- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Tuesday, 02 June 2026
-
Current Status:
Answered by Stephen Gethins on 16 June 2026
To ask the Scottish Government what specific financial mechanism it has modelled as a replacement to the UK-wide Contracts for Difference scheme, and what estimate it has made of the cost to the public purse of underwriting such a mechanism to secure capital investment for future ScotWind projects.
Answer
The Contracts for Difference scheme is currently reserved to the UK Government. Any future changes to market arrangements will require careful design to support the continued delivery of Scotland’s offshore wind project pipeline and deliver savings for consumers.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 02 June 2026
-
Current Status:
Answered by Stephen Flynn on 16 June 2026
To ask the Scottish Government what its position is regarding the need to ensure that A roads have a speed limit of 30mph instead of 20mph, particularly in larger towns.
Answer
The Scottish Government published The Implementation Guide for 20 mph Speed Limits in Scotland in October 2024.
This national guidance is in place to support a consistent, evidence-led roll out of 20 mph speed limits on appropriate roads across Scotland. This can be viewed at: The Implementation Guide for 20 mph Speed Limits in Scotland | Transport Scotland
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Tuesday, 02 June 2026
-
Current Status:
Answered by Stephen Gethins on 16 June 2026
To ask the Scottish Government, in the event of the establishment of an independent or fully devolved energy market, what assessment it has made of any legal and financial liabilities regarding existing 15- and 20-year Contracts for Difference agreements entered into by Scottish generators with the UK-owned Low Carbon Contracts Company, and whether any such liabilities would be transferred entirely to consumers in Scotland.
Answer
Contracts for Difference are long-term private law contracts that would continue to operate according to their agreed terms, unless and until amended in accordance with those terms.
- Asked by: Sanne Dijkstra-Downie, MSP for Edinburgh Northern, Scottish Liberal Democrats
-
Date lodged: Thursday, 04 June 2026
-
Current Status:
Answered by Stephen Flynn on 16 June 2026
To ask the Scottish Government, further to the answer to question S7F-00008 by John Swinney on 4 June 2026, for what reason the west of Scotland was chosen for the next stage of the roll-out of the £2 cap on bus fares.
Answer
The extension of the £2 bus fare cap pilot to the west of Scotland will help address cost of living pressures for people in that region. Once introduced, it is our priority to then take forward legislation in this parliament to put in place a £2 bus fare cap across Scotland.
- Asked by: Maggie Chapman, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Friday, 05 June 2026
-
Current Status:
Answered by Stephen Flynn on 16 June 2026
To ask the Scottish Government how much Transport Scotland has spent on (a) rail infrastructure enhancements, (b) new stations, (c) line reopenings, (d) electrification projects and (e) associated feasibility studies and business cases in each year since 2007, broken down by (i) project and (ii) local authority area.
Answer
- Asked by: David Green, MSP for Caithness, Sutherland and Ross, Scottish Liberal Democrats
-
Date lodged: Monday, 08 June 2026
-
Current Status:
Answered by Angela Constance on 16 June 2026
To ask the Scottish Government what discussions it has had with NHS Highland regarding the delayed opening of the Invergordon GP walk-in clinic, and what action is being taken to ensure that the service becomes operational as soon as possible.
Answer
My officials are in regular contact with NHS Highland regarding the opening of the Invergordon GP walk-in clinic. NHS Highland is responsible for the operational management of the pilot however the Scottish Government is providing support where required. I appreciate the hard work of the health boards to get these services up and running and my thanks go to our hard-working NHS staff for delivering these.
- Asked by: David Green, MSP for Caithness, Sutherland and Ross, Scottish Liberal Democrats
-
Date lodged: Monday, 08 June 2026
-
Current Status:
Answered by Angela Constance on 16 June 2026
To ask the Scottish Government, further to its announcement that a GP walk-in clinic would open in Invergordon in May 2026, for what reason the original opening date was missed, and when it first became aware that it would not be met.
Answer
NHS Highland is responsible for the operational management of the GP walk-in pilot site in Invergordon, including opening dates and securing staffing. We are clear that any site must be safe and sustainable- NHS Highland informed us last month of a delay due to recruitment and my officials are in regular contact with NHS Highland to ensure that there are no further delays.
- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 04 June 2026
-
Current Status:
Answered by Shirley-Anne Somerville on 16 June 2026
To ask the Scottish Government how many empty homes were sold to (a) homebuyers and (b) developers through matchmaking schemes in 2025-26, broken down by local authority area.
Answer
The Scottish Government does not hold data about the number of homes sold through matchmaker schemes. This includes the Matchmaker Scheme for Empty Homes in Scotland - Scottish Empty Homes Partnership, launched by the Scottish Empty Homes Partnership last year, as well as local schemes run by some individual local authorities such as Aberdeen City. We are aware that some local schemes are being discontinued in favour of supporting the national scheme.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Thursday, 04 June 2026
-
Current Status:
Answered by Angela Constance on 16 June 2026
To ask the Scottish Government whether it will provide information on the estimated total NHS Scotland maintenance backlog, as of 31 March 2026.
Answer
It is important to note that the situation relating to maintenance is dynamic; as NHS Boards address and eliminate items of maintenance, new items will emerge. It is therefore expected that there will be ongoing requirement for maintenance across the NHS estate.
While it is possible to compare year-on-year changes in backlog maintenance values, this does not represent a cash requirement. Elimination of backlog is achieved from a variety of measures – estate rationalisation and disposal of older properties, incorporating backlog work with redevelopment or lifecycle investment and targeting high risk areas, as we are already doing through NHS whole system infrastructure planning (WSIP).
This whole system approach to infrastructure investment supports continued safe operation of existing facilities. Boards have completed risk-based assessments and received confirmation of items which can be progressed with additional funding from the Scottish Government. Future Business Continuity Plan submissions will be on a two-yearly full submission cycle, with interim years only requiring ‘by-exception’ reporting of new essential maintenance or equipment replacement items not previously reported.
Further detail on NHS WSIP is set out in the answer to question S7W-00813 on 16 June 2026. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh North Western, Scottish Liberal Democrats
-
Date lodged: Wednesday, 03 June 2026
-
Current Status:
Answered by Maree Todd on 16 June 2026
To ask the Scottish Government, following its withdrawal from the Home Office and National Crime Agency Wastewater Analysis for Narcotics Detection (WAND) Programme, how will it coordinate and gather intelligence with the rest of UK to tackle the increasing availability of synthetic opioids, which can be significantly more powerful than heroin.
Answer
As confirmed in the answer to S7W-00736 on 16 June 2026, the Scottish Government has not withdrawn from the Wastewater Analysis for Narcotics Detection (WAND) programme.
Reports from the WAND study have highlighted the difficulties in being able to detect the presence of synthetic opioids in wastewater due to their instability and because testing methods are not as developed as they are for other drugs.
Investments made in surveillance, like Scotland’s RADAR early warning system, are supporting the ability to identify and respond to new and emerging threats such as dangerous synthetic opioids. The RADAR system has played a pivotal role in the public health response to nitazene-linked drug harm clusters by identifying trends and sharing information. Work is also progressing to deliver drug checking services which will also help to provide a fuller surveillance picture and better identification of emerging trends and new drugs.
Scottish Government Ministers and officials engage routinely with counterparts in the UK Government and the other Devolved Administrations in response to the shared threat posed by the increasing prevalence of synthetic substances.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers.