In parallel with this review the FMPG team, working closely and directly with CMAL representatives on site, has reconsidered the assumptions behind the commissioning programme and has concluded that given the risk of further ‘unknown’ legacy issues it will be prudent to make allowance to increase the commissioning period from 6 months to 8 months on 801 (Th...