Current Status:
Answered by Maree Todd on 24 August 2026
To ask the Scottish Government, further to the answer to question S7W-00815 by Maree Todd on 16 June 2026, what the timetable is for bringing bowel screening in line with the UK NSC recommendations.
Answer
S7W-00815 refers to prostate cancer screening. Information on both bowel and prostate cancer screening is set out below.
Since 2009, Scotland has offered bowel screening in line with the current UK National Screening Committee (UK NSC) recommendations; screening is offered every two years to people aged between 50 and 74. Those aged 75 and over can also request a kit every two years. In July 2026, the Scottish Government submitted a proposal to the UK NSC to review their recommended age range, highlighting that the number of bowel cancers are increasing in those under the age of 50.
As noted in the answer to S7W-00815, our initial focus is on strengthening existing high-risk surveillance pathways for prostate cancer, which already allow eligible men to access testing in line with the UK NSC recommendation. This work will progress at pace, and will be completed ahead of any implementation of a national screening programme, which will require a number of formal processes to be developed, including a dedicated IT system.
To support both pieces of work, we have established a multi-disciplinary Prostate Cancer Screening Working Group (PCSWG).
- Asked by: Lorna Slater, MSP for Edinburgh Central, Scottish Green Party
-
Date lodged: Monday, 10 August 2026
-
Current Status:
Answered by Stephen Flynn on 24 August 2026
To ask the Scottish Government, in light of the UK Government’s update to the National Transport Strategy, Better Connected, which included a commitment to update the Traffic Signs Regulations and General Directions 2016, whether it will consider issuing guidance to allow Scottish local authorities to install ‘paint only’ side road zebra crossings to improve safety of walking and wheeling, following the example of guidance issued by the Welsh Government in April 2026.
Answer
Transport Scotland officials are engaging with UK Department for Transport regarding potential amendments to the Traffic Signs Regulations and General Directions 2016, including the introduction of simple ‘paint only’ side road zebra crossings. These crossings have been subject to associated trials on their effectiveness and safety. Transport Scotland will consider the published trial findings when available.
Should it be established that side road zebra crossings are appropriate for use in Scotland, their incorporation in Traffic Signs Regulations and General Directions 2016 as it applies in Scotland is intended. In this case, it is anticipated that Transport Scotland would also direct roads authorities and designers to suitable guidance on their use.
- Asked by: Lorna Slater, MSP for Edinburgh Central, Scottish Green Party
-
Date lodged: Monday, 10 August 2026
-
Current Status:
Answered by Stephen Flynn on 24 August 2026
To ask the Scottish Government in light of the UK Government’s response to Wendy Chamberlain UIN 469 tabled on 13 May 2026, whether (a) it intends to bring forward amendments to the Traffic Signs Regulations and General Directions 2016, and (b), if so, what amendments it is considering
Answer
Transport Scotland officials are engaging with UK Department for Transport regarding its proposed amendments to the UK Traffic Signs Regulations and General Directions 2016, including side road zebra crossings as noted in the UK Government’s response to Wendy Chamberlain MP, UIN 469.
Should it be established that side road zebra crossings are appropriate for use in Scotland, their incorporation in Traffic Signs Regulations and General Directions 2016 as it applies in Scotland is intended. Scottish Ministers are yet to determine what other amendments will be progressed. Any amendments would be subject to consultation.
- Asked by: Jamie Langan, MSP for South Scotland, Reform UK
-
Date lodged: Friday, 07 August 2026
-
Current Status:
Answered by Stephen Gethins on 24 August 2026
To ask the Scottish Government what assessment it has made of recent YouGov polling conducted on behalf of the Nuclear Industry Association which reportedly found that a higher percentage of people in Scotland identify nuclear power generation as the most important energy source for maintaining a reliable electricity supply than offshore wind or solar.
Answer
The Scottish Government does not support the building of new nuclear power stations under current technologies. New nuclear is expensive, slow to deliver and generates radioactive waste which can remain dangerous for thousands of years.
We are working to deliver a resilient, affordable and clean energy system for the people of Scotland. Scotland’s renewable resource, supported by storage, flexibility and grid investment, offers the quickest route to achieving this.
- Asked by: Michelle Campbell, MSP for Renfrewshire North and Cardonald, Scottish National Party
-
Date lodged: Friday, 07 August 2026
-
Current Status:
Answered by Stephen Flynn on 24 August 2026
To ask the Scottish Government how many (a) young people have now received a free bus pass through the Young Persons’ (under 22s) Free Bus Travel scheme and (b) journeys have been made through the scheme, broken down by local authority area.
Answer
a) As from 1 August 2026 there are 842,653 cardholders under the Young Persons’ Free Bus Travel Scheme.
Cardholder Notes:
- This data is provided by the National Entitlement Card Programme Office (NECPO). Cardholder numbers are monitored on a monthly basis and may change regularly as individuals join or leave the scheme.
- The data refers to the number of people with a valid card but does not include those whose products either start in the future or have expired.
- NECPO work with stakeholders and partners to carry out regular data cleansing of the customer database which may impact cardholder numbers when records are updated.
b) The following table shows the number of journeys, broken down by local authority, made through the Young Persons’ Free Bus Travel Scheme since its launch in January 2022 up to 31 July 2026.
Local Authority | Total Journeys to 31-07-26 |
Aberdeen City | 18,282,458 |
Aberdeenshire | 9,119,538 |
Angus Council | 4,508,794 |
Argyll & Bute | 2,530,080 |
City of Edinburgh | 65,926,253 |
Clackmannanshire | 1,625,339 |
Comhairle nan Eilean Siar | 470,317 |
Dumfries and Galloway | 4,292,052 |
Dundee City | 14,067,594 |
East Ayrshire | 7,687,318 |
East Dunbartonshire | 4,353,470 |
East Lothian | 9,099,489 |
East Renfrewshire | 4,269,986 |
Falkirk | 4,926,865 |
Fife | 25,633,202 |
Glasgow City | 44,092,163 |
Highland | 6,858,745 |
Inverclyde | 4,692,192 |
Midlothian | 8,391,007 |
Moray | 2,678,626 |
North Ayrshire | 8,630,110 |
North Lanarkshire | 13,354,704 |
Orkney Islands | 462,415 |
Perth & Kinross | 7,300,827 |
Renfrewshire | 10,789,067 |
Scottish Borders | 4,247,320 |
Shetland Islands | 839,419 |
South Ayrshire | 4,556,917 |
South Lanarkshire | 12,422,053 |
Stirling | 4,105,110 |
West Dunbartonshire | 5,574,398 |
West Lothian | 7,718,924 |
Total to 31st July 2026 | 323,506,752 |
Journey Notes:
- These figures represent smart journeys recorded against a valid product that have been received and processed for payment by Transport Scotland.
- Journeys are based on the local authority in which the card was issued, therefore some journeys will have been undertaken out with the local authority area.
- This data is subject to change due to late data being received.
- Asked by: Ross Greer, MSP for West Scotland, Scottish Green Party
-
Submitting member has a registered interest.
-
Date lodged: Friday, 07 August 2026
-
Current Status:
Answered by Stephen Flynn on 24 August 2026
To ask the Scottish Government, further to the response to question S6W-35719, what engagement has taken place in the last two years in the Bearsden and Milngavie area with "Local Authorities, Regional Transport Partnerships, Housing Developers and the wider Business community to understand current and future markets which may inform varying the frequency of rail services."
Answer
This is a matter for ScotRail, as the train operator. The member may wish to contact ScotRail directly to request this information.
- Asked by: Russell Findlay, MSP for West Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 03 August 2026
-
Current Status:
Answered by Stephen Flynn on 24 August 2026
To ask the Scottish Government, regarding the £200,000 provided by Sustrans for the proposed Neilston to Uplawmoor link, whether it will provide a breakdown of how those funds were spent and whether any consideration has been given to recovering or repurposing them following the project's termination.
Answer
The total claimed from Sustrans through the Transport Scotland funded Places for Everyone Fund for the Neilston to Uplawmoor link was £199,274, of which £28,932 was claimed for Royal Institute of British Architects (RIBA) Plan of Work stages 0-2 and £170,342 for stages 3-4.
No consideration has been given to recovering or repurposing the funding, as the £199,274 provided was expended for the purposes for which it was awarded, namely development and design work associated with the proposed Neilston to Uplawmoor link.
- Asked by: Russell Findlay, MSP for West Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 03 August 2026
-
Current Status:
Answered by Stephen Flynn on 24 August 2026
To ask the Scottish Government, regarding the proposed Neilston-Uplawmoor link, for what reason Transport Scotland has decided not to provide additional support to the project.
Answer
The Active Travel Infrastructure Fund (ATIF) is the primary vehicle for the Scottish Government to fund active travel infrastructure. The tiered model for infrastructure delivery increases flexibility and control for partners to meet the active travel needs and priorities of people living and working in their communities. Tier 1 of the Fund is provided directly to Local Authorities through their General Capital Grant and they have the flexibility to use the funding as required. Tier 2 funding, directly managed by Transport Scotland, was open to applications from Local Authorities, Regional Transport Partnerships and National Park Authorities for the funding of larger scale projects most recently at the start of the calendar year 2026. Transport Scotland did not receive an application from East Renfrewshire Council nor Strathclyde Partnership for Transport for this project.
- Asked by: Kayleigh Kinross-O'Neill, MSP for Edinburgh and Lothians East, Scottish Green Party
-
Date lodged: Wednesday, 05 August 2026
-
Current Status:
Answered by Ivan McKee on 24 August 2026
To ask the Scottish Government what proportion of electricity generated by Berwick Bank offshore windfarm is expected to be (a) exported outwith Scotland and (b) purchased by data centres, such as the proposed QTS data centre at Cambois, Northumberland, where Berwick Bank offshore windfarm is planned to connect to the grid.
Answer
The Berwick Bank offshore wind farm consent and marine licences, granted in July 2025, included export cables to a grid connection point at Branxton, located south-west of Torness Power Station. Following the National Grid Electricity Systems Operator (NGESO) Holistic Network Review in 2022, an additional grid connection at Blyth, Northumberland (referred to as the Cambois connection) was also identified and a separate marine licence application was submitted by SSE Renewables and a marine licence granted in August 2025. No further information was provided through the Section 36/marine licence application process as to the onward use of electricity once exported to the grid.