- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 July 2026
-
Current Status:
Answer expected on 30 July 2026
To ask the Scottish Government how many applications under section (a) 36 and (b) 37 of the Electricity Act 1989 are currently awaiting determination by the Energy Consents Unit, and what proportion of applications in each category have exceeded the 52-week determination target.
Answer
Answer expected on 30 July 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 July 2026
-
Current Status:
Answer expected on 30 July 2026
To ask the Scottish Government what the current resourcing levels are within the Energy Consents Unit, and whether it considers those levels to be sufficient to manage the projected increase in application volumes.
Answer
Answer expected on 30 July 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 July 2026
-
Current Status:
Answer expected on 30 July 2026
To ask the Scottish Government what assessment it has made of Scottish Enterprise's Human Rights Due Diligence procedure, including whether it considers it to be of public interest.
Answer
Answer expected on 30 July 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 July 2026
-
Current Status:
Answer expected on 30 July 2026
To ask the Scottish Government what assessment it has made of any cumulative impact of delays in the consenting process on Scotland's pipeline of renewable energy investment across all technologies, including any effect on investor confidence, project delivery timescales and the growth of associated supply chains.
Answer
Answer expected on 30 July 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 02 July 2026
-
Current Status:
Answer expected on 30 July 2026
To ask the Scottish Government what representations it has made to Scottish Enterprise regarding the publication of its Human Rights Due Diligence procedure.
Answer
Answer expected on 30 July 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 10 June 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 24 June 2026
To ask the Scottish Government what discussions it has had with local authorities and COSLA regarding replicating its Future Planners Programme.
Answer
We have had no discussions with local authorities and COSLA about replicating the Future Planners Programme.
Heads of Planning Scotland has been supportive with the current Programme, providing work shadowing opportunities and other learning and development sessions for Student Planners. We will continue to work in partnership with planning authorities and other stakeholders to deliver innovative solutions to increase resilience of the planning profession.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 10 June 2026
-
Current Status:
Answered by Hannah Mary Goodlad on 24 June 2026
To ask the Scottish Government what plans it has to increase the number of places on its Future Planners Programme.
Answer
There are no plans to increase the number of places on the current Future Planners Programme. We will consider options for the future of the Programme to address the shortage of professional planners working in Scotland in advance of the completion of the current Programme in summer 2027.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 11 June 2026
-
Current Status:
Answered by Jamie Hepburn on 22 June 2026
To ask the Scottish Government, further to the 3 June 2026 Court of Session ruling, which found that Scottish Ministers' failure to comply with the compliance timescale set out in a December 2025 Freedom of Information Decision amounted to a contempt of court, what procedures have been put in place to (a) mitigate the risk of similar action in future and (b) protect the public purse.
Answer
The Scottish Government respects the Court’s judgement of 3 June and will consider its implications in detail.
It should be noted that the material required to be released under the Commissioner’s Decision Notice was published on 24 February. The release consisted of over 700 documents, totalling over 4500 pages and can be accessed on the Scottish Government website.
There were a number of challenges which were specific to the context of this case. Ministers have previously set out to Parliament the requirement to balance our obligations under Freedom of Information legislation with the need to prevent identification of alleged victims in cases of sexual assault.
Ministers do not believe that the challenges experienced in this particular case are indicative of wider issues in the Scottish Government’s ability to meet its FOISA obligations within required timescales. As the Scottish Information Commissioner has recognised, the Scottish Government is a high performing authority in relation to the discharge of its FOI obligations generally. We will consider whether there are specific lessons that can be learned from this case, and from the detail of the Court’s judgement.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 11 June 2026
-
Current Status:
Answered by Tom Arthur on 18 June 2026
To ask the Scottish Government how many households have access to a full fibre connection, broken down by local authority.
Answer
The telecommunications regulator, Ofcom, regularly publishes information in relation to full fibre and gigabit-capable broadband coverage in Scotland as part of their Connected Nations updates. The most recent update was published on 13 May 2026 showing coverage figures for January 2026. An interactive report is published alongside, including local authority area breakdown of full fibre coverage, which can be found at: Connected Nations update: Spring 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 11 June 2026
-
Current Status:
Answered by Tom Arthur on 18 June 2026
To ask the Scottish Government what plans it has to require full fibre operators to publish future rollout plans to enable households and businesses to plan their future activities.
Answer
While the Scottish Government continues to monitor commercial delivery plans to inform eligibility for publicly subsidised intervention, it does not have the power to mandate publication of these commercial plans. We will however continue to publish build plans for publicly subsidised interventions through our address checker which can be found at: Faster broadband in Scotlandhttps://broadbandchecker.service.gov.scot/.