- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Patrick Harvie on 31 July 2023
To ask the Scottish Government what assessment it has made of the presence of reinforced autoclaved aerated concrete in private sector buildings, including those that were initially built for the public sector, and how it will raise awareness of any problems related to its presence.
Answer
The focus of our activity remains engagement with public sector organisations to seek reassurance of both their awareness and any action identified on this issue. Maintaining the safety of buildings is the responsibility of building owners, and this includes responsibility for any assessment of the presence of reinforced autoclaved aerated concrete in private sector buildings.
Authoritative guidance on identification and assessment of reinforced autoclaved aerated concrete is already published by organisations such as the Institution of Structural Engineers. We continue to engage with the UK government and such organisations to understand and support broader action being taken to raise awareness of this risk topic across all sectors.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Michael Matheson on 31 July 2023
To ask the Scottish Government how much funding it will make available to NHS boards that find reinforced autoclaved aerated concrete present in (a) hospital buildings and (b) other NHS board buildings, in order to (i) manage and (ii) remove it.
Answer
NHS Scotland Assure are conducting a survey programme which will confirm how many buildings in the NHS Estate contain reinforced autoclaved aerated concrete.
Once the extent of the programme is determined, the condition will be assessed, thereafter it will be possible to establish the management and removal plans that may be necessary. This means however, that it is not currently possible to assess what these plans might cost until the survey work is complete.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Michael Matheson on 31 July 2023
To ask the Scottish Government by what date it expects (a) local authorities, (b) NHS boards and (c) other public sector bodies to (i) have identified reinforced autoclaved aerated concrete in buildings, (ii) publish risk management plans and (iii) remove it entirely.
Answer
Owners are responsible for building maintenance and safety and should meet all relevant health and safety requirements related to those working in or using their buildings.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Patrick Harvie on 31 July 2023
To ask the Scottish Government what meetings ministers have had about reinforced autoclaved aerated concrete, and whether it will publish the minutes and any other documentation that accompanied these.
Answer
Scottish Ministers discussed reinforced autoclaved aerated concrete at a Building and Fire Safety Ministerial Working Group meeting on 21 June. Agreed minutes of the meeting will be published on the Building and Fire Safety Ministerial Working Group website.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Shona Robison on 31 July 2023
To ask the Scottish Government which public sector organisations have notified it that they have found or suspect reinforced autoclaved aerated concrete to be in their buildings.
Answer
The following organisations have contacted The Scottish Government on the presence or suspected presence of reinforced autoclaved aerated concrete within their building estate:
- NHS Scotland
- Police Scotland
- Scottish Fire and Rescue Service
- East Lothian Council
- West Lothian Council
We are in the process of contacting other public bodies to seek reassurance of both their awareness and of any action identified on this issue.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Shona Robison on 31 July 2023
To ask the Scottish Government whether it will establish a register of public sector buildings that have been found to contain reinforced autoclaved aerated concrete.
Answer
Maintaining the safety of buildings is the responsibility of building owners. Our focus remains on engagement with public sector organisations to gauge awareness and response to this issue. This will include receipt of information on the status of buildings in the public sector. A decision on whether there is a need to establish a register of buildings would be based upon the information received and subsequent input from our Ministerial Working Group on Building and Fire Safety.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Shona Robison on 31 July 2023
To ask the Scottish Government whether it has identified whether reinforced autoclaved aerated concrete is present in any Scottish Government buildings.
Answer
The Scottish Government has not undertaken an inspection for reinforced autoclaved aerated concrete (RAAC) in the Core SG Estate since 2021 and as such has not identified any reinforced autoclaved aerated concrete (RAAC) in the core SG estate.
A specialist has been appointed to support the development of a scope to undertake building inspection surveys which will also assist in identifying the presence of Reinforced autoclaved aerated concrete in the Core Estate. The Core Estate is defined as those sites/buildings where SG Directorates operate from.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Shona Robison on 31 July 2023
To ask the Scottish Government, further to the answer to question S6F-02291 by Humza Yousaf on 29 June 2023, whether it will establish a national fund to assist (a) NHS boards, (b) local authorities and (c) other public sector bodies.
Answer
In his answer, the First Minister identified a need to understand the scale and scope of the problem before discussions on any fund that might or might not be necessary. This remains the case.
We are engaging with public sector organisations to seek reassurance of both their awareness and any action identified on this issue.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Shona Robison on 31 July 2023
To ask the Scottish Government whether it has any estimate of the number of public sector buildings currently (a) partially and (b) fully closed due to issues related to reinforced autoclaved aerated concrete, broken down by (i) building type and (ii) location.
Answer
As noted in the reply to S6W-19672, five organisations have contacted The Scottish Government on the presence or suspected presence of reinforced autoclaved aerated concrete within their building estate.
At this time, the following public sector buildings are reported to us as partially or fully closed:
Building type | No. | Location | Partially or fully closed? |
School | 1 | East Lothian | Partially closed |
School | 5 | West Lothian | 4 partially closed, 1 fully closed |
Police Scotland property | 1 | Edinburgh | Partially closed |
Police Scotland property | 1 | Dundee | Partially closed |
We will continue to work collaboratively with local authorities’ Scottish Heads of Property Services network and Scottish Futures Trust to better understand the presence of RAAC across the school estate.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Shona Robison on 31 July 2023
To ask the Scottish Government how it will ensure that every public sector body is aware of the risks and dangers of reinforced autoclaved aerated concrete.
Answer
We are engaging with public sector organisations to seek reassurance of both their awareness and any action identified on this issue. Building owners and employers are responsible for managing the condition of buildings within their ownership or control, including duties under health and safety legislation to maintain a safe workplace.