In addition, the post commissioning dry-docking, trials, and handover programme of 2 months did not include a period for snagging and defect rectification, provisions for complications associated with dry- docking and surveys and assumed ‘handover’ was a single day; we have now allowed for the post commissioning activities to take up to 3 months. Overall, t...