- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Taken in the Chamber on 23 September 2026
To ask the Scottish Government what its response is to Audit Scotland’s report, Scotland’s colleges 2026.
Answer
Taken in the Chamber on 23 September 2026
-
Current Status:
Withdrawn
- Asked by: Paul McLennan, MSP for East Lothian Coast and Lammermuirs, Scottish National Party
-
Date lodged: Tuesday, 18 August 2026
-
Current Status:
Answered by Ivan McKee on 16 September 2026
To ask the Scottish Government whether the Programme for Government 2026-27 will be closely aligned or mapped to the revised National Performance Framework.
Answer
In the Programme for Government, the First Minister states that his priorities and ambitions will help build a Scotland that is fair, healthy, prosperous, secure, skilled, sustainable, and connected. The Scottish Government’s five-year (corporate) plan explains that we will continue to improve how we track progress towards the National Outcomes by establishing a new system in 2026. I have written to committees this week regarding the proposed National Outcomes. We intend to launch the reformed National Performance Framework, including the National Indicators, later this year and will keep Parliament informed of progress.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 25 August 2026
-
Current Status:
Answered by Gillian Martin on 16 September 2026
To ask the Scottish Government, following the departure of Dr Calum MacLeod, how many Land Commissioners currently serve on the board of the Scottish Land Commission; for what reason, in the context of public service reform, it has not yet recruited a replacement for Dr MacLeod, whether it plans the board to return to its full statutory complement of five Commissioners and, if (a) so, by what date it expects to do so and (b) not, (i) on what legal authority it is operating with fewer than five Commissioners and (ii) whether it will lay regulations under section 4(5) of the Land Reform (Scotland) Act 2016 to alter the number of Commissioners.
Answer
I wrote to the Parliament’s Rural Affairs Committee on 3 September 2026 to notify them of my intention to bring forward a Scottish statutory instrument which, subject to Parliament’s consideration, will amend the number of Land Commissioners at the Scottish Land Commission from five to four. We expect the instrument to be laid in early October. The letter can be found on Parliament’s website: https://www.parliament.scot/chamber-and-committees/committees/current-and-previous-committees/session-7/rural-affairs-committee/correspondence/2026/land-reform-scotland-act-2016-of-3-september
Following Dr Calum MacLeod's resignation earlier this year, there are currently four Land Commissioners serving as members of the Scottish Land Commission. The Tenant Farming Commissioner also serves as a member of the Commission.
- Asked by: Paul McLennan, MSP for East Lothian Coast and Lammermuirs, Scottish National Party
-
Date lodged: Tuesday, 18 August 2026
-
Current Status:
Answered by Ivan McKee on 16 September 2026
To ask the Scottish Government how it plans to address any gaps in data in order to improve reporting against the National Indicators.
Answer
The Scottish Government is committed to improving data availability and quality to support reporting against the National Indicators. The National Indicators bring together data published elsewhere and do not collect data specifically for monitoring. They provide a streamlined measure of progress across the work of the Scottish Government, the wider public sector, and Scotland more broadly. As source data improves, this will be reflected in the National Indicators.
- Asked by: Paul McLennan, MSP for East Lothian Coast and Lammermuirs, Scottish National Party
-
Date lodged: Tuesday, 18 August 2026
-
Current Status:
Answered by Ivan McKee on 16 September 2026
To ask the Scottish Government whether it will provide details of its approach and timeline for the development of the National Indicators that underpin the National Outcomes, and how it plans to consult with relevant sectors and organisations as part of this process.
Answer
The Scottish Government is in the process of finalising a streamlined set of National Indicators, drawing on international good practice such as the recent United Nations (UN) Expert Group on Beyond GDP report and which aligns with the UN Sustainable Development Goals. The Chief Statistician will recommend a National Indicator set to ministers. We intend to launch the reformed NPF, including the National Indicators, later this year and will continue to keep Parliament informed of progress.
- Asked by: Paul McLennan, MSP for East Lothian Coast and Lammermuirs, Scottish National Party
-
Date lodged: Tuesday, 18 August 2026
-
Current Status:
Answered by Ivan McKee on 16 September 2026
To ask the Scottish Government what progress has been made in reviewing the National Performance Framework, including when the revised framework and National Outcomes will be published.
Answer
The Scottish Government is in the process of finalising the National Performance Framework (NPF) following an extensive programme of engagement earlier this year which included organisations from a range of sectors. I have written to committees this week to inform them of the proposed new National Outcomes that form part of the NPF, and that we intend to launch the reformed NPF, including the National Indicators, later this year. I will continue to keep Parliament informed of progress. We will also publish background information on the process as part of the evidence base
- Asked by: Paul McLennan, MSP for East Lothian Coast and Lammermuirs, Scottish National Party
-
Date lodged: Friday, 04 September 2026
-
Current Status:
Answered by Alison Thewliss on 16 September 2026
To ask the Scottish Government whether it will publish any cost estimates, financial modelling or resource assessments relating to the implementation of the commitments contained in Palliative Care Matters for All: palliative care strategy 2025 to 2030.
Answer
The Scottish Government’s Palliative Care Strategy 2025-2030 - Palliative Care Matters for All – was published on 10 September 2025, alongside an initial three year delivery plan containing 23 actions intended to deliver on the eight strategy outcomes.
Whilst specific cost estimates, financial modelling or resource assessments relating to the implementation of the overall strategy have not been published, we have worked closely with delivery partners to agree the work plans and project costs associated with the delivery of the actions.
We are also committed to publishing annual strategy progress reports providing updates on the delivery of the actions. The first of these will be published before the end of the year and will outline how we are seeking to ensure value for money and best use of resources throughout delivery of the strategy.
- Asked by: Sanne Dijkstra-Downie, MSP for Edinburgh Northern, Scottish Liberal Democrats
-
Date lodged: Thursday, 03 September 2026
-
Current Status:
Answered by Gillian Martin on 16 September 2026
To ask the Scottish Government how many high-priority illegal waste sites SEPA is currently monitoring, broken down by (a) estimated tonnage of waste and (b) site location.
Answer
SEPA has advised that it uses a risk model that provides a score to allow prioritisation. At the start of 2026-27 there were 76 sites classified as high priority. Of these, 45 sites were identified as deposit of waste or disposal of waste by burial. Investigation and Enforcement action has concluded at one site with full compliance achieved and this will not be included in the data set.
Since the start of 2026-27 a further six high-priority illegal waste sites have been identified, providing a total of 50 high-priority waste sites being actively investigated. Of these 50 sites, 7 have been sufficiently disrupted to reduce the risk to the environment and communities however, investigations will continue until the identified outcome has been achieved.
High priority 1 monitored illegal waste sites.
Site Location (SEPA Geographic Locations) | Site identifier | Estimated Tonnage |
| Argyll, Hebrides and South Highlands | Site 1 | 145 |
| Edinburgh, Lothian and Borders | Site 1 | 725 |
| Site 2 | 725 |
| Fife, Angus and Dundee | Site 1 | 725 |
| Site 2 | >725 |
| Site 3 | 145 |
| Site 4 | 145 |
| Falkirk, Alloa, Stirling and Perth | Site 1 | 300 |
| Grampian & Speyside | Site 1 | 300 |
| Site 2 | 145 |
| Greater Glasgow and Clyde Estuary | Site 1 | 300 |
| Site 2 | >725 |
| Site 3 | 75 |
| Site 4 | 300 |
| Site 5 | >725 |
| Site 6 | 725 |
| Site 7 | 145 |
| Site 8 | >725 |
| Site 9 | 145 |
| Site 10 | 145 |
| Site 11 | >725 |
| Site 12 | 725 |
| Lanarkshire | Site 1 | >725 |
| Site 2 | 725 |
| Site 3 | 725 |
| Site 4 | >725 |
| Site 5 | 300 |
| Site 6 | 725 |
| Site 7 | 145 |
| Site 8 | 300 |
| Site 9 | >725 |
| Site 10 | 725 |
| Site 11 | >725 |
| Site 12 | 145 |
| Site 13 | >725 |
| Site 14 | >725 |
| Site 15 | 145 |
| Site 16 | 145 |
| North Highland and Northern Isles | Site 1 | 145 |
| Site 2 | 300 |
| Site 3 | 300 |
| Site 4 | 300 |
| Site 5 | 145 |
| South West Scotland | Site 1 | 145 |
| Site 2 | 725 |
| Site 3 | 145 |
| Site 4 | 300 |
| Site 5 | >725 |
| Site 6 | >725 |
1 For prioritisation purposes SEPA do not record exact or estimated tonnages. SEPA record estimated financial benefit so a calculation using estimated financial benefit and the UK landfill tax rate of £130.75 per tonne has been used to estimate tonnage. SEPA’s Digital Transformation Project will improve the data captured as part of a centralised repository of investigations. Where SEPA investigations are still active the tonnage may not yet be fully determined or it may be part of the evidence. As such, any data released into the public domain could compromise the investigation, influence witness statements, affect future court proceedings or impact the privacy of those involved. The data provided is set out to protect detection and investigative processes.
Throughout an investigation the calculated tonnage on site may increase or decrease, e.g. it may be determined that the illegal deposit initially identified as being above ground extends below ground level upon further investigation resulting in an increase in tonnage. Definitive tonnages of waste on significant waste disposal sites will only ever be available following site removal of the waste.
The data provided is based on the investigation progress as of 7 September 2026.
Further Information is available from SEPA.
- Asked by: Sanne Dijkstra-Downie, MSP for Edinburgh Northern, Scottish Liberal Democrats
-
Date lodged: Thursday, 03 September 2026
-
Current Status:
Answered by Gillian Martin on 16 September 2026
To ask the Scottish Government whether it is satisfied that the current definition and recording of waste crime adequately capture large-scale illegal waste operations, including sites where waste is deliberately stored or buried over an extended period, rather than being disposed of through fly-tipping.
Answer
For information of this nature, you may wish to contact the Scottish Environment Protection Agency (SEPA), as they may be able to assist further.