I wish the witnesses a good morning and thank them for coming along at relatively short notice. I hope that you appreciate that the committee was keen to see further evidence. There were two reasons for that. First, in the relatively short time since our last evidence-taking session, the situation seems to have changed fairly dramatically. Secondly—as I am sure you are aware—we are required to report to Parliament on the second stage of the budget process, which will be done later this week. Obviously the committee would like to explore a number of issues, but it might be that someone would like to make an opening statement. If that is the case, please carry on.
It might be helpful to say one or two things just to remind colleagues of where we are. As the convener has implied, this report comes between the normal quarterly reports, the next of which is due in January or early February next year. This report follows the Presiding Officer's letter of 19 November.
The witnesses will be aware that Parliament authorised the Finance Committee to scrutinise the Holyrood project. It is neither an understatement nor an overstatement to say that there is considerable concern that the way in which information changes in short periods makes that job difficult. The committee is concerned that that situation will continue, if we are to report properly to Parliament.
It is fair to point out that the construction managers always said to us that they could not give total guarantees for finishing dates or costs because, as you rightly say, they are moving targets. In particular, until the blast proofing and glazing issues were resolved, they were major issues that had a potential impact on the whole programme. Happily, we are now mostly through that situation and—I hope—there will not be further problems of that kind. We have always said that the information would become firmer when we reached the later stages of the project. We are now arriving at that point.
The job of programming the different contractors on site—there are about 30 to 40 at the moment—is one of the key tasks in the contract that we have with Bovis Lend Lease (Scotland) Ltd. Bovis is our construction manager, but a principal within that organisation normally advises the corporate body directly. We have always been aware that the task is highly complex and that, as the position shifts—or if any contractor's position shifts on any given day—a certain amount of resequencing must take place. As Robert Brown said, the advice that we have had from Bovis has always been given in the context of understanding the pressures on the programme and the logistical difficulty of managing the site. Bovis has always been open with us about the programme and given us a great deal of information to back up what it has said, which the project managers in my team scrutinise and advise us on. I have no reason to believe that the programme advice is not based on sound information that Bovis receives from individual package contractors.
Yes, but if the advice was sound in the past, why did it change dramatically and why do you still have confidence in the people who supply the advice?
As I understand the programming activity, it involves Bovis liaising all the time with individual package contractors and understanding what they can achieve against the overall targets for the programme. Ideally, a programmer starts off with a fair degree of float, which means that anything that happens in an individual package can be accommodated by rescheduling and resequencing; however, that can be done only up to a point.
Can you give the committee a clear assurance that the advice from the construction manager was to extend the completion date?
That is the wrong way around.
The construction manager did not advise that the date should be extended, but that it was no longer possible to achieve the original target date and that, if all things happened—
With great respect, you are entering into semantics. If the construction manager says that the target date cannot be achieved, it follows that it must be extended.
The convener is correct. The advice that we have given to the committee is based on the construction manager's programme. On top of that, the corporate body must judge the additional period that is required to move the Parliament to the new building. Of course, the starting point for that decision must be the latest programme information from the construction manager.
Can the committee be clear that the construction manager advised that the completion date would have to be extended?
Yes.
At the committee's meeting on 8 October, Miss Davidson said:
That quote does not represent the thrust and tenor of the evidence that we gave to the committee on 8 October, which referred to the risks that the project team is dealing with and the difficulties that it is having with the glazing contracts and the blast-proofing issue. Sarah Davidson and I gave considerable evidence about the uncertainties that those factors created, which could not be put to bed until the bomb-blast test was completed.
If we assume that members accept those reasons, is August a very unlikely date? Is there a chance in hell that the project will be completed by August?
There are associated risks, in the same way that there are risks with the finance for the project, which we have discussed with the committee. An outcome of last week's risk review is that Bovis will assess the likelihood that the target date will be met and we will report their findings at the next meeting. However, our working assumption—based on information that we have received from Bovis—is that it is unlikely that the project will be completed by August.
I find it difficult to understand why the target date has not only slipped three to four months since last you gave evidence on 8 October, but has become less certain rather than more certain.
The current target date of best completion at the end of August, which means that everything will have happened to the best possible outcome, has the same status as the previous date of the end of April.
Do you have a worst possible outcome date?
No.
What kind of Gantt chart is used? Some kind of worst-case scenario must have been considered.
The object of the exercise is to finish the thing as quickly as possible—that is clearly what we are after and the progress group is keeping on top of the contractors to try to ensure that that happens. However, as we have already explained, the business of the glazing and blast proofing could have had a dramatic effect on the progress of the contract. Had last Friday's blast test failed, we would be coming to the committee today to report a serious situation; there are no two ways about that. Happily, the blast test was passed. Although we have to take account of the fact that the test had to happen in the first place, that is part of the risk review that is taking place at the moment. The major concerns that we would have had if the blast test had failed have not materialised. We are therefore able to come to the committee with good news on that particular point because passing the test removes what was probably the single biggest risk that remained on the contract.
What are the remaining risks that cause all the uncertainty?
The risks are changing from the design and testing risks to the usual risks that would be associated with a building contract. Weather problems and other problems can hold up the work. Those risks are less significant than the ones that existed in the beginning—the major design risks about which the committee knew.
With respect, you are in some danger of playing good cop, bad cop here. Ms Davidson has portrayed a fairly depressing situation in which the August date that appeared soon after our last evidence-taking session is pretty uncertain. At the same time Mr Brown is telling us that there is good news on the glazing contract and that that is a reason for some optimism.
I am sorry, but I am not prepared to accept that the information that the progress group and the corporate body has given to the committee has been anything other than frank and honest. The information was given to the best of our ability on a very complex project.
A date of August 2003 appeared in the past few weeks, but considerable doubt has been cast on that date in the past few minutes. That is not under any circumstances acceptable.
It is not acceptable to the corporate body, either. We have been trying as hard as we can to get clear dates and clear information.
I have a sense of déjà vu. Just over a year ago I was sitting here asking questions on the same subject, but we do not seem to be any more certain. That is really what we are talking about.
I invite Paul Grice to deal with that question.
I hope that I can answer most of the points that Dr Simpson raised. The corporate body and the progress group have agreed to get together in early January to look ahead to the final nine months or year of the project. Many issues that have just been raised will be considered. The idea is to try to anticipate the kind of questions that have been asked—for example, what are the major hurdles to finishing the project? We will have the benefit of the output from the risk review and it will be possible to provide a report to the committee that I hope will answer many questions. The risk in global terms and the types of risk could certainly be identified. Sarah Davidson might want to say more about that, but it is fair to say that the types of risk have shifted.
If I remember correctly, you thought originally that the rateable value of the building might be about £6 million. Was that the annual rateable value?
Yes.
I appreciate that perhaps that money comes out of a different budget but it comes, nonetheless, out of the Parliament's budget. If the building does not open in April, we will not pay rates, so there will be a £0.5 million saving per month to offset the £600,000 per month idling costs that you have reported today.
That is a fair point, although I think that the rates estimate was £4 million—the figure is still an estimate at this stage. The money is still a significant amount. Richard Simpson is right—rates will not be paid until we take occupation and ownership of the buildings. On the other hand, we pay rates and other charges where we are at the moment. I think that there will be a net overall increase in that the rateable value will be higher than the collective value of the current buildings, but one would have to net the rates that we pay on the current buildings, which are still substantial—they run to millions of pounds. Therefore, there will not be a complete saving.
Will you give us your thoughts on the process of construction? You expressed concerns about the management of the contract and you now have considerable experience.
The members of the corporate body are obviously not experts on construction methods; we take guidance from officials on this kind of thing. My view of the construction method is, to be frank, slightly jaundiced because of our experience of the project.
I hope that the SPCB might, at the conclusion of the process, make recommendations to the Executive on the method that has been used. It has clearly not been possible to estimate risk using that method and the risk has been more than fulfilled in many aspects. The financial position report states:
I have some sympathy with that. It is probably a matter for the auditors and the Audit Committee to examine in due course. I am not sure that it is necessarily our job to make recommendations to the Executive, but in the interests of the Parliament, I hope that our experience will be of use to our overall knowledge although I hope that we, as individuals, do not have to repeat it.
I hope that the SPCB will take a view and pass it on to the Executive.
I accept that point. The corporate body has considered the issue and is yet to make a final decision. The provisional view is that it is probably not good to move part of, rather than the whole, operation at once. There are issues of double working and so on if the Parliament is partly in one place and partly in another, which would cause difficulties. Against the background of the dates that we are now considering, the corporate body will examine the situation again nearer the time with a view to making a final recommendation and a decision on the best way forward.
The matter of glazing does not just concern the chamber; there is also a key glazed stairway, which provides public access to the committee rooms. The corporate body's judgment was about how much of the site would be usable at that stage. It felt that, on balance, if it would be difficult for the public to get to the chamber and committee rooms, it would be harder to justify moving down the road at that time.
I accept Robert Brown's comments about inheriting a system that he had no part in designing. As I said in my report for the Finance Committee, it is beginning to come through clearly that there is huge uncertainty at every stage of the contract process.
Yes. The SPCB met the contract manager a little while back with a view to pressing him on many such questions. The answer boils down to the same answer that I gave earlier. Until some of the uncertainty is out of the way, the contract manager will not guarantee a final date. Nobody could possibly do otherwise in such a situation.
However, you now have the information from that test.
I hope that we can become a bit clearer about that. We may wish to meet the contract manager again soon with that issue in mind. The progress group has more detailed involvement, but the SPCB will want to know what the position is.
If the bomb-blast testing has been sorted out, another big uncertainty is out of the way. If you ask the project manager for a date, I presume that he could give you one and tell you what he is concerned about. Surely, given his experience and the stage that the project has reached, the project manager could give you the safety lead times that he would need to be able to deliver, encompassing the matters with which he thinks there might be difficulties, and you could make a decision based on that information. Is that a fair comment?
Yes, but the question goes back to what was said about the current review of the position. If you follow my point, a contract such as the Holyrood project is full of little decisions—and bigger decisions—that have an impact on issues such as reprogramming or who is on site when. We must consider that impact, which Sarah Davidson mentioned earlier.
Will you answer another fairly simple question? Have you had any notification that remedial work requires to be done to complete contracts? It is normal for such work to come along at this stage in a contract. Are any contract plans being pulled together to deal with such situations, or have they been dealt with?
Contract plans are not involved, but I understand that, as individual packages are completed, the work is checked for matters such as the need for additional services and intrusions. No package of works has been let for major remedial work.
Are there no alignment issues to deal with in the building?
I am not aware of any.
I am interested in your comments on the recent article in The Scotsman that estimated a completion date of August 2004.
I will pick up the last point, which is important, and Paul Grice will deal with the other issues. We have been advised that there is more or less no slack in the programme, which has a completion date of the end of August. That programme assumes that every contractor exactly hits its date, which is why we feel considerably uncertain about the situation. Bovis has advised us that individual contractors might have hidden a little slack in their programmes, but if they have, Bovis cannot clearly see it. Having worked that out, one can see that site logistics are tight and, as Paul Grice said, could have significant knock-on consequences.
The view that every contractor will hit their target seems optimistic, to say the least. Are you convinced that a scenario is not being created that will automatically add cost to the project? Normally, major construction projects are so vulnerable to a programme that if any contractor does not fully meet its deadlines, that has a knock-on effect and considerable cost implications, although that does not happen in the normal course of events. Given that this is a major public sector project, are you concerned that some contractors are—I will put it kindly—taking advantage?
We are conscious of the risk to a major construction project at this stage of contractors recognising that their client is over a barrel. Bovis is employed to examine closely on our behalf all claims for additional money. We authorise such claims only if we are fully satisfied that the work for which a claim has been made has been done and that the delays were not the contractor's fault.
I do not think that that advice is rocket science, mind you, even though it is professional advice. Do you remain confident in the advice that you receive from Bovis?
I have no reason not to be confident in it.
I want to answer Elaine Thomson's question on migration because I recognise that it is of particular interest to the committee. The global amount that we spend on migration will be relatively unaffected by when we migrate, although it is likely, given the latest uncertainty, that the move will fall into the next financial year rather than the present one. When we know more, we will try to give the committee a more precise estimate.
Is the plan contingent on the number of weeks of recess?
If we move entirely during a recess, the process will be faster, for obvious reasons. If we are not in a recess, we can carry out testing of the chamber and other systems at weekends. However, I strongly advise that a period of recess—at least a couple of weeks—is required for the flit. My advice is not to attempt the move while Parliament is sitting. However, provided that we carry out testing at other times, we probably need only two to three weeks for the move. Those points might affect the date on which we decide to move. Although the corporate body has not decided the issue yet, we might not move in as quickly as possible because it might make sense to move over a longer period in order to continue the business of the Parliament. That judgment can be made only in the next session, when we will have a clearer idea of the matter.
As someone who used to be responsible for the business of the Parliament, I appreciate your point that a key issue is to migrate in a way that best suits business. However, as the cost of the project is causing increasing concern, I suggest, with respect, that a key issue is to migrate in a way that minimises escalations in cost, which are becoming regular. I appreciate your point, but it could be misunderstood easily.
I agree absolutely.
The committee also agrees with the sentiment that the key issue is to try to minimise costs. Politicians would be prepared to put up with discomfort if it saved the taxpayer at least some money in the project.
I do not seek a long, philosophical answer, just a brief one. Why do the people who are charged with managing the project on behalf of the Parliament have such confidence in the guarantees that have been given by the Bovis construction manager, rather than in the advice of John Spencely, who said that he thought that the Parliament would be ready for entry in January 2004? If we consider all the difficulties associated with migration, such as testing, one can understand why Spencely said that at the time of his report. The matter might have become a bit clearer for all of us since then.
If any of us were there.
Margo MacDonald raises several points. I ask Paul Grice to deal with the RMJM point first, as that stands apart from the rest.
I should preface my answer by saying that I will check the detail when I go back—if I have got it wrong, I will obviously put it right. You are right to say that EMBT/RMJM is a company created out of RMJM, an Edinburgh-based company, and EMBT, a Barcelona-based company. The four original directors were the two directors from RMJM and two directors from EMBT, one of whom—Enric Miralles—subsequently died. The company now has three directors.
I assure you that it is. I have them in front of me.
The key issue is that, when the contract was originally let, we were required to take out public indemnity insurance lasting a long period of time. In other words, if, for example, after the contract has finished, one of the designs turns out to be faulty—although I have no reason to believe that that would be the case—there will be PI insurance to claim from, which will last well into the future.
This is an important issue. EMBT/RMJM, the joint company that was created specifically for this contract, has no money and it is arguable whether it should be trading.
I do not think that that matters. The public indemnity insurance is in place and is carried by RMJM principally. I have asked that question and have been assured categorically that PI insurance is in place for the circumstances to which you allude. There is a risk, but a high level of PI insurance—several millions of pounds for each individual claim—is in place and will last well past completion. I give the committee a categorical assurance that, if the joint companies ever wound up, the PI insurance would still be in place. I will double check that point and if I have misled you in any way, I will write to you to clarify the situation.
May I ask whether there is money for accelerated working?
You have asked a number of questions and other members have questions to ask.
I repeat what Paul Grice said. The standard warranties and the defect liability periods will be for a year. There is also a retention. If, for example, a roof leaked, it would have to be determined whether that was a fault of the contractor or a fault of the designer. As Paul Grice said, the PII would cover any issues that arose in relation to the design of the building. Bovis is responsible under its contract for a duty of care to the client. It is therefore Bovis's job to ensure that the contractors that it manages on our behalf are fulfilling satisfactorily their contract terms at the various stages of the contract. If concern were expressed about whether Bovis had done that satisfactorily, we would have recourse under the original contract.
I am sure that Sarah Davidson knows about more of the building mistakes that contractors have made than I do, although I know of some. In instances in which mistakes have been made, were the contractors not paid or was some sort of penalty clause imposed? That question relates to one that I asked previously about whether you had refused to endorse any of the recommendations for payment that Bovis had made to you.
I do not know off the top of my head whether any payments were refused. None has come to my level of attention, but that does not mean that there has not been dialogue. I would expect that, if any refusing were to be done, Bovis would do it before it got to our level. I can check that and inform the committee on that point. I am not sure that I caught the first part of the question.
I think that the reply covered the question.
I have a quick question about accelerated working. As far as I can work out, the figure for that is about £20 million. Living in the south side of Edinburgh, I see the site at times that others perhaps do not. As far as I can see, there is not all that much evidence of weekend or night working. How much of the money that has been allocated for accelerated working has been spent?
Because of the reduced amount of daylight at the moment, there is less night working than there was in the early part of the autumn when working hours were extended. Individual contracts have been subject to acceleration and, in relation to programme 6b, the figure is in the tens of thousands of pounds. I can make that evidence available to the committee. I meant to bring it with me today, but I forgot to do so.
I wish to ask about Flour City, but my questions are not about the advice that Shepherd and Wedderburn has given in relation to the prospect of court action against the company. My questions relate to the circumstances prior to the formation of the contract, so I hope that we can have dollops of the frankness and honesty that have been talked about. Did Bovis take up references in respect of Flour City UK or its parent company from any other person or company outwith the Bovis group before Flour City UK was awarded the £7 million contract?
Before you answer that question, Mr Brown, if at any time you feel, on the basis of advice that you have received, that an answer would compromise the legal position of the Parliament, I would be obliged if you would make that clear to the committee.
I am certain that I cannot give an answer to the level of detail in Mr Ewing's question. As the question is slightly off the main thrust of the Finance Committee's current focus, I am not certain whether we have the full detail with us to answer the question. We are well aware that Mr Ewing has asked an enormous number of parliamentary questions on the matter. As far as I am aware, he has received an enormous number of answers. I am not sure whether Sarah Davidson can respond.
I do not have all the papers on Flour City with me today. I would not therefore want to run the risk of misleading the committee by giving information that I cannot be 100 per cent certain of.
You can, however, supply the information at a later date.
Yes.
I ask that the answer be supplied in relation to clients of Flour City UK and its parent company, bankers and suppliers, by which I mean the people from whom the Flour City group of companies bought goods.
With respect, Mr Ewing, that is a hypothetical question. The answer to it would depend on an answer supplied later. I do not think that the question is entirely fair at this point.
In that case, I will give the document headed "Prequalification Questionnaire: SECTION 1 COMPANY DATA" to the witnesses and they can take it away with them. I also have copies for the members of the Finance Committee. The questionnaire is a Bovis Lend Lease document. As I understand it, Bovis requires every potential contractor to complete the questionnaire before business can be considered and before any tender can be put forward. I understand from the Presiding Officer that one such document has been completed, although I point out that the document that I have supplied is only section 1. In reply to a question that I lodged, requesting that a copy of the completed document be placed in the Scottish Parliament information centre, I was informed that that could not be done.
I am fairly certain that we will not think it appropriate to give the committee answers to some aspects of that question at this stage. All that I can undertake to do is to have officials look at Mr Ewing's questions, which will be on the record, and to reply to them as far as we can. If issues arise from that, we are happy to respond to those as far as we can.
If I could add to that, convener—
Before you go any further, I should point out that there is a question mark over the issue that Mr Ewing has raised. I appreciate that you are trying to be helpful, Mr Ewing, but it would have been more helpful if the paperwork in your possession had been supplied to the committee before the meeting. That would have allowed officials, members and those who have come to give evidence the opportunity to peruse the documentation and give more precise answers. I do not know how useful it is at the moment to continue to discuss a piece of paper that no one has had the opportunity to read in any great detail. I suggest to the witnesses that, if they wish to take the opportunity to read the paperwork that Mr Ewing has supplied, they give us their thoughts on it in writing.
I think that that would be the right thing to do.
I will take your steer, convener. I assure the committee that the auditors have considered the entire process and have had access to all the papers. That is the proper and right procedure—we are still in the middle of that. The Auditor General and his staff have had access to information and have received co-operation in examining the whole way in which the Flour City contract was let. If there are lessons to learn from that, they will be learned.
Excuse me, convener, but I have to leave now and attend another committee meeting.
That is fair enough. Thanks very much.
In a letter that the Auditor General wrote to me, he stated:
I am bound to say that that falls within the worries that I described at the beginning of the meeting. We will examine such detailed questions and do our best to respond as far as we can. In fairness, it would have helped to have had notice of some of these questions, if they are the committee's major concerns today.
I appreciate that fully. However, Mr Ewing has offered the questions.
We will do what we can to answer them.
I am sure that you will do your best to find answers to supply to him and the rest of the committee.
That would be a first.
I will go back over some ground that has been covered, to make matters clear in my mind, at least. Did you say that a successful bomb-blast test was a necessary condition of keeping the project on track for a completion date of August, but certainly not a sufficient condition? Will you tell us the other main necessary conditions for meeting that date? As the Christmas and new year holidays fall between now and early January, I am a bit puzzled about what will happen in that time to bring more clarity to the situation, because I expected Bovis to be in a position to say, "If the test is passed, such-and-such will follow."
The situation is not as simple as that. The date is late January, not early January, so that does not cover just the Christmas period.
I understand that the hurdles that remain to be crossed and the matters that pose risks to the project are the possibility of contractors being unable to manufacture to the programme that is on the table and the possibility that, once things come to the site, those components cannot be installed to the planned programme, through the fault of that manufacturer or another trade that it follows.
Surely such considerations were always going to exist. That risk always existed, so does that not imply that the previous date that we were given—April—was, equally, a best-possible date, which would not have been met unless no one had slippage?
That was a best-possible target date. It might have involved slightly more fat in the individual contracts than the current one does—I do not fully know the answer to that. As has been said, such target dates are met if everything falls into place. As the end becomes nearer, our understanding of how likely everything is to fall into place becomes much better.
What will happen between now and late January, given that August is the completion date? Why will the situation be much clearer in late January?
The risk review to which the Presiding Officer referred in his letter took place last week. I was present for a small part of it, but it lasted a whole day. It involved every package manager and representatives of the architects and of the cost consultants going through every package and sharing all their knowledge of the outstanding issues associated with the packages.
I have a question about risk registers. This morning, targets and target dates for completion have been discussed. I presume that a risk register is based on worst-scenario planning and that matters with which you may have difficulties have been accounted for. If those difficulties are passed, they will drop out of the risk register. What is the worst scenario in respect of the move that has been put in the risk register? Is there such a scenario in the register at this stage?
We have two approaches. There is the long-standing risk approach to the building. A worst-case scenario is not used; instead, I understand that risks and the probability that such risks will materialise are identified. The costs of such risks materialising are identified. Essentially, the two figures are multiplied together to produce the numbers in the risk register—that is a tried and tested method.
What figures have been used for migration and dual-site costs beyond August 2003?
I think that Elaine Thomson referred to our budget. Such costs are in the budget for next year. The global sum should not significantly change. To say that most of the costs are most likely to fall in 2003-04 as opposed to straddling the two financial years is not rocket science. I would not expect much, if anything, to fall into 2004-05. However, it should be borne in mind that the terms of the leases of some buildings require us—as they normally do—to put things back and there may be associated works in respect of the General Assembly hall, for example. Such costs are part of the same global sum, but might fall in a future year.
David Steel's letter of 10 December mentions the risk review exercise on 11 December and the cost consultant's advice that, by failing to keep up pressure for completion, we would incur further costs. It seems extraordinary that we are sitting here only a couple of months after the previous review in October when an April or May completion date was suggested with the bomb-blast problems still outstanding. I accept that there was considerable uncertainty. Since the letter, the major bomb-blast problem has been solved, but you are presenting us with not only a further three-month delay, but increased uncertainty. I simply do not follow that. We are supposedly within eight months of the completion date, and would have been within five to six months of it, yet the level of uncertainty is increasing. I find that totally incomprehensible.
That is a fair point, which the corporate body has wrestled with all the way through. If we set targets that are too optimistic, we end up in the position that we are arguably in now. If we set targets that are too pessimistic, arguably that takes the pressure off. We have wrestled with that issue. We want to keep the pressure on by setting tight targets but we need to realise that there is a risk of missing them. That is a genuine issue.
We need to see the key packages and the key areas in which there are still fault lines and problems. In addition, we need to see a list of the contractors' deadlines and the penalties involved. I assume that there are penalty clauses for contractors who fail to manufacture or fail to install. Why are we always paying out for those penalties, while nobody else seems to be? Indeed, are there any penalty clauses? In January, I would like to see all the remaining contractor issues and design faults laid out before us so that we can get a degree of certainty. We need to see the full risk review.
For reasons of commercial confidentiality, it may not be possible to provide the committee with everything, but the corporate body will certainly look to give whatever information it can and try to meet those points. There certainly are penalty clauses for non-compliance but, as in all these things, one must establish who is at fault.
We would like to see which contractors have been penalised.
As members know, we bear the entire risk of the construction management. That is just the nature of the contract that we have.
Forgive me for taking a simplistic view but, having sat through today's meeting and having followed the issue prior to today, I find it remarkable that we are getting no real answers. We are no further forward than we were. Day in and day out, we MSPs are required to provide answers for the people to whom we are accountable on what is happening with the building. I find it remarkable that, although it is now December 2002, we will still not know until the end of January 2003 the estimated completion date for the building.
I am sure that the members of the corporate body and of the progress group would be delighted to change places with members of the Finance Committee to give them an insight into all of this. Sarah Davidson will deal with the aspect that Karen Gillon has raised.
As well as responding to that point, I will pick up on what Dr Simpson said. When we report back in January, I think that we will be able to show that there is a high degree of certainty about the completion of a great deal of the complex. We have a high degree of certainty that Queensberry House and the MSP building will be entirely complete by dates in, I think, March and April next year. It is highly likely that those time scales will be met. There is also a very high likelihood that the dates associated with the completion and fitting out of most of the towers will be met.
I have two very brief follow-up questions. We were given confident assurances two years, 18 months and a year ago, so you will forgive me if I am a bit sceptical about your confidence that we will receive a final date at the end of January. Do you have an estimated ballpark figure or not? Do you know the amount of money that you are working to or do you need to keep coming back to Parliament for more? After all, there are other pressures on the budgets.
I entirely accept that point. You have raised no questions that the progress group and the SPCB have not already looked at in considerable detail. I am sure that members will accept that nothing would delight us more than being able to tell the committee that we have reached the end of the ball game and are finished with the matter.
I think that that completes the questioning. In summing up, I want to express the committee's concern about the job that has been placed on both the Holyrood progress group and the SPCB. We are aware that you have faced—and are facing—an extremely difficult task that originated in a set of circumstances that were outwith your control.
Meeting suspended.
On resuming—