- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26458 by John Swinney on 31 July 2015, when the meeting with the Office of the Scottish Charity Regulator was arranged.
Answer
The answer given to question S4W-26458 contained an error. The meeting referred to was held on 23 June 2015; this was arranged on 5 June 2015.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 06 October 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government when it will publish the Scottish Ministers' pay remit guidance.
Answer
The Scottish Government will publish its pay policy alongside its draft budget, following the publication of the UK Government spending review.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26463 by John Swinney on 31 July 2015, whether it has discussed the revised structure for the proposed model with the Office for National Statistics and, if so, when.
Answer
As I advised Parliament on 9 September 2015, the Scottish Futures Trust has submitted proposals for changing the hub model to the Office for National Statistics, which has indicated that it hopes to respond to these proposals in the course of November 2015.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26441 by John Swinney on 31 July 2015, whether all projects with a financial close date of after September 2014 have been affected by the Eurostat change.
Answer
Project timetables can be affected by a wide range of factors. Twelve hub projects are considered to be in a position where they would be likely to be able to move to financial close now should current classification issues be resolved. Other hub projects in the pipeline are scheduled to reach financial close later in 2015.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26468 by John Swinney on 31 July 2015, in light of the reported public interest in the matter, whether it will publish the advice.
Answer
The relevant legal advice was provided on a confidential basis.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26461 by John Swinney on 31 July 2015, which projects where capital contributions are no longer being made are affected and, in these cases, what the unitary payments (a) were before and (b) are expected to be now.
Answer
A list of projects where capital contributions are no longer being made is provided in the following table. Unitary payments for these projects will be confirmed when contracts are signed.
|
Health Design, Build, Finance and Maintain (DBFM) Projects
|
|
Project Name
|
Territory
|
Procuring Authority
|
|
Inverclyde Care Home
|
West
|
NHS Greater Glasgow and Clyde
|
|
NHS Lothian Bundle
|
South East
|
NHS Lothian
|
|
Pharmaceutical Special Services
|
East Central
|
NHS Tayside
|
|
Stirling Care Village
|
East Central
|
NHS Forth Valley
|
|
Gorbals/Woodside Health Centre
|
West
|
NHS Greater Glasgow and Clyde
|
|
Project Name
|
Territory
|
Procuring Authority
|
|
Oban and Campbeltown High Schools
|
North
|
Argyll and Bute Council
|
|
Newbattle High School
|
South East
|
Midlothian Council
|
|
South of the City Academy
|
North
|
Aberdeen City Council
|
|
West Calder High School
|
South East
|
West Lothian Council
|
|
Barrhead High School
|
West
|
East Renfrewshire Council
|
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26467 by John Swinney on 31 July 2015, what the implications are for projects transferring to the new structure and, other than the schools referred to in the response, which projects will transfer.
Answer
The intention is that all hub design-build-finance-maintain projects signed after the introduction of ESA10 in September 2014 will transfer to the new structure. Details about all projects in the hub programme are available on the Scottish Futures Trust website at: www.scottishfuturestrust.org.uk
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26471 by John Swinney on 31 July 2015, which of the capital projects that it has announced without firm timings are to be funded by the hub design-build-finance-maintain programme, which is subject to time delays.
Answer
Detailed information about all projects being delivered through the hub programme is available on the Scottish Futures Trust website at: www.scottishfuturestrust.org.uk.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26450 by John Swinney on 31 July 2015, for what reason it has not carried out an assessment of project costs or inflation impacts on the delayed projects.
Answer
I refer the member to the answer given to question S4W-27757 on 27 October 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at: www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 29 September 2015
-
Current Status:
Answered by John Swinney on 27 October 2015
To ask the Scottish Government, further to the answer to question S4W-26442 by John Swinney on 31 July 2015, whether it will provide details of all of the projects delayed for each year, also broken down by (a) the length of delay and (b) what the additional cost will be.
Answer
The length and cost for projects of any delay will only be known when contracts are signed.