Displaying 2811 contributions
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
So it was not Mr Tydeman.
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
So those two payments were approved by different people.
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
Mr Boyle, you mentioned that the internal audit had picked up 10 high-risk areas. Can you say what they were, or at least tell us what some of them were?
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
Okay. Do you think that there is any connection between those discoveries and Mr Tydeman being asked to leave the organisation?
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
Was it also Mr Tydeman who approved the other payments that were above the £95,000 threshold, which the Scottish Government has not given approval for?
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
So one was approved by Mr Tydeman.
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
I cannot remember when David Tydeman was fired. To save me looking it up, was that before or after the report was concluded?
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
I completely agree with that. Mr McMillan and I have been in meetings in which we, and others, have argued that the yard needs investment to modernise in order to be able to compete for orders, and ultimately to return to the private sector, which was the Government’s ambition for the yard. It needs to modernise—I am in no doubt that that is required.
However, if the yard does not win any of the small vessel replacement programme work, how much extra work does it need to be able to continue?
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
I will express it in another way. Let us say that the yard gets to September and it has finished the Glen Rosa, which is off and sailing, and carrying passengers, and there is no further work. How long can the yard continue, in your view, without extra work?
Public Audit Committee
Meeting date: 16 January 2025
Graham Simpson
Yes, but at some point, the Government is going to have to make a decision on what it does about the future of the yard.
I have a couple of other questions. At paragraph 7 of your report, you mention “Under Recoveries funding”. Can you tell us what that is? According to your report, it amounts to £1 million per month.