- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 20 April 2017
-
Current Status:
Answered by Humza Yousaf on 2 May 2017
To ask the Scottish Government, in light of recent fatal accidents, what its position is on installing street lighting at the Toll of Birness junction on the A90.
Answer
In the last five years, no injury accidents at the A90 Toll of Birness junction have occurred in the hours of darkness, therefore there is no evidence to suggest that street lighting would reduce the risk of accidents occurring and we have no plans to install it.
The recent tragic fatal accident on 5 April 2017 did not occur at the junction itself and took place in daylight. There have been no other fatal accidents at the junction in the last ten years.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 10 April 2017
-
Current Status:
Answered by Fiona Hyslop on 25 April 2017
To ask the Scottish Government what action it took to ensure that transport (a) to, (b) from and (c) within the United States for the First Minister's recent visit was completed in the most environmentally sustainable way possible.
Answer
The First Minister visited the United States between 2 and 7 April attending events and meetings in California and New York.
The visit focused on promoting trade and investment, boosting tourism, sharing best practice across the public and private sector and promoting Scottish innovation and entrepreneurship. I refer the member to the answer to question S5W-08856 on 20 April 2017 for more details on the visit. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx
Transport arrangements for the visit were made in line with Scottish Government's sustainable Travel Strategy.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 24 April 2017
-
Current Status:
Taken in the Chamber on 27 April 2017
To ask the First Minister what the Scottish Government's position is on the accuracy of the GERS figures.
Answer
Taken in the Chamber on 27 April 2017
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 31 March 2017
-
Current Status:
Answered by Keith Brown on 19 April 2017
To ask the Scottish Government, further to the answer to question S5T-00479 by Keith Brown on 28 March 2017 (Official Report, c. 5), on what date the cabinet secretary was advised of the possible delay to the opening of the Queensferry Crossing; how much the delay will add to the overall cost of the project, and what the economic impact will be.
Answer
I met with the contractor, Forth Crossing Bridge Constructors, on Monday 27 March 2017 when they advised me that, due to the continued impacts of wind on the construction operations, they were unlikely to be able to achieve an opening date in May for the Queensferry Crossing.
As I stated at the Rural Economy Connectivity Committee any increase in delivery time will not result in any increase to the overall cost to the taxpayer which stands at £1.35 billion as before. The £245 million of savings that have been released since the construction started are secure.
The Forth Road Bridge is operating well. Consequently, there will be no further economic impact as a result of the revised timescales.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 24 March 2017
-
Current Status:
Answered by Keith Brown on 18 April 2017
To ask the Scottish Government, further to the answer to question S5W-07768 by Keith Brown on 23 March 2017, in what month during the winter period the route will be opened.
Answer
The AWPR/B-T is currently scheduled to open to traffic in Winter 2017-18. As with all complex civil engineering contracts of this scale, delivery and completion of certain elements of work are dependent on a variety of factors project wide including weather, rates of productivity and scheduling of other works. Given these variables, it would not be prudent to estimate the exact opening date at this time.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 24 March 2017
-
Current Status:
Answered by Keith Brown on 18 April 2017
To ask the Scottish Government what the initial estimated cost was for the A944 South Kingswells Junction, and whether it will provide a breakdown of any subsequent revisions to that estimate.
Answer
Due to the Design Build Finance and Operate (DBFO) procurement model for the AWPR/B-T project, the costs associated with construction works on specific junctions cannot be disaggregated from the cumulative cost information held for the project.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 23 March 2017
-
Current Status:
Answered by Keith Brown on 18 April 2017
To ask the Scottish Government, in light of the comment by a Transport Scotland spokesman in The Courier on 23 March 2017 regarding the date of the opening of the Queensferry Crossing that “it is difficult to give a cast iron guarantee at this stage”, whether it will provide an update regarding what date it expects the crossing to open.
Answer
As the Cabinet Secretary for Economy, Jobs and Fair Work announced in his statement to the Rural Economy and Connectivity Committee in Parliament on 29 March 2017, the Queensferry crossing is expected to open to traffic between mid-July and the end of August.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 24 March 2017
-
Current Status:
Answered by Keith Brown on 18 April 2017
To ask the Scottish Government whether it will provide an update regarding the construction of the A944 South Kingswells Junction.
Answer
The construction of the AWPR/B-T is now well underway. The project currently remains on schedule to open to traffic in Winter 2017-18.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 24 March 2017
-
Current Status:
Answered by Keith Brown on 18 April 2017
To ask the Scottish Government whether it will provide a breakdown of any revisions made to the original plans for the A944 South Kingswells Junction.
Answer
There has been no change to the plans for the A944 South Kingswells Junction which were published in September 2007.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 21 March 2017
-
Current Status:
Answered by Keith Brown on 18 April 2017
To ask the Scottish Government for what reason it has relocated its office in London to Scotland House on Victoria Embankment; how much the relocation will cost; what the annual running cost will be, and how this will compare with the cost of running the previous office at Dover House.
Answer
The Scottish Government is committed to making Scotland a better place to work and do business by attracting investment, promoting the research and innovation capabilities of Scottish companies and universities and enhancing international collaboration. In her Programme for Government of 1 September 2015 the First Minister announced the establishment of Innovation and Investment Hubs to meet this commitment.
Dover House provided minimal limited office accommodation for Scottish Government use only at an annual cost of £130,000. Through the Smarter Workplaces Programme, the Scottish Government is delivering new ways of working across the Government estate to help the Government and public bodies to deliver better services through, for example, co-location and common use of facilities. Scotland House London brings together under one roof the Scottish Government and other partners; Scottish Enterprise, Scottish Development International, Highlands and Islands Enterprise and Visit Scotland, and provides more flexible space and improved facilities which allows Scottish businesses and entrepreneurs to meet potential customers and investors, to showcase their goods and services and to host events. SG will pay an estimated £425,000 per annum towards the occupancy costs which are shared across the partners and there are no Scottish Government re-location costs.