- Asked by: Emma Harper, MSP for South Scotland, Scottish National Party
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Jenny Gilruth on 23 September 2022
To ask the Scottish Government for what reason Transport Scotland has reportedly exceeded its projected timescale of six months to carry out the roadworks between Cairnryan and Glenapp on the A77 by over four years, and whether it will provide (a) an urgent update on the status of these roadworks and (b) a timescale for their completion, in order to prevent any further disruption due to any single-lane traffic convoy systems for both HGV traffic, and other drivers, on the A77 arterial route.
Answer
I understand the frustration of local communities and users of the A77 and the difficulties and delays they cause, but these works are essential to maintain the safety and resilience of this section of the A77. Work at Carlock Wall commenced in February 2020 and was due to be completed by the end of that year. However, unforeseen adverse ground conditions were identified during construction. This included bed rock to support the new wall being much deeper than anticipated and significant volumes of unstable material on the existing slope face requiring additional stabilisation. Work started immediately to tackle both of these issues. Good progress has been made despite impacts associated with Covid-19. Carriageway re-opening to two way traffic is currently programmed to be completed by late Autumn 2022. Further landscaping and finishing works to areas remote from the carriageway will be complete in Spring 2023.
- Asked by: Colin Smyth, MSP for South Scotland, Scottish Labour
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Jenny Gilruth on 23 September 2022
To ask the Scottish Government how much funding for the upgrade of the A75 and A77 has been committed by the UK Government.
Answer
To date, we are not aware of the UK Government committing any funding for the upgrade of either the A75 or the A77. The UK Government’s Union Connectivity Review (UCR) published its interim findings in March 2021 and identified both the A75 and A77 as critical road transport corridors connecting Northern Ireland with Scotland and England.
At the same time, the UK Secretary of State for Transport announced that a £20m Union Connectivity Development Fund was available for advance design / development on a select number of transport corridors, including the A75. It is not clear if any of that funding has been spent on preliminary work for the A75.
The Final UCR Report was published in November 2021 and recommended that the UK Government commit funding to support the significant upgrade of the A75. The failure to mention the A77 suggests it will no longer be considered a priority for upgrading.
- Asked by: Graham Simpson, MSP for Central Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Jenny Gilruth on 23 September 2022
To ask the Scottish Government when the Minister for Transport will next meet representatives from Glasgow Airport to discuss any challenges facing Scotland's aviation industry.
Answer
I refer the member to the answer to question S6W-10967 on 23 September 2022. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers .
- Asked by: Neil Bibby, MSP for West Scotland, Scottish Labour
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Jenny Gilruth on 23 September 2022
To ask the Scottish Government how the alcohol ban on ScotRail trains is enforced, and who it is enforced by.
Answer
The alcohol ban on ScotRail trains and in stations is enforced by the British Transport Police who assist railway staff to ensure that the rules are being adhered to as far as possible.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 06 September 2022
-
Current Status:
Answered by Ivan McKee on 23 September 2022
To ask the Scottish Government for what reason the Isle of Barra was not included as a proposed site as part of the Scottish 4G Infill Programme.
Answer
In the development phase of the Scottish 4G Infill Programme, we analysed future predicted coverage data supplied by mobile network operators. These indicated plans for commercial deployment on Barra. State Aid regulations then in force precluded S4GI deployment where there was planned commercial investment. On that basis, it was not possible to include candidate locations on Barra within the scope of the programme, and as consulted on as part of public consultations conducted by the programme in 2017 and in 2018.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Thursday, 01 September 2022
-
Current Status:
Answered by Jenny Gilruth on 23 September 2022
To ask the Scottish Government what recent (a) discussions it has had on and (b) consideration it has given to improving lifeline interisland services in Orkney.
Answer
I met with Orkney Islands Council on 8 th August during my visit to the Northern Isles, where we discussed a range of issues including inter-island connectivity.
The Scottish Government recognises the challenges for local authorities with responsibility for ferries and has provided more than £136m over the last 5 years through the Local Government settlement and Specific Grant. A total of £33.095m has been made available for local authorities in 2022-23, including £13.402m for Orkney, which fully funds the Council to operate inter-island ferry services.
- Asked by: Beatrice Wishart, MSP for Shetland Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 26 August 2022
-
Current Status:
Answered by Michael Matheson on 23 September 2022
To ask the Scottish Government what assessment it has made regarding the location of the three Shetland ScotWind projects, announced on 22 August 2022, overlapping with fishing grounds for the Shetland fishing fleet.
Answer
The three projects now offered Option Agreements from Crown Estate Scotland under the ScotWind clearing round are located entirely within the SMP-OWE Plan Option NE1. Adoption of the SMP-OWE and the seabed leasing round followed the delivery of a Sustainability Appraisal, which included a Social and Economic Impact Assessment (SEIA). This SEIA estimated the negative impact of the Plan Option NE1 and the SMP-OWE as a whole, based on a series of development scenarios. Through that process and direct engagement with the fishing sector, the Plan Option was reduced further to avoid overlap with fishing activity. The SMP-OWE planning process considered fisheries data through an assessment of spatial and economic data, alongside consultation and steering group information. Although the planning process attempted to minimise impact on a wide range of receptors, there remains some overlap with receptors and we would expect engagement with the fishing sector as project applications are developed to be critical to determining the ultimate footprint of any development.
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Michael Matheson on 23 September 2022
To ask the Scottish Government how much has been (a) budgeted for and (b) distributed from the Fuel Insecurity Fund in each year of its operation.
Answer
The Fuel Insecurity Fund was first established in the winter of 2020, as part of the wider Winter Support Fund, to help households struggling with their energy costs who were at risk of severely rationing, or self-disconnecting entirely because they could not afford their energy costs.
Fuel Insecurity Fund |
Year | Budgeted | Distributed |
2020-21 | £7m | £3.595m |
2021-22 | £10m | £10m |
2022-23 | £10m | £4.1m* |
In financial year 2020-21, £3.595m was spent by our partners.
As set out in our Programme for Government this year we have committed to using the Emergency Budget Review to double our Fuel Insecurity Fund to £20 million, to provide further support for the many households across Scotland who are already struggling to pay their bills and heat their homes.
* Full current 2022-23 budget of £10 million has been allocated across our third sector partner organisations, which they have the flexibility to drawdown in the financial year to best support and target customer needs up to the end March 2023.
- Asked by: Graham Simpson, MSP for Central Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Jenny Gilruth on 23 September 2022
To ask the Scottish Government when the Minister for Transport last visited Glasgow Airport.
Answer
I have not visited Glasgow Airport during my time as Minister for Transport, however I look forward to meeting with the CEO of AGS Airports on 5 October 2022.
- Asked by: Beatrice Wishart, MSP for Shetland Islands, Scottish Liberal Democrats
-
Date lodged: Friday, 26 August 2022
-
Current Status:
Answered by Michael Matheson on 23 September 2022
To ask the Scottish Government what consultation it will undertake with the fishing industry regarding the three Shetland ScotWind projects announced on 22 August 2022.
Answer
Following the ScotWind and clearing announcements, the Scottish Government is undertaking a review and re-assessment of the Sectoral Marine Plan for Offshore Wind Energy (SMP-OWE). As part of this process, the draft review of the SMP-OWE and associated assessments will be consulted upon in Spring/Summer 2023. The consultation is planned to last 12 weeks. Fisheries representatives will also be asked to form part of the review steering group.
The three projects that were successful at clearing for NE1 will be required to apply for relevant licences for activities in the marine environment and for a consent to generate electricity. As part of this process, developers will be required to engage directly with the local fishing industry. In addition, Marine Scotland Licensing Operations Team will run a statutory consultation for each project.