Official Report 200KB pdf
Item 1 concerns oral evidence on the updated preliminary financial case. I welcome the Minister for Transport, Nicol Stephen, and his official, Damian Sharp. I take it, minister, that you were held up deliberating the removal of tolls from the Erskine bridge—
And the Forth bridge.
I invite you to make an opening statement.
I apologise sincerely to members of the committee, the public and others who were delayed as a result of my being held up. I am sorry to say that my discussions had more to do with the Forth bridge than the Erskine bridge. However, for some reason, the journey down was about an hour longer than usual this morning. I apologise for that.
We need a new bridge.
We should bring back the ferry services.
Can we get on with it?
I note those representations.
Thank you. I will lead you gently into the questioning. In your opening remarks, you said that the £375 million funding is subject to presentation
The business case is being developed. Damian Sharp will give the committee an indication of progress.
We received a draft of the outline business case during the summer, on the basis of which we were prepared to continue to support the project. The process of developing a full robust business case for such a large and complex project will take the best part of two years. Some of that work cannot be concluded until we know the outcome of the committee's deliberations, but progress is being made in that we have received a draft outline business case. We expect it to be finalised, including the work to which we referred in our written evidence, by spring next year. If it still suggests that the project has a good net present value, that it is still deliverable, that risks and costs are under control and that it is likely to achieve the required patronage, we will continue to support the scheme as the final business case is developed over the subsequent year or so.
Given the amount that the Executive will contribute, does that give you comfort in relation to the need for flexibility later? Are you comfortable with the process and do you feel that the business case will deliver a firm figure on which to base your calculations?
Do you mean a firm figure for the total project cost?
I mean a figure including the Executive's contribution to it.
We have made it clear that we intend to cap our contribution at £375 million, as previously announced. It is already clear that there are significant cost pressures on the current cost estimates. On the public finance accounting procedures, we have to build in what is called optimism bias. When we are assessing the final value of any major project, we must include a calculation of the tendency to underestimate the total cost of the capital project. When we consider the current estimated cost of the two tramlines—which I believe is around £475 million—and add the optimism-bias figure of about 25 per cent, we see that there are significant financial issues to tackle. We have been aware that those cost pressures have been developing since we announced the availability of the £375 million.
In paragraph 4.3 of your response, you outline a list of issues on which you expect progress to be made. I would like to know two things. First, why did you see those issues as being important? Secondly, what progress has been made on them?
Damian Sharp will talk a bit about progress.
I would like to know why the issues in paragraph 4.3 of your response have been highlighted and what progress has been made on addressing them.
Those issues were raised in the National Audit Office report as being critical to the success of tram schemes, and TIE has identified them as critical issues in response to that report. We agree with TIE that progress on those matters will lead to a reduction in risk and to greater certainty about costs. If they cannot be sorted out and controlled, that will be known at an early stage. We have every reason to believe that they will be sorted out, but they are significant.
Two points are worth emphasising. First, a new company has been established by the City of Edinburgh Council to bring together the trams and the bus operations. That is an important development.
What are your views about the economic value of the scheme? Ove Arup & Partners Scotland Ltd has put a question mark over whether the net present value of £40 million and the benefit-to-cost ratio of 1:2.1 represent a particularly strong case. What are your views on the economic value of the scheme, particularly based on those figures? Any small change in revenue could throw the whole thing out. How robust are you on that?
The general point to make is that in our assessment of the benefits of public transport projects it is still the case that investment in public transport projects often compares poorly with the assessed benefit of investment in roads projects. As you know, in the overall transport budget we are deliberately shifting our investment towards public transport. We aim to invest 70 per cent of the transport budget in public transport schemes. That is a big shift from the late 1990s, when only about 25 per cent of the transport budget went to public transport schemes. All the rest was spent on roads.
You seem to be saying that, regardless of whether the tram can stand on its revenue forecasts, you want to go ahead in any case because of public transport policy. If there is a shortfall in revenue, who will pay? Will it be the Scottish Executive or the Edinburgh council tax payer?
The short answer to that is that the risk will rest with the promoter, which is the City of Edinburgh Council, which means that if there were to be a profit—the current prediction—the surplus would fall to the organisation that was responsible for the project, as would any deficit.
I asked you about the fact that Arup has questioned the strength of the case in relation to the economic value of the scheme, and you have just talked about how serious the situation would be if there were a negative net present value. Does that mean that, ultimately—in a worst-case scenario—the Executive could withdraw the funding?
We have always said that our provision of the £375 million of funding is subject to analysis of the final business case. We see nothing at the moment that would start alarm bells ringing or that would suggest that the positive net present value will shift to a negative one. However, if some such thing did happen, we would have to treat that seriously. It would raise issues of value for money in terms of investment of taxpayers' resources and of Scottish Executive funds. We have a duty to manage public funds properly and would therefore examine any significant shift in the financial position or the deliverability of the project. If a major new issue arose, we would of course have to take that into consideration. However, there is nothing on the horizon that causes us such concern.
When the promoter responded on 12 November to Arup's analysis of the updated PFC, it said that
We all want the trams project to go forward and the Executive has made available significant funding—£375 million—to ensure that it does. In this life, nothing is ever certain, but there is considerable certainty that such funding will ensure that we can have trams in Edinburgh. In the eventuality that you describe, discussions would have to take place about phasing of the project, about which line could proceed first and about the level of other public and private sector funding for the projects.
You have pre-empted a large part of my next question, but I will press you a little more. We recognise that, as you say, line 3 will be dependent on a referendum on congestion charging. If either line 1 or line 2 was not passed by the Parliament, would the Executive still provide financial support to the project if there was only one line rather than a network?
The assumption behind the £375 million that we announced was that it would fund at least two tramlines. As the costs have grown, the hope that it would fund, or help to fund, a third line seems to be receding. The question is: how much of the two proposed lines can we fund? I do not think that we will resolve those discussions today, but the £375 million from the Scottish Executive is still very much available—provided that the final business cases are delivered in the way we expect. In relation to updated and realistic assessments of the cost of the lines, we must ask whether we will be able to deliver both lines for £375 million plus the additional resources that TIE and the City of Edinburgh Council believe can realistically be found. Those important discussions need to be had and it is clear that they will take place, but I do not believe that we are in a position to give you a final and definitive answer today.
Can I clarify what you are saying, for my own benefit? It strikes me that you are saying three things to us: first, the £375 million is capped; secondly, significant financial issues remain to be resolved, which will be done through continuing discussion on the business case and modelling; and thirdly, it is possible that Parliament will pass both bills, but the £375 million will fund only one line or part of one line. Is that a reasonable summation?
The first two points are fair summaries. On your third point, the £375 million is available. One key to triggering the delivery and building of the lines is the parliamentary approval process, but that is an issue for the promoter to address in due course in consultation and partnership with the Executive. The decision on how the £375 million will be allocated between the two lines is yet to be made. The decision will be based on the views of the committees, Parliament, the updated business case and the current funding situation.
Given that the environmental study predicts only a 1 per cent reduction in congestion as a result of the trams, please elaborate on your comments that the scheme will reduce congestion? Section 5.1 of your written submission says that the scheme would have a "major impact" on congestion.
Section 5.1 of our submission says:
By 1 per cent?
Even a 1 per cent reduction in roads congestion is worth striving for. Our current problem is a growth in congestion through the increasing number of cars on Scotland's roads. Edinburgh in particular has big congestion problems, so it is important to support a scheme that can take literally millions of people away from their cars. All the evidence in other parts of the globe and other European cities is that investment in major public transport projects and new tram projects, along with other measures—it is important to emphasise that it is not one single capital project such as a tramline that will make the difference—can tackle congestion, improve the economy of a city and improve the quality of life for communities. However, I agree that the approach needs to be integrated and we need to reverse the current growth in congestion in every city in Scotland.
That is fine, but we are talking about Edinburgh tramline 1, and the committee is charged with examining that case virtually in isolation. Section 2.7 of your written submission says that the scheme
I do not have all the technical details to which the promoter has access. However, the information in front of me at the moment suggests that 9.44 million people a year will make use of tramline 1 when it is first opened in 2011 and that that figure will rise to about 13.69 million in 2026.
Your figures are laudable. If the committee concluded that it would not be possible to attain those figures—let us say that others demonstrated to us that the figures on car reduction were a dream—would that change the Executive's stance on the scheme's funding?
We would consider any of the committee's findings very seriously. As Damian Sharp made clear, our discussions on funding are likely to carry on beyond the duration of the bill's consideration. I give the committee an undertaking that if there were findings that were a cause for concern or that revealed the existence of a degree of over-optimism, the Executive would pay them a great deal of attention, consider them in great depth and respond to them publicly.
In your written evidence, you state that a key aspect of national planning policy guideline 17 is
That is a good question. Every city in Scotland should consider all the different ways in which public transport can be improved. As I have said, we need to do more to raise the image of the bus and the quality of bus services. Much is being done through investment in park-and-ride facilities, bus lanes, new vehicles and raised kerbs to allow for disabled access. Although there has been more investment in buses, we have very little in the way of guided busways. It is possible that the guided busway that is being introduced in Edinburgh might have to be removed to make way for the tram. There are some cities where trams and guided busways can be run together. I want to give serious consideration to that in Edinburgh. If the plans for trams go ahead, I would like Edinburgh to have trams and guided busways and I would like there to be more guided busways in other cities.
The viability of tramline 1 is dependent on the minimisation of potential competition from buses. Experience elsewhere has shown that to be the case. If City of Edinburgh Council proposed to introduce a bus quality contract, would you look on that favourably as a means of eliminating wasteful competition?
I am not sure that it would be appropriate for me as Minister for Transport to use the words that you have just used as part of any approval that I gave to such a contract. However, the Executive has made it clear that we are willing to support quality partnerships and quality contracts, provided that the scheme is appropriate and there is good evidence of local support for such an initiative. If that were the case, I would be prepared to approve such a scheme, regardless of where in Scotland it was proposed. There has been discussion of a quality contract in Edinburgh as part of the overall trams initiative. However, the opportunity exists to get the system right through partnership working, discussion and negotiation. That could offer a fair solution, but I would never rule out the possibility of a quality contract.
Keep me right, but I get the impression that neither Lothian Buses nor the City of Edinburgh Council is particularly keen on quality contracts. Given that the Executive's investment of £375 million could be jeopardised by cowboy bus companies coming in and taking over, are you prepared to argue for such contracts, in the face of opposition from Lothian Buses and perhaps the council?
As I said, a partnership or negotiation approach could be one way ahead. That has happened successfully in other cities in which tram schemes have been introduced and I do not rule it out. I also mentioned that the Scottish ministers are willing to support quality partnerships and quality contracts, although we have not as yet had a statutory quality contract in any part of Scotland. However, we would support a scheme if it was right and appropriate.
Will the proposed national concessionary travel scheme for older people and the disabled apply to tram journeys?
The partnership agreement commitment does not cover tram journeys, but we do not have trams at present. Without prejudging the statement that I will make in Parliament before Christmas, the technical answer is that the current scheme that I am tasked with delivering relates to bus travel. TIE and the City of Edinburgh Council have made it clear that they envisage that the scheme will apply to the new tram system, but a discussion is needed between the Executive and the council about the funding of the concessionary scheme. However, I have not made an announcement that covers trams as well as buses, and nor am I likely to do so next week. I have no doubt that, when the trams run, elderly and disabled people will travel on them free. We have time to sort out the funding arrangements for that; there is no formula for dealing with trams at present and we need to have discussions with the council on that issue.
I do not want to put words in your mouth, but are you saying that, at this stage, the answer is no, but that later it might become yes?
Yes, that is what I am basically saying. By that stage, several members of the committee might benefit from free travel on the trams, but I do not want to introduce a potential conflict of interest into the discussion.
You are on dangerous territory, minister. I advise you to desist from making agist comments.
No, not me.
Yes, you. The convener says that it is you.
I will read it unrehearsed. In evidence to the Public Accounts Committee, the permanent secretary to the Department for Transport stated:
I am sure that that issue was raised last week, when Damian Sharp gave a solid answer to the question. I ask him to reply to you.
The Executive has encouraged TIE and City of Edinburgh Council to participate fully in the discussions of the UK tram group. The strict position is that, although we expect TIE and the council to take account of the best practice of the UK tram group, they are not bound by it in the way that the Department for Transport has determined. However, if they wished to diverge from that best practice, they would have to justify clearly why they were doing so. We would expect that to be part of the developing business case.
There are no further questions from members. I thank the minister and Damian Sharp for appearing before the committee. We will now change witnesses. Panel 2 is witnesses on behalf of the promoter. I welcome Graeme Bissett and Mark Bourke, who are both from TIE; John Watt, from Grant Thornton UK LLP; and Les Buckman, from Steer Davies Gleave. Welcome back to the committee, gentlemen. It does not seem like last week when you were before us. Do you have any opening statements to make?
No.
We will move straight to questions.
At the meeting on 30 November, the committee heard that Transport Edinburgh Ltd has been created by City of Edinburgh Council as an umbrella organisation covering TIE and Lothian Buses. How will TEL work financially, and will it be possible for Lothian Buses to contribute financially to the tram project?
At present, TEL is established as a company with a limited number of formal directors. We anticipate appointments to the board to be made in the spring, which will need to be approved by the council. We are working through that process just now. By that time, a board will be formally constituted that will have the right level of experience and knowledge from the industry. We have already established informally the operational teams that are working together on the design of the tram and related matters. One of those groupings is Lothian Buses.
Will you elaborate on the financial relationship between the City of Edinburgh Council and TEL? If TEL ran into financial difficulties, would the council be financially responsible?
TEL is and is intended to remain a 100 per cent-owned subsidiary of the council. In that sense, the council will remain responsible for TEL's financial performance and condition. If TEL required funding, that could have only one source: the council. However, that in itself does not change the basic proposition that, when the grant from the Executive has been taken into account, the tram system is fundamentally the council's responsibility. TEL is just the repository of the cash flows.
You may recall that at our meeting on 30 November, Transdev suggested that line 2 could be extended to create a route from Leith to the airport. Would that have a significant impact on revenue calculations for line 1? Has that been considered, or is the proposal just a feather in the air?
I would not accuse the suggestion of being the latter. The underlying point is that we have developed financial cases for lines 1 and 2 independently. The objective is to produce a network, part of which would be a routing from the north of the city and from Leith all the way out to the airport and on to Newbridge. If the overall funding was deemed inadequate to build the entire network, one alternative configuration might be to run from Newbridge to the airport, Princes Street and Leith. However, we have not established or evaluated that case in detail.
I am not sure what that means for the circular route's future. If the Leith extension were considered, would you drop the Granton extension and the route by Roseburn?
We are not saying that. We have been given the task of developing the cases for the two separate lines and how they would look as a network. We are not considering a truncated version of that or any alternative configuration.
I understand that. Why stop at Leith with line 2? In considering value for money, have you thought about taking line 2 right along to Granton and having one line overall?
We have concentrated efforts on line 1 as a loop and line 2 as an independent branch. No detailed work has been undertaken on any other configuration. I think that some early evaluation took place—perhaps my colleagues can help on that. I guess that that was intended to ensure that the two lines were the best bet overall and that an alternative configuration would be no improvement. If in future funding was limited and we were looking for an alternative configuration, there would be every prospect of our examining the routing that you describe, which does not stop at Leith but moves west to Granton.
Given that Edinburgh council tax payers will be liable to pick up any additional costs if the calculations are incorrect, should overall revenue implications as well as capital costs be a major factor?
There is no question about that.
I take you back to the evidence that we heard last week from Bill Raynal, who was speaking for the Wester Coates Terrace action group. He expressed concern about what he regards as the lack of accountability in relation to the line 1 project. He referred to the involvement of both TIE and the City of Edinburgh Council in the proposal, but added that it was not at all clear who was ultimately responsible for the scheme. For the record, can you tell the committee today what the lines of responsibility and accountability are? Who is ultimately accountable?
The answer is quite clear to us. TIE is a wholly owned subsidiary of the City of Edinburgh Council and it was established to deliver the project from development through to completion. Ultimate responsibility for the project when it is operational and during its development phase is with the City of Edinburgh Council. TIE's responsibility is to do the best job that it can to provide the council with the best information on which to base the decisions that it needs to make.
For the record, can you clarify the extent to which the council has approved the line 1 proposals, including the updated PFC and STAG documents? What further council approvals are being sought? When will they be sought?
The council approved formally the original PFC, which was submitted with the bill about a year ago, along with the STAG documentation and the content of the bill. Since then, there has been a rolling process of further work. The PFC that the committee received in September was produced at the request of Parliament, to provide further information. The next main stopping-off point will be around the middle or end of next year, when tenders will be issued to the market. As the committee has heard, those will be supported by an outline business case. Ultimately, there will be a final business case, supporting financial close. I defer to those who understand the administrative process better, but I understand that the final business case will have to be approved formally by the council.
The table of sources of tram patronage that you provided to us was hugely helpful, because I like things simple. I want to confirm a point with you. You say that the 5.19 million or 55 per cent of tram passengers in 2011 from "North Edinburgh" correspond to demand from new housing or business developments. Is that the case? What would the effect on the economic case be if the level of development were lower than expected or if development were delayed for any reason?
Before asking Les Buckman to answer the question in detail, I will make a couple of comments. There is no denying that the development to which you refer is one of the key reasons why the line 1 project has been brought this far. I suspect that if it were not for that development, we would not be sitting here. The development is an important element of the forward projections for the tram. We have allowed for the development for which consent has already been given, but not future potential development, although landowners have already tabled a range of further developments and have made their intentions public. We have not incorporated such development in the revenue projections to date.
The convener has asked us to clarify what areas are covered by the term "North Edinburgh". In effect, it covers the Granton and Leith development areas. However, because of the nature of the model and the zones and how those are brought together to produce the numbers in the table, some existing areas of Wardie, Trinity and Newhaven are included. Those areas extend 0.5 to 1km back from the shoreline across the whole of north Edinburgh.
I understand that the forecast is only for those areas that have been given consent and not for others that may be coming. I am simply focusing on the areas that have been given consent. If there is a delay, for any reason, in those developments and the tram does not get the forecast patronage, have you factored that in?
At the moment, the modelling is consistent with the structural plan, so the developments are, in effect, reflected in the forecast that we have made to date. New or upgraded development proposals are in the pipeline for Leith, which would go over and above that. I believe that that demonstrates the commitment of all parties to carry through the regeneration and redevelopment of those north Edinburgh areas. I am sure that members are aware that much has already been built there and that, as we speak, much is under construction.
Thank you.
If I said that, it sounds as if the 25 per cent figure would be right. I cannot remember using that phraseology, but perhaps I could try again. I will ask Les Buckman to embellish my point. There is a ramp-up period at the front end and the model has assumed a three-year period. The issues beyond that are the most critical ones. The key problem area in a large number of the English schemes, but not across the board, has been lack of integration. That is why we are spending so much time on the TEL arrangements and working with Transdev, Lothian Buses and other bus companies. We want to avoid the problem of lack of integration and we have worked proactively to ensure that we have much better visibility of a stable revenue base, with stable bus and tram operations, long before the commitment is made to build the project. Les Buckman will add to that.
I confirm that we have used figures of 75, 85 and 95 per cent for the ramp-up period for line 1 until demand reaches maturity, which is standard practice. The NAO report has statistics on existing tram systems in the United Kingdom that show approximate figures for ramp-up periods that are consistent with our figures.
If I may, I will add a few points to that. In essence, the NAO identified a number of factors that triggered a reduction in patronage. I acknowledge that forecasting was one of those factors; other factors included reliability issues, which we expect to overcome with the early involvement of the operator. Undoubtedly, as Graeme Bisset said, lack of integration has also been a main factor, but we are confident about our team and our adviser base. It is worth noting that one of the most successful tram schemes to be implemented—the Manchester scheme—used the same adviser team that we have used to construct and develop our model.
Do you believe that through the action that you are taking, given the shortfall that has been experienced elsewhere, the 25 per cent reduction can be minimised?
We believe that it can be minimised. We believe that if we apply all good sense we can exceed our estimates, because they are conservative.
We also have an arrangement with the operator, Transdev, whereby it will share on what is known as a pain-and-gain share basis. In this case, that relates to revenue around a target. We are saying that the operator has a strong interest in getting the projections right and doing all it can to beat them in due course through smart marketing and other means. The scheme is designed to do better than the numbers on the table.
You confirmed the forecast that car demand is likely to grow by 50 per cent between 2001 and 2026. Do you believe that Edinburgh's roads have sufficient capacity to cater for such an increase in traffic in that time? Is it more likely that car trips will be suppressed in some other way?
The modelling framework that we have employed in the forecasting process includes a series of facilities to consider the capacity of the highway network and the demand that is placed on it. The model will take a view on whether it is realistic to have that level of demand on the network. If the model forecasts overcapacity and high levels of congestion, it will suppress that level of demand to a more reasonable level and/or move some of the excess demand into adjacent time periods. Last week we talked about the phenomenon of peak spread. If, in the morning peak, there is not enough road capacity for the trips to be made, they will to some extent be moved to adjacent periods. If that still leaves overcapacity, trips will be suppressed. There is a mechanism to ensure that the level of demand is consistent with the available capacity.
Can you put that simply for me? Do you think that there is sufficient capacity on the roads?
At a strategic level there is. It could be that in isolated cases, a particular junction becomes what one might consider excessively over capacity. On the broad network, that is reflected in the modelling and is taken account of.
We have heard that 50 per cent of the total economic benefits of the project will be non-user benefits. Is it the general experience that non-user benefits account for such a high proportion of the forecasted economic benefits?
The firm that I work for, Steer Davies Gleave, has been involved in a number of tram schemes in recent years. We have done the same kind of exercise as that which is laid out before the committee today. We also audit schemes; in effect, we have fulfilled the same role as that of the committee adviser. The 50 per cent figure is within the range of our experience.
Do the calculations that you used on other schemes not show a relatively low level of switch from car to tram? Surely an extremely low level of switch from car to tram is anticipated.
All the empirical evidence from the monitoring studies indicates that the proportion of tram riders who were formerly car users is in the range of 15 to 20 per cent. The forecast that the committee has in front of it is consistent with that evidence.
Given the circular route that tramline 1 will take, I find it difficult to see where the savings—the figure of 15 to 20 per cent of car users—will come from. Do you envisage a wider car-user saving to the city of Edinburgh? Will the people who come into the city centre by car from outside the city boundary not simply drive to somewhere within the circular route, park their car in a suburban area and move on to the tram?
Although that might happen to some extent, it has not been reflected in the modelling. No formal park-and-ride sites have been identified for line 1.
That is the hub of my question. There is no formal park and ride and yet, to get the switch from car to tram, surely informal car parking will have to occur in the suburban areas.
The figures assume no park and ride. If informal park and ride were to happen, the number of car users making the switch would increase. Clearly, where we will get a transfer from the car is in the sphere of influence of line 1. I agree that it is important to point out that line 1 is a circular route, but it has what I would call two core linear routes—the route that runs along the Roseburn corridor from Granton into Haymarket and the city centre and the route that runs along Leith Walk from Leith to the city centre.
I do not want to labour the point, but I get the impression that few of the car users in that part of the city take their cars to either Haymarket or the centre of the city.
Although I do not have the exact figures with me, from memory I recall that a significant proportion of the car trips that are made into the city centre are from north Edinburgh. It is clear that some of those car users will be able to switch to the tram.
Comments have been made about severe congestion in the future. To some extent, if the STAG report is taken into account, there are two contradictory views on that. Will you comment on the time benefits to car users? Will you estimate the time saving, in minutes, on car journeys?
The figure of 1 per cent has been mentioned a number of times. I believe that that stems from a table in the STAG report, which says that 1 per cent of car trips within the Edinburgh area will transfer to the tram. Perhaps that does not seem a lot, but as the 1 per cent transfer relates to the whole city, it will be higher within the area of line 1.
On the economic benefits, what would the effect be if car growth could not be accommodated or if it and congestion do not reach the expected levels?
If car growth does not reach the expected level because the congestion level is so severe, we would still get much the same numbers that we get now, because the sheer level of congestion would suppress demand. Demand might go down, but we would get much the same order of magnitude of congestion relief as we have done.
What if the congestion level is lower than anticipated?
My point is that, if the congestion level is such that it constrains the level of car demand, that would still give us benefits when we take away some of that demand. We would still see substantial congestion relief benefits.
I will address bus and tram patronage issues. Response 17 sets out details of the checks that were made on 2001 bus passengers in the detailed assignment model, or DAM. TIE has not provided an answer to the 1997 central Scotland traffic model 3—CSTM3—validation, but instead refers to Diarmid Lindsay at the Scottish Executive.
Table 4 compares 2001 modelled forecast flows with observed data from 2003, so there is an element of growth in actual ridership, which was alluded to in the note and accounts for some of that variation. In deriving our forecast, we have taken account of the relatively systematic shortfall of public transport demand and adjusted the patronage figures to be consistent with the observed flows in 2001.
If that is the case, we are introducing observed data from 2003 to compare with the 2001 DAM, which was itself supposed to be related to the 1997 CSTM3. How are we to judge whether the case holds up?
I will step back and explain the provenance of the DAM. CSTM3 has a base year of 1997, but it was actually developed after 1997. The timeline was such that 1997 was the chosen base year for CSTM3. A range of surveys was done in that year, and they were combined with existing modelled data to produce a robust model with a base year of 1997. CSTM3 is probably about to be superseded by the transport model for Scotland, but at the time it was the standard model for use by the Scottish Executive and its advisers for all major transport schemes in Scotland. As I said, CSTM3 has a base year of 1997, but given that the model development process probably takes two years, we are talking about it being available in 1999 or perhaps 2000.
Thank you. The question was complicated and that was an interesting answer. Let us try to apply it to the results of the bus surveys. There were considerable fluctuations between the surveys and the models by both time period and location. In relation to table 3 of response 17, can TIE confirm that the application of a 10 per cent uplift would lead to a 26 per cent overestimate in outbound morning bus passengers?
What you are saying is correct. However, conversely, the inbound number of passengers would now be 7 per cent under, and that would be the dominant flow in the morning. Similarly, the outbound flow in the afternoon is the dominant flow by a 75:25 split. That would now be 16 per cent under, instead of 26 per cent under, notwithstanding the growth that we know has occurred between 2001 and 2003, which would probably bring that figure closer to 6 to 8 per cent.
Would that lead to a similar overestimate of tram passengers, bearing in mind the fact that 83 per cent of the 2011 tram passengers will come from buses?
No. In effect, we are applying an uplift that brings into line what we feel the 2001 baseline level should be. That is then carried through into our forecasts. I do not feel that that would lead to an overestimate of tram ridership.
Okay. Given the importance of car travel time benefits to the economic case, were similar checks made of car volumes in the CSTM3 model and DAM?
CSTM3 has a robust calibrated and validated audit trail for the base year of 1997, which is set out in the documents that are referred to in our response. On DAM, given that we are considering a public transport scheme, the most important thing in establishing the financial case was for us to ensure that we were getting a robust model and robust demand and revenue estimates. On that basis, we took the view that we would focus on the PT side, which is when we did the counts.
But no data on car movements are available to us. The data for us to be able to validate what you say are missing.
No formal validation was undertaken on the 2001 DAM, but extensive and robust validation was undertaken on the 1997 CSTM3 model—the documents that are referred to set that out.
I have a supplementary question to keep things simple, because I like things that way. Do you not need to know the accurate number of vehicles in order to predict flow accurately? I refer to what you said right at the beginning. I need to know whether you think that your model predicts the actual number of vehicles. You started to talk about flow, but I am much more interested in whether you have the number of vehicles right.
We believe that we do.
You say that despite the discrepancy.
Do you mean on the public transport side?
Yes.
Yes, we do.
It is worth noting that we are talking about only one step in the process. There will be further development of an overall, robust case to put before the Executive and part of that work stream will include further refinements in the model. We certainly welcome the committee's independent review—as a risk manager, I think that it is most welcome. Obviously, we will take on board all the observations that are made by the committee's advisers and ensure that the issues are dealt with.
That is helpful to know.
I turn to bus and tram patronage along Leith Walk. We understand that there will be a reduction in the number of buses from around 49 buses an hour to around 27 buses an hour as a result of the trams. Even with a reduction to 27 buses an hour, those buses are likely to carry more passengers than the eight trams an hour. It seems that the bus-tram passenger split that is forecast will be achievable only if a substantial proportion of tram passengers allow buses to pass them while they are waiting for a tram. That needs to be substantiated. Will you clarify and explain how the numbers of tram and bus passengers along Leith Walk are derived from the expected rate of 27 buses and eight trams an hour?
Considering the split between bus and tram not only on Leith Walk but across the whole route is a function of the modelling process, which will consider every journey that is made and the available choices, whether between bus routes or between buses and trams. It will say that a route will take X amount of time by bus and that there is a bus every 10 minutes or that a person can get a tram with a run time of so many minutes and that that person will wait for it for so long. Considering the split is a function of the modelling process.
Can you tell me—you may have told the committee before, in which case I am sorry that I missed it—how you have factored people's destinations into the model? If someone is standing at one end of Princes Street and wants to go to the other end, a bus and a tram might appear equally attractive, but if they want to go from one end of Princes Street to somewhere down by the sea—beyond Leith and round to the left—that would be quite different and they would then favour the tram ahead of the bus. How have you worked that in?
The modelling will disaggregate the origins and destinations of all the trips made. If someone wants to go from the west end of Princes Street or from Haymarket to Leith, the modelling will simply say where the nearest bus stops and tram stops are and it will work out the best options. It will take account of where someone is and where they are going when determining the choice set. That applies wherever one goes by bus or tram. The normal issues of frequency, fares and run times come into that in the normal way. The modelling reflects the potential for tram access times to be longer than those for the bus, perhaps because of where someone is coming from or because the tram stops are more widely spaced than the bus stops.
I take it that you have worked in the figures that my colleague Rob Gibson highlighted.
Yes.
Given the overall costs, it seems that TIE has an allocation of £210 million for line 1 and that £11.6 million is to come from a private developer. At the same time, the estimate for the cost of the scheme is £219 million. That leaves only a small sum of money to cover contingencies, optimism bias and other aspects. Do you feel comfortable about that? What other sources of income can you identify at this stage that will perhaps create more reasonable levels to cover those costs?
When we spoke briefly about the matter last week, I made the point that the allocation of grant to lines 1 and 2 in the PFC for line 2 is not mandated by anyone. That was an estimate that we prepared in order not to be seen to be counting the £375 million twice across both lines. The figure of £210 million is not cast in stone, but your underlying point is still absolutely valid. If we build a network, there is only £375 million to spend and that has to be spread across the totality. If we do not build a network, the headroom between £375 million and what line 1 needs is very substantial.
What kind of value would you put on that?
For line 1, we have estimated that it would come to £300,000. For both lines, we have estimated a sum of £700,000.
That is relatively small beer compared to the overall costs.
Those estimates are for revenue accrued each year. If those numbers are multiplied by 30, they become quite large. We think that, over 30 years, advertising would raise between £5 million and £12 million. That is not an insignificant sum of money.
Yes, but if you fit that into your revenue estimates, in which you suggest that your operating revenue surplus will be something like 4 per cent a year, and take into account other aspects, such as replacement, I suggest that the sum raised from advertising is insignificant. At the same time, the margin of revenue surplus is extremely low, given the risks that the minister has told us that council tax payers have to take.
There are risks. However, line 1 is producing a surplus that is more than adequate to pay for the replacement and refurbishment life cycle costs. The net surplus from that set of cash flows contributes to the capital cost. Overall, depending on which component or element of the grant is offered to line 1, in isolation, the proposition is comfortable. As I said earlier, however, the issue of the stretch in the funding will arise when line 1 and line 2 combine to create a network and there is a fixed grant of £375 million.
Could you remind me, because my memory is not up to the task, whether that £375 million is at today's prices?
It is.
There has been a lot of discussion about the risk exposure on the capital expenditure, for obvious reasons. The Treasury identified a tendency of promoters and scheme developers to underestimate capital costs at the outset of projects. A number of reasons for that were put forward, including naivety or conspiracy, neither of which is tolerable.
That is full of merit, particularly given the Treasury's comments that you mentioned. However, I will just say that Scotland's nuclear power stations were pretty well built to budget.
Before we go too far down that track, I should say that the committee has no doubt about the promoter's intentions and professionalism or about the professionalism of its advisers. Nor do we doubt that you have learned from the experiences of others. However, we need to understand the long process that you have followed and be absolutely reassured that it will deliver what you hope that it will deliver—hence our questions.
It is fair-ish.
All right, work with me on this. Let us assume that it is a fair comment and that there are 50 per cent more cars on the road. Your model then says, "We cannot all squeeze in, given current capacity, so we'll just push some people to the sides." However, the reality is that I want to travel between 8 am and 9 am. I do not want to travel at the sides. Does your model over-egg the 50 per cent?
I would say not, because the model has been calibrated and validated to reflect observed behaviour. In that sense, my view is that the model is not over-egged.
Even though the model reflects observed behaviour, we will still all try to travel between 8 am and 9 am unless we do something different. Your model disperses that number; it does not do what we would do.
The model has been calibrated to reflect observed behaviour of when people choose to travel, which is influenced by levels of congestion and the available alternatives. In that sense, the model should be able to reflect the basis on which people want to travel and the ability of people to transfer to a different time period. The model is disaggregated by trip purpose. For example, a journey to work is much more fixed than a shopping trip. The model will reflect people's ability to transfer to a different time period depending on what they are doing for that particular journey.
Okay. Do you see the difficulty that I have with a model that does not necessarily relate to what I understand to be our behaviour?
The model was constructed explicitly to pick up a broad range of behavioural responses. It breaks down the levels of demand out there now, based on the reasons for those journeys. It reflects the fact that certain journeys, such as business trips and journeys to work, will be much less flexible in when they can be made.
I am conscious of time, but I have another quick question. As Phil Gallie said, the STAG appraisal says that there will be "severe levels of congestion". Does that tally with the comment that there is sufficient capacity at a strategic level?
It depends on what you mean by "congestion" and "capacity". Trips will still get through, but they will take a lot longer. That is the issue. When there is overcapacity in an area, that will mean that journey times are extended, but ultimately those trips will get through.
As the minister said this morning.
Exactly.
My final point is about utilities, although I am not looking for an immediate response. We asked for information about up-to-date estimated costs of the utility diversions because of the risk. Can we have that information, please?
Yes.
That would be helpful.
Meeting continued in private until 12:33.
Previous
Item in Private