- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Tuesday, 11 August 2026
-
Current Status:
Answered by Stephen Flynn on 8 September 2026
To ask the Scottish Government when its planned Major Projects Office will begin work and which Cabinet Secretary will have lead responsibility for the office.
Answer
Our Major Projects Office will be designed to accelerate progress on nationally and strategically significant investment and private capital projects, unblocking barriers to project delivery and unlocking private investment across strategic sectors including housing and energy. It will help contribute to a transformational change in economic performance across Scotland by unlocking significant strategic developments across Scotland to bring jobs and economic growth.
It will begin to be operationalised by the end of 2026, with work underway to developing its remit, governance arrangements, and operating model. Ministerial responsibility for the Major Projects Office will be in the Economy, Tourism and Transport portfolio.
- Asked by: Finlay Carson, MSP for Galloway and West Dumfries, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 11 August 2026
-
Current Status:
Answered by Angela Constance on 8 September 2026
To ask the Scottish Government whether it has undertaken any assessment of the impact of the Vision 3 GP clinical system on GP appointment capacity and, if so, what the findings were.
Answer
The Scottish Government has not undertaken an assessment of the impact of the Vision 3 GP clinical system on GP appointment capacity.
Responsibility for the delivery and operation of GP IT systems, including the Vision 3 migration programme, sits with Public Services Delivery Scotland (PSDS), which manages the national GP IT service on behalf of NHS Scotland.
Public Services Delivery Scotland has advised that some short-term disruption to practices has been reported following migration. In response, a number of enhancements to post-migration support arrangements have been implemented in conjunction with OneAdvanced to support practices during their transition to the Vision 3 system.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 24 August 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 8 September 2026
To ask the Scottish Government what its position is on the enforcement of National Planning Framework 4 (NPF4) Policy 7 (Historic assets and places), specifically in circumstances where a developer cites private commercial targets, such as a 20% Profit on Cost (PoC) margin, as the primary justification for the demolition of a listed building rather than structural impossibility.
Answer
NPF4 forms part of the development plan and should be taken into account in planning decision making. It is for the decision-maker, normally local authorities, to interpret and apply policy 7 and other relevant policies, making decisions in accordance with the development plan unless material considerations indicate otherwise. Applications are considered on individual merits.
- Asked by: Adam Harley, MSP for Strathkelvin and Bearsden, Scottish Liberal Democrats
-
Date lodged: Thursday, 20 August 2026
-
Current Status:
Answered by Neil Gray on 8 September 2026
To ask the Scottish Government on how many occasions (a) nitazenes and (b) other synthetic opioids were discovered in Scotland in each of the last five years.
Answer
The Scottish Government does not hold data relating to seizures of nitazenes and other synthetic opioids. This data is held by Police Scotland.
The Scottish Government supports the activity by Police Scotland and other partners on the Serious Organised Crime Taskforce to remove illicit drugs from our communities and reduce the harm they cause.
- Asked by: Mark Ruskell, MSP for Mid Scotland and Fife, Scottish Green Party
-
Date lodged: Monday, 10 August 2026
-
Current Status:
Answered by Stephen Gethins on 8 September 2026
To ask the Scottish Government, in relation to its consultation on the Draft Energy Efficiency (Domestic Private Rented Property) (Scotland) Regulations, which closed on 29 August 2025, when it will publish the responses received.
Answer
Due to delays to the UK Government’s implementation timeline for Energy Performance Certificate (EPC) reform in England and Wales, the former Cabinet Secretary for Housing confirmed to the Local Government, Housing and Planning Committee on 9 March 2026 that, due to the impact of this delay on introducing EPC reform in Scotland, it would not be appropriate to lay the Private Rented Sector (PRS) Minimum Energy Efficiency Standards (MEES) regulations during that session of Parliament. The delay would impact landlords’ ability to obtain an EPC certificate which accurately reflects the new Heat Retention Rating. This letter can be found: https://www.parliament.scot/-/media/files/committees/local-gov/correspondence/2026/epc-reform-and-energy-efficiency-standards_cab-sec-housing-to-lghp_9-march-2026.pdf
The Scottish Government has now laid the draft Energy Performance of Buildings (Scotland) Amendment Regulations 2026 before Parliament, which, if agreed, would see reformed EPCs introduced from April 2028. This new date reflects the UK Government’s revised timeline for EPC reform, to allow time for the roll-out of, and assessor training in, the new Home Energy Model, to be finalised during the second half of 2027. We will confirm the next steps to Parliament as soon as possible on our approach to the PRS MEES regulations.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 24 August 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 8 September 2026
To ask the Scottish Government what constitutes "adequate marketing" under Historic Environment Scotland’s guidelines before a listed building can be demolished on the grounds that its retention is not economically viable; and whether it considers a failure to actively market a site for facade retention or alternative development models for several years as meeting this evidentiary threshold.
Answer
Interpretation and application of Historic Environment Scotland’s non-statutory guidance is a matter for Historic Environment Scotland. Decisions on whether sufficient evidence has been provided in support of an application, including evidence relating to marketing and economic viability, are considered on a case-by-case basis by the decision maker having regard to the circumstances of the application.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 24 August 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 8 September 2026
To ask the Scottish Government what criteria it uses to determine when the proposed demolition of a listed building transitions from a localised planning dispute to a "significant issue for planning policy" warranting a ministerial call-in under section 46(1) of the Town and Country Planning (Scotland) Act 1997.
Answer
Ministers consider the need for call-in on a case-by-case basis, taking account of the specific individual circumstances. They use their powers under section 46(1) of the Town and Country Planning (Scotland) Act 1997 sparingly, recognising the important role of local planning authorities in decision making. As set out in the Ministerial statement on call-in, Ministers will generally consider intervention only where there may be some important issue at stake which should be determined at the national level.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 24 August 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 8 September 2026
To ask the Scottish Government what guidance it provides to local authorities to ensure that alternative regeneration models, such as partnerships with registered social landlords or housing associations/trusts/cooperatives, are fully exhausted before granting consent for the demolition of a listed building on the grounds of private commercial unviability.
Answer
The Scottish Government does not provide guidance requiring specific regeneration models or ownership arrangements to be exhausted before consent is granted for the demolition of a listed building. It is for planning authorities to assess each case on its merits, taking account of the evidence provided and the specific circumstances of the application.
- Asked by: Adam Harley, MSP for Strathkelvin and Bearsden, Scottish Liberal Democrats
-
Date lodged: Thursday, 20 August 2026
-
Current Status:
Answered by Neil Gray on 8 September 2026
To ask the Scottish Government what discussions ministers have had with Police Scotland regarding the discovery of Scotland's first nitazene lab in 2025.
Answer
Scottish Ministers have not had discussions with Police Scotland regarding the discovery of the nitazene lab as it is an operational matter and investigations are ongoing.
- Asked by: Claire Baker, MSP for Mid Scotland and Fife, Scottish Labour
-
Date lodged: Wednesday, 19 August 2026
-
Current Status:
Answered by Stephen Gethins on 7 September 2026
To ask the Scottish Government when it expects any changes to the recommended level of community benefit for solar developments, as proposed in its working paper, Refreshing the Good Practice Principles for Community Benefits from Onshore Renewable Energy, to take effect.
Answer
I refer the member to the answer to question S7W-02321 on 24 August 2026. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers