- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Wednesday, 13 February 2002
-
Current Status:
Answered by Allan Wilson on 13 March 2002
To ask the Scottish Executive what progress has been made towards establishing the Loch Lomond and the Trossachs National Park and the Cairngorms National Park.
Answer
The draft Designation and Election Orders for the Loch Lomond and The Trossachs National Park were tabled for Parliament's consideration on 26 February. Ministers continue to consider the recommendations contained in the Scottish Natural Heritage Report with regard to the establishment of a Cairngorms National Park. We hope to complete that consideration soon and to consult on a draft Designation Order for the Cairngorms National Park in the near future.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Tuesday, 26 February 2002
-
Current Status:
Answered by Ross Finnie on 12 March 2002
To ask the Scottish Executive, with regard to the Katrine Water Project, what the cost of acquiring land will be for the new holding reservoir at Bankell farm.
Answer
I have asked the Chief Executive of West of Scotland Water to respond. The response is as follows:Unfortunately I am unable to give an answer to this question as disclosure may prejudice the current land negotiations.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Tuesday, 26 February 2002
-
Current Status:
Answered by Ross Finnie on 12 March 2002
To ask the Scottish Executive, with regard to the Katrine Water Project, whether West of Scotland Water's preferred option required untreated water to be pumped above the level at which it originated at Loch Katrine.
Answer
I have asked the Chief Executive of West of Scotland Water to respond. The response is as follows:The water in Loch Katrine originates from a number of lochs which form a complex combined catchment system. Loch Katrine is the lowest point of this system with Loch Finglas the highest point at 157 metres AOD. The difference in level between the top water level at Loch Katrine and the reservoirs at Milngavie is only 22 inches, an impressive Victorian engineering achievement and one which constrains solution development for the Katrine Water Project.The top water level to which the proposed solution will pump is approximately the same as the top operating level in Loch Katrine. On occasions throughout the year, when Loch Katrine is drawn down, the level to which water is pumped at Milngavie may be higher than the level of Loch Katrine but may not necessarily be higher than the level at which the water originated.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Tuesday, 26 February 2002
-
Current Status:
Answered by Ross Finnie on 12 March 2002
To ask the Scottish Executive what the excess capacity of the proposed new Milngavie water treatment plant will be following completion of the Katrine Water Project.
Answer
I refer the member to the answer given to question S1W-22819 on 20 February 2002.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Tuesday, 26 February 2002
-
Current Status:
Answered by Ross Finnie on 12 March 2002
To ask the Scottish Executive, further to the answer to question S1W-22086 by Ross Finnie on 4 February 2002, what relative weightings were allocated to the different disciplines in the project team in respect of decisions made by comparing options, identifying key trade-offs and reaching consensus on the preferred options through discussions and debate.
Answer
I have asked the Chief Executive of West of Scotland Water to respond. The response is as follows:I would refer you to Annex D of the Environmental Statement which is available for inspection at the offices of East Dunbartonshire Council and West of Scotland Water.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Thursday, 28 February 2002
-
Current Status:
Answered by Ross Finnie on 12 March 2002
To ask the Scottish Executive what volume of water will be pumped per day to Balmore water treatment works under the Katrine Water Project proposals.
Answer
I have asked the Chief Executive of West of Scotland Water to respond. His response is as follows:No water will be pumped to Balmore water treatment works under the Katrine Water project proposals. However, as a consequence of the solution adopted up to 8.5 million kWh of energy consumption will be saved at Ross Priory Pumping Station.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Tuesday, 26 February 2002
-
Current Status:
Answered by Ross Finnie on 12 March 2002
To ask the Scottish Executive what the performance levels will be in respect of water pressure and reliability and continuity of the drinking water supply in Greater Glasgow following completion of the Katrine Water Project.
Answer
I have asked the Chief Executive of West of Scotland Water to respond. The response is as follows:The proposed scheme is planned to comply with the standards set out in West of Scotland Water's Code of Practice and Guaranteed Standards Scheme.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Thursday, 28 February 2002
-
Current Status:
Answered by Ross Finnie on 8 March 2002
To ask the Scottish Executive, with regard to the Katrine Water Project, what the energy consumption per year will be as a result of pumping treated water from Balmore through the pipe network at Bardowie.
Answer
This is a matter for West of Scotland Water. The Chief Executive's response is:The energy consumption associated with pumping water from Balmore to the existing Glasgow supply system will vary depending upon the water demand in any given year and the mode of operation selected for both the Balmore and the new Milngavie water treatment plants. Based on an average year demand, the energy consumption of pumping from Balmore into the Glasgow supply system could lie within the operating range of 3.6 million kWh to 7 million kWh. For the option selection process, the lower figure was selected for use in all option comparisons as being the most representative energy consumption figure for a typical operating year and compatible with operating efficiency frameworks.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Thursday, 28 February 2002
-
Current Status:
Answered by Ross Finnie on 8 March 2002
To ask the Scottish Executive, further to the answer to question S1W-22086 by Ross Finnie on 4 February 2002, whether the relative weightings chosen by West of Scotland Water in respect of different disciplines in the project team distorted the importance attached to immaterial differences in engineering criteria.
Answer
This is a matter for West of Scotland Water. The Chief Executive's response is:Each discipline was asked to score options against their criteria to assist in summarising the information in the Environmental Statement. Each discipline adopted its own scoring approach and a variety of different ranges and scoring methods were used, although for all criteria a low score represented worse and a high score better performance. So for example the environmental team scored all options on a range of 1 (worst) to 10 (best) for all environmental criteria; the different engineering disciplines used ranges e.g. 0-2, 0-5, 1-5, depending on the criterion and the degree of differentiation between the options. For energy consumption the quantitative values were simply converted to a scale of 1 to 10 from worst to best. It should be emphasised that the scores for different criteria are not equivalent and cannot be summed together. The scoring ranges are indicated on the appraisal framework in Table D6.2 of Appendix D in the Environmental Statement.It is worth stressing that throughout the complex decision making process, final choices were made by discussion and debate between different disciplines in the team. Consequently distortions related to importance did not occur. Tools were used to help the team sort out their ideas and distil information down into a manageable form to help their discussions, but they were not the principal methods used to make choices.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Thursday, 28 February 2002
-
Current Status:
Answered by Ross Finnie on 8 March 2002
To ask the Scottish Executive what volume of leakage is anticipated per year from the new pipe network to be installed as part of the Katrine Water Project.
Answer
>This is a matter for West of Scotland Water. The Chief Executive's response is:West of Scotland Water would not anticipate any leakage from the new pipe network to be installed as part of the Katrine Water Project.