Timescale for installing air source heat pumps to suitable buildings:-2023-24 – (1st quarter) - Feasibility studies will be carried out with business cases and funding applications submitted for suitable projects.2023-24 – (2nd quarter) - Apply, design and install power cable upgrades if required or – if the incoming power needs to be increased from the supplier.2023-24 – (3rd/4th quarter quarter) - Design, tender, appoint a contractor, planning permissions2024-25 – Installation of ASHP, radiators, pipework. S6W...