- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government how many of the 1,500 new clinical and non-clinical staff, committed to in its NHS Recovery Plan, will be based in the National Treatment Centre Lanarkshire.
Answer
National Treatment Centres (NTCs) require an appropriate mix of new and experienced staff to operate safely and efficiently. While initial modelling of projected workforce requirements was undertaken to inform earlier phases of our planning for the National Treatment Centre programme, detailed plans relating to the size and composition of the workforce for NTC Lanarkshire will be developed by the Board and submitted to the Scottish Government as part of the wider planning and approval process for the site in operation.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Fife, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
The following table outlines the current projected activity for National Treatment Centres during 2023-24 with reference to the position in the NHS Recovery Plan.
NTC projected 2023-24 activity
NTC | Current projection (procedures) | Comparison with NHS Recovery Plan position |
Golden Jubilee Phase 1 | 12,481 | Higher |
Fife | 472 | Higher |
Highland | 1,586 (partial) | Lower – see Note 1 |
Forth Valley | 450 (partial) | Lower – see Note 2 |
Golden Jubilee Phase 2 | 390 (partial) | Lower – see Note 3 |
Notes
1. Part-year figure due to opening during 2023-24: current projection excludes additional Ophthalmology capacity due to commence in Autumn and for which planned activity is in the process of being finalised.
2. Part-year figure due to opening during 2023-24: full-year activity as per NHS Recovery Plan will be achieved from 1 April 2024.
3. Part-year figure due to opening during 2023-24: full-year activity as per NHS Recovery Plan will be achieved from 1 April 2024.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Fife, and what the revised timetable is as of 30 June 2023.
Answer
The following table outlines the opening dates set out in the 2022 update to the NHS Recovery Plan and the current projected opening dates for National Treatment Centres with approved Full Business Cases:
NTC | Opening Date in 2022 Recovery plan update | Currently Projected Opening Date |
Golden Jubilee Phase 1 | December 2020 | December 2020 |
Fife | Early 2023 | Opened March 2023 |
Highland | Spring 2023 | Opened April 2023 |
Forth Valley | Spring 2023 | End of 2023 |
Golden Jubilee Phase 2 | Late summer 2023 | End of 2023 |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Fife, and what the revised cost is as of 30 June 2023.
Answer
This information is available in the Infrastructure Investment Plan 2021-22 to 2025-26: major capital projects progress update - March 2023 - gov.scot (www.gov.scot) the Scottish Government published on 20 June 2023. The plan outlines the progress and current projected costs of NTC Fife as well NTC Golden Jubilee Phase 2, NTC Grampian, NTC Lothian, NTC Highland, NTC Forth Valley and NTC Ayrshire and Arran.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Ayrshire and Arran, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
The Full Business Cases (FBC) for NTCs in Ayrshire & Arran, Tayside, Lothian, Lanarkshire and Grampian remain under development. The proposed number of patients treated will be revised to align with national treatment targets once FBCs are finalised.
NTC | 23/24 Activity in Recovery plan | Currently Projected activity |
Ayrshire & Arran | N/A | To be agreed at FBC |
Tayside | N/A | To be agreed at FBC |
Lothian | N/A | To be agreed at FBC |
Lanarkshire | N/A | To be agreed at FBC |
Grampian | N/A | To be agreed at FBC |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Ayrshire and Arran, and what the revised timetable is as of 30 June 2023.
Answer
The following table outlines the opening dates set out in the 2020 NHS Recovery Plan and the current projected opening dates for National Treatment Centres without approved Full Business Cases:
NTC | Opening Date in 2020 Recovery plan | Currently Projected Opening Date |
Ayrshire & Arran | 2025 | To be agreed at FBC |
Tayside | 2025 | To be agreed at FBC |
Lothian | 2025 | To be agreed at FBC |
Lanarkshire | 2026 | To be agreed at FBC |
Grampian | 2025 | To be agreed at FBC |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned new Edinburgh Eye Pavilion, and what the revised timetable is as of 30 June 2023.
Answer
It is not possible to compare the current proposal with the previous one at this point. The Full Business Case is still under development and project timetable will be revised to reflect the impact of inflation, net zero carbon targets, plot change and updated clinical brief to align with national treatment targets.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Tayside, and what the revised cost is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19963 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 03 July 2023
-
Current Status:
Answered by Michael Matheson on 28 July 2023
To ask the Scottish Government how many of the 800 additional nurses, midwives and allied health professionals recruited from overseas, as announced on 8 June 2023, have started their posts, as of 1 July 2023.
Answer
Of the 800 additional nurses, midwives and allied health professional recruited from overseas, as announced on 8 June 2023, 357 have started in their post with the remaining due to arrive in the coming weeks.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Thursday, 29 June 2023
-
Current Status:
Answered by Jenni Minto on 27 July 2023
To ask the Scottish Government, in relation to SARS-CoV-2 swabs that underwent whole-genome sequencing (WGS), how many were identified as having as their likely source of transmission (a) healthcare associated and (b) community-acquired infection, broken down by (i) NHS board and (ii) each month in which the WGS took place, since March 2020.
Answer
I refer the member to answer to question S6W-19519 on 27 July 2023.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers .