- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Tuesday, 10 October 2006
-
Current Status:
Answered by Ross Finnie on 7 November 2006
To ask the Scottish Executive what further steps are being taken to ensure that recyclate markets are developed in Scotland and, in particular, what involvement Scottish Enterprise and Highlands and Islands Enterprise have in such activities.
Answer
Scottish Enterprise providesa range of support to recycling. This support includes using recycled material andcompost in construction and regeneration projects; signposting businesses to servicesoffered by the Waste and Resources Action Programme (WRAP) and REMADE Scotland andthe inclusion of waste management issues in training for all Business Gateway businessadvisers.
In 2005-06, Scottish Enterprisehelped around 300 businesses to achieve businessbenefits from environmental activities, in many cases diverting waste from landfill.Scottish Enterprise, along with the Scottish Executive and the Scottish EnvironmentProtection Agency, also support the Scottish Industrial Symbiosis Programme - aresources exchange for business that seeks to identify synergies and new businessopportunities.
Highlands and Islands Enterprise has a particular focus on socialenterprise and, for example, over the last four years has supported 27 communityled recycling projects through £228,000 of financial assistance.
The Executive’s main work ondeveloping markets for recyclate is through WRAP and REMADE. Their work includescapital grant and lease guarantee schemes for bodies reprocessing recyclate; research;encouraging the use of recycled material and compost in contracts and in manufacturing;helping to develop standards and quality protocols for recyclate and compost; monitoringthe state of the markets and providing advice on ensuring the quality of recyclateand compost.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Tuesday, 26 September 2006
-
Current Status:
Answered by Ross Finnie on 20 October 2006
To ask the Scottish Executive, in light of recent concerns expressed by the paper and aluminium industries about the quality of recyclable material being sent for reprocessing, what steps it is taking to ensure that the quality of recyclate is not being compromised in any attempt to increase the quantity of recyclables being collected.
Answer
We are taking action in a numberof areas to ensure that the quality of recyclate is not being compromised.
First of all, Strategic WasteFund awards to local authorities have included provision for education and awareness,to support local Waste Aware Scotland campaigns, co-ordinated by the Scottish WasteAwareness Group (SWAG). Clear and simple advice to householders helps minimise contaminationof recyclate.
Secondly, both the Waste andResources Action Programme (WRAP) and REMADE Scotland carry out work on developingmarkets for recycled products. Their work includes liaison with local authoritiesand industry. REMADE, with support from WRAP, are currently undertaking a detailedmarket analysis for a variety of materials recovered in Scotland, andwill be reporting on the state of these markets in the next few months.
Finally, WRAP are working to develop a specification(PAS 105) for recovered paper. The introduction of a specification will help guaranteethe quality of recovered paper.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Wednesday, 20 September 2006
-
Current Status:
Answered by Nicol Stephen on 4 October 2006
To ask the Scottish Executive whether it is aware that Renewable Devices’ Swift Rooftop Wind Energy System is not available in Scotland through the exclusive distributors Scottish and Southern Energy.
Answer
The Swift system has been installedin a number of locations with support from the Scottish Community and HouseholderRenewables Initiative. I understand that refinements have been made to the systemand that it is currently being monitored in a number of locations across Scotland beforebeing made more widely available.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Wednesday, 16 August 2006
-
Current Status:
Answered by Johann Lamont on 11 September 2006
To ask the Scottish Executive how many developments of 1,000 square metres of floor space or greater have been granted planning permission in each of the last five years, broken down by local authority area.
Answer
The following table shows thenumber of developments which are 1,000 square metres or greater that have been grantedplanning permission over the last five years. These figures include business, industryand all other major developments.
| | 2001-02 | 2002-03 | 2003-04 | 2004-05 | 2005-06 |
| Aberdeen City | 43 | 37 | 28 | 32 | N/A |
| Aberdeenshire | 55 | 42 | 49 | 57 | 70 |
| Angus | 7 | 4 | 3 | 4 | 8 |
| Argyll and Bute | 22 | 11 | 9 | 30 | 17 |
| Cairngorms | N/A | N/A | N/A | 4 | 32 |
| Clackmannanshire | 10 | 10 | 3 | 13 | 5 |
| Dumfries and Galloway | 33 | 31 | 18 | 36 | 43 |
| Dundee City | 12 | 24 | 25 | 12 | 23 |
| East Ayrshire | 23 | 13 | 18 | 28 | 23 |
| East Dunbartonshire | 7 | 6 | 6 | 9 | 9 |
| East Lothian | 41 | 46 | 32 | 24 | 22 |
| East Renfrewshire | 8 | 8 | 11 | 11 | 7 |
| Edinburgh | 90 | 55 | 54 | 46 | 43 |
| Falkirk | | 15 | 23 | 17 | 31 | 20 |
| Fife | | 58 | 73 | 58 | 57 | 47 |
| Glasgow City | 85 | 74 | 91 | 90 | 79 |
| Highland | 42 | 39 | 66 | 69 | 51 |
| Inverclyde | 17 | 9 | 9 | 11 | 14 |
| LLTNP | | N/A | 3* | 6 | 4 | 6 |
| Midlothian | 20 | 8 | 6 | 7 | 25 |
| Moray | | 7 | 0 | 5 | 44 | N/A |
| North Ayrshire | 21 | 15 | 15 | 18 | N/A |
| North Lanarkshire | 50 | 33 | 50 | 46 | 41 |
| Orkney | | 8 | 4 | 3 | 5 | 12 |
| Perth and Kinross | 12 | 10 | 16 | 34 | 57 |
| Renfrewshire | 38 | 41 | 52 | 42 | 21 |
| Scottish Borders | 15 | 11 | 9 | 6 | 17 |
| Shetland | 2 | 17 | 10 | 13 | 4* |
| South Ayrshire | 16 | 26 | 7 | 14 | 16 |
| South Lanarkshire | 46 | 42 | 36 | 45 | 68 |
| Stirling | | 13 | 8 | 19 | 28 | 57 |
| West Dunbartonshire | 6 | 3 | 6 | 21 | 13 |
| West Lothian | 28 | 31 | 15 | 39 | 38 |
| Western Isles | 9 | 21 | 7 | 3 | 8 |
| Scotland | 859 | 778 | 759 | 933 | 896 |
Notes:
*Incomplete year.
N/A Statistics not yet available.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Wednesday, 16 August 2006
-
Current Status:
Answered by Johann Lamont on 6 September 2006
To ask the Scottish Executive whether it plans to allow public sector bodies to have access to information on the energy performance of buildings gained through the provision of energy performance certificates and how this will be achieved.
Answer
A public consultation on implementationof Articles 7, 8 and 9 of the EU Directive 2002/91/EC on the energy performanceof buildings closed on 11 August 2006 having run for 12 weeks. Section 9 of the consultationentitled
Retaining and making use of information from energy performancecertificates presented four options regarding provision of a register of energyperformance certificates with national coverage. The options given were:
1. no register;
2. the building standards register;
3. a register held by a non-publicbody, and
4. a hybrid of options 2 and3.
Options 2, 3 and 4 all have registersthat are accessible to both Scottish ministers and local authorities. The responsesto the consultation are still in the process of being analysed and no decision hasbeen taken.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Friday, 21 July 2006
-
Current Status:
Answered by Nicol Stephen on 28 August 2006
To ask the Scottish Executive how much Scottish Enterprise spent on energy saving developments in (a) 2002, (b) 2003, (c) 2004 and (d) 2005.
Answer
This is an operationalmatter for Scottish Enterprise.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Friday, 21 July 2006
-
Current Status:
Answered by Nicol Stephen on 28 August 2006
To ask the Scottish Executive how Scottish Enterprise invests in energy saving developments.
Answer
The Executive’s strategicdirection to Scottish Enterprise requires it to help deliver the ScottishExecutive’s green jobs strategy, with its twin aims of improving resourceefficiency in business and exploiting new business opportunities.
Information on ScottishEnterprise’s investments is an operational matter for Scottish Enterprise.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Friday, 21 July 2006
-
Current Status:
Answered by Nicol Stephen on 28 August 2006
To ask the Scottish Executive in which energy saving developments Scottish Enterprise invested in (a) 2002, (b) 2003, (c) 2004 and (d) 2005.
Answer
This is an operationalmatter for Scottish Enterprise.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Friday, 21 July 2006
-
Current Status:
Answered by Nicol Stephen on 28 August 2006
To ask the Scottish Executive what criteria Scottish Enterprise applies in allocating funding to energy saving developments.
Answer
This is an operationalmatter for Scottish Enterprise.
- Asked by: Shiona Baird, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Tuesday, 27 June 2006
-
Current Status:
Answered by Tavish Scott on 17 August 2006
To ask the Scottish Executive what the estimated average construction cost per mile is of the Aberdeen Western Peripheral Route.
Answer
We currently estimate the totalcost of the Aberdeen Western Peripheral Route as being between approximately £10 million to £13 millionper mile.