- Asked by: Pauline McNeill, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 01 June 2026
-
Current Status:
Answered by Siobhian Brown on 11 June 2026
To ask the Scottish Government, in light of the commitment outlined in the Scottish National Party's 2026 manifesto, when it will commence work on a public health campaign on the safe use of social media for young people.
Answer
I refer the member to the answer to question S7W-00409 on 9 June 2026. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 02 June 2026
-
Current Status:
Answered by Stephen Gethins on 11 June 2026
To ask the Scottish Government what its position is on the shortlisted sites of SSEN’s proposed Elgin new-build substation.
Answer
It would not be appropriate for the Scottish Government to comment on the merits of any proposals.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 04 June 2026
-
Current Status:
Answered by Stephen Gethins on 11 June 2026
To ask the Scottish Government, further to the answer to question S7W-00644 by Stephen Gethins on 3 June 2026, which did not address the question posed, and in light of remarks by Alan Brown MSP in the debate, It’s Scotland’s energy, on 28 May 2026, in which he said, "Zonal pricing was an option that could bring down bills, but that was immediately ruled out by Westminster", whether it supports the introduction of zonal pricing in the electricity market, and what specific evidence it has relied upon in forming its position.
Answer
The Scottish Government was not provided with detailed policy design details for the implementation of zonal pricing nor did the UKG provide a full assessment of the impact of this on consumers, communities and businesses in Scotland. We have been clear that reform is required now to address the immediate issue of high energy costs for consumers.
- Asked by: Mark Ruskell, MSP for Mid Scotland and Fife, Scottish Green Party
-
Date lodged: Monday, 01 June 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 11 June 2026
To ask the Scottish Government what plans it has to review its Planning Advice Note 50, which provides advice on controlling the environmental effects of surface mineral workings, and associated annexes.
Answer
The Scottish Government has no current plans to review Planning Advice Note 50.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 28 May 2026
-
Current Status:
Answered by Shirley-Anne Somerville on 11 June 2026
To ask the Scottish Government, further to the answer to question S6W-44204 on 23 March 2026 by Mairi McAllan, how many homes have been built through the Rural and Islands Housing Fund in the 2025-26 financial year, broken down by local authority area.
Answer
I refer the member to the answer to question S7W-00181 on 5 June 2026. 42 homes were delivered through the Rural and Islands Housing Fund between 1 April 2025 and 31 December 2025 in 7 local authorities. This data is based on management information and may be subject to change. Figures for 1 January 2026 to 31 March 2026 are not yet available.
The Rural and Islands Housing Fund is a demand-led scheme open to a range of organisations, including community organisations, development trusts, private landowners, private developers, and traditional housing providers.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 28 May 2026
-
Current Status:
Answered by Stephen Gethins on 11 June 2026
To ask the Scottish Government what information it has regarding the price per MWh of electricity generated (a) for Hunterston B prior to its closure and (b) is for Torness nuclear power station.
Answer
The Scottish Government does not hold information on the price of electricity currently generated by Torness nuclear power station or by Hunterston B prior to its closure. Both stations sell or sold electricity into the wholesale market and the specific prices received by the operator are a commercial matter.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 01 June 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 11 June 2026
To ask the Scottish Government what work it has undertaken to develop a public sector insourcing plan.
Answer
The Scottish Government recognises the importance of ensuring public services deliver best value and this is at the core of the Public Service Reform strategy.
Public bodies are supported to consider all delivery models, including insourcing where appropriate. However, decisions on whether services are delivered in-house or externally are for individual bodies, based on their assessment of value for money, delivery confidence and outcomes.
The Scottish Government has established and signposts guidance to support best value decisions which includes the Scottish Public Finance Manual and Public Service Reform Frameworks.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Wednesday, 03 June 2026
-
Current Status:
Answered by Neil Gray on 11 June 2026
To ask the Scottish Government what steps are being taken to ensure consistent and comprehensive data collection on the profile of perpetrators of sexual assault and rape in Scottish hospitals, including whether they are (a) patients, (b) staff or (c) visitors, in order to better inform prevention and safeguarding measures.
Answer
The recording of information on the profile of sexual assault and rape perpetrators is an operational matter for Police Scotland, and any such incident should be reported to them to ensure victims can access the justice they deserve. Beyond this, Health Boards have a legal duty to record data on violence and aggression within their estates, and the Scottish Government expects them to have the necessary reporting systems in place to do this.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Friday, 05 June 2026
-
Current Status:
Answered by Shirley-Anne Somerville on 11 June 2026
To ask the Scottish Government whether it will consider reallocating any projected underspends in local authority budgets for affordable housing supply to Glasgow City Council.
Answer
There is currently no projected underspend in the 2026-27 Affordable Housing Supply Programme (AHSP).
The AHSP seeks to optimise the positive impact of spend and delivery, and does so by supporting local authorities to deliver fully against its Resource Planning Assumptions (RPAs). Where local authorities are unable to deliver against its RPA the programme will seek to move funding to other areas that are able to deliver. This process is taken forward as part of normal in year programme management, in discussion with local authorities and reported on through annual outturn reports.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 01 June 2026
-
Current Status:
Answered by Stephen Flynn on 11 June 2026
To ask the Scottish Government what support mechanisms are available to small business owners whose businesses have been significantly impacted by harassment, online abuse or prolonged legal disputes.
Answer
Any small business owner who experiences harassment or online abuse can report these matters to the police for consideration of investigation. There are a range of laws which operate that may be relevant depending on the specifics of any harassment and online abuse the business is experiencing such as the threatening or abusive behaviour offence. Operational decisions on criminal investigations are an independent matter for Police Scotland.
All businesses – wherever they are in the country – can access support from a wide variety of public sector organisations through the Find Business Support website.