- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 29 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government how often emergency telephones on the A90, including the section north of Dundee, have been used in the past five years.
Answer
In the past five years 51 calls have been received on the emergency telephones on the A90 north of Dundee.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 29 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government what the annual cost is of maintaining emergency telephones on (a) the A90 in the (i) section north of Dundee and (ii) other sections and (b) other trunk roads.
Answer
Transport Scotland’s Traffic Scotland Infrastructure Contractor, Amey Ltd, is paid a monthly Unitary Charge for the inspection, maintenance and repair of ITS (Intelligent Transport System) roadside infrastructure and individual costs specific to emergency telephones cannot be disaggregated.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 29 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government how often emergency telephones are inspected and tested on (a) the A90 in the (i) section north of Dundee and (ii) other sections and (b) other trunk roads.
Answer
All emergency telephones on the Scottish Trunk Road Network, including on the A90, are inspected and tested every three months.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 29 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government whether it has carried out an analysis of the cost-effectiveness of maintaining emergency telephones on the A90, including the section north of Dundee, compared with alternative measures.
Answer
The emergency telephones on the A90 are maintained under a term contract managed by Transport Scotland whereby a monthly unitary payment is made, for the maintenance and repair of, Scotland wide, ITS (Intelligent Transport System) roadside assets such as the A90 emergency telephones.
In the summer of 2024, on behalf of Transport Scotland, the Traffic Scotland Service Operator (Mobiie) conducted an Operational Requirement review of Emergency Roadside Telephones (ERT’s) resulting in the recommendation that the ERT’s remain in operation as a service to the public.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 28 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government, further to the answer to question S6W-33161 by Fiona Hyslop on 22 January 2025, how much has been spent on maintaining the 2,297 street lights on the A90 in each of the last five years, broken down by local authority area.
Answer
Please see the following table which provides the costs of maintaining the 2297 streetlights on the A90.
Activity | 2020-21 | 2021-22 | 2022-23 | 2023-24 | 2024-25 |
Maintenance | £2,713.53 | £8,884.67 | £850.77 | 0.00 | 0.00 |
Transport Scotland does not hold the above information by local authority area, and these figures are for the full length of the A90.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 28 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government, further to the answer to question S6W-33168 by Fiona Hyslop on 22 January 2025, what specific challenges were encountered in repairing the A90 Glencarse overpass following the vehicle strike in March 2023, and how these were addressed.
Answer
Following the incident, ecological surveys were required before detailed structural investigations and repair works could begin. These identified protected species in the vicinity of the bridge and as such, repairs could not commence until further surveys were completed. These processes cannot be circumvented as they are a statutory requirement, and Transport Scotland must ensure compliance with legislation.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 28 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government, further to the answer to question S6W-33161 by Fiona Hyslop on 22 January 2025, how many of the 2,297 street lights on the A90 are fitted with LED bulbs.
Answer
2296 of the 2297 streetlights on the A90 are fitted with LED bulbs.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 28 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government, further to the answer to question S6W-33168 by Fiona Hyslop on 22 January 2025, whether there have been any reported safety concerns or incidents involving overbridges and overpasses along the A90 in the last five years, and what actions were taken to address these concerns.
Answer
Safety concerns are recorded as defects and addressed in accordance with contractual requirements and timescales.
Safety defects and remedial actions on the A90 over the last five years are detailed below:
- A90 840 Portlethan Overbridge – Damaged parapet mesh. Parapet mesh was replaced.
- A90 630 Stracathro Overbridge - Damage to Vehicle Restraint System (VRS) post. VRS post replaced.
- A90 310 Kings Cross West Overbridge – Plugged drain. Drain cleared.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 28 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government, further to the answer to question S6W-33168 by Fiona Hyslop on 22 January 2025, what the expected (a) timeline and (b) costs are for completing ongoing repairs to the A90 Finavon Bridge, which was damaged during Storm Babet.
Answer
The current estimated costs are £716,432.40. However, this may increase as the investigation and design for the permanent works progresses.
Construction is anticipated to be complete by the end of September 2025. However, investigations and permanent works design are still ongoing. Ecological factors at the site will also severely affect the available construction window
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 28 January 2025
-
Current Status:
Answered by Fiona Hyslop on 11 February 2025
To ask the Scottish Government, further to the answer to question S6W-33168 by Fiona Hyslop on 22 January 2025, whether Transport Scotland or its operating companies have identified any of the A90 overbridges and overpasses as requiring significant structural upgrades or replacement.
Answer
Refurbishment and upgrades to the A90 Kingsway, Dundee Strathmartine and Old Glamis footbridges are planned for the 2025-26 financial year.
These works are currently at the tendering stage so a detailed construction programme is unavailable. Preparatory works have commenced on site with temporary pedestrian crossings being installed prior to the footbridges being removed from site for refurbishment/upgrade.