- Asked by: Brian Whittle, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 24 January 2023
-
Current Status:
Answered by Lorna Slater on 7 February 2023
To ask the Scottish Government, further to the answer to question S6W-13230 by Lorna Slater on 20 December 2022, over what period the data used for the modelling by Zero Waste Scotland was collected from local authorities.
Answer
The data used was the last full year of data prior to modelling, wherever possible. This was not always available and, in those circumstances, Zero Waste Scotland agreed with the Local Authority the most appropriate data to be used. The model was then handed over to the Local Authority, allowing updates to be made if more appropriate or recent data became available.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 23 January 2023
-
Current Status:
Answered by Lorna Slater on 7 February 2023
To ask the Scottish Government how much it has spent to date on a Biodiversity Investment Plan, as set out in the new Scottish Biodiversity Strategy, and how many civil servants have worked on delivering this.
Answer
Following the recent publication of the draft biodiversity strategy, a delivery plan is now being developed and this will include the development of an investment plan. The delivery plan is being led jointly by Scottish Government and NatureScot officials, drawing on engagement from key policy areas and across a wider network which includes significant stakeholder engagement. No expenditure has therefore been directly devoted to the development of the Biodiversity Investment Plan yet.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 23 January 2023
-
Current Status:
Answered by Lorna Slater on 7 February 2023
To ask the Scottish Government whether any external organisations or individuals have provided paid consultancy services to date in relation to the development of a Biodiversity Investment Plan, as set out in the new Scottish Biodiversity Strategy, and, if so, which external organisations or individuals have done so.
Answer
No organisations or individuals have provided paid consultancy services in relation to the development of a Biodiversity Investment Plan.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Neil Gray on 7 February 2023
To ask the Scottish Government whether it will provide a breakdown of any (a) grant funding and (b) loans provided by Architecture and Design Scotland for each year since 2007-08.
Answer
Architecture and Design Scotland works to help deliver Scottish Ministers’ policies and objectives for the built and natural environment by providing advice, resources and advocacy, and through a programme of projects and initiatives. It does not provide grants or loans to external organisations.
In 2014-15 Architecture and Design Scotland facilitated the Stalled Spaces Scotland project on behalf of Scottish Government which provided funding to local authorities to enable stalled space projects to be delivered with communities. The following table details the local authorities and amounts awarded. Those organisations were required to match fund the award.
Local Authority Area | Funding awarded (£) |
Angus | 10,000 |
Argyll and Bute | 5,000 |
East Dunbartonshire | 15,000 |
East Renfrewshire | 10,000 |
Fife | 12,000 |
North Ayrshire | 15,000 |
Renfrewshire | 10,000 |
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
Submitting member has a registered interest.
-
Current Status:
Answered by Tom Arthur on 7 February 2023
To ask the Scottish Government whether it can provide an estimate of how long it will take Registers of Scotland to clear any backlog of title holders who are awaiting copies of their title deeds.
Answer
This is a question for the Keeper of the Registers of Scotland (RoS). She advises me that, following the impact of the pandemic, RoS has stabilised and started to improve the position this year, in line with the strategy set out in their Corporate Plan .
RoS has committed to clearing the stock of older casework within the duration of the current Corporate Plan. RoS is in fact slightly ahead of target on their strategic objectives and the series of Key Performance Indicators (KPIs) used to measure progress. KPI statistics are published quarterly on the RoS website .
- Asked by: Miles Briggs, MSP for Lothian, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Neil Gray on 7 February 2023
To ask the Scottish Government how many libraries have closed in each year since 2009.
Answer
Public Library services in Scotland are devolved to local authorities which have a statutory duty to secure the provision of adequate library facilities for all persons resident in their area.
No Scottish Libraries have permanently closed in the last three reporting years. The following table from the Scottish Library and Information Council provides data, compiled by the Chartered Institute of Public Finance and Accountancy (CIPFA), capturing the number of service points and net increase / decrease per year between 2009-10 – 2021-22. Information for 2022-23 will be available at the end of the current financial year.
Year | Total Service Points | Net Increase/decrease |
2009-2010 | 627 | 0 |
2010-2011 | 619 | -8 |
2011-2012 | 610 | -9 |
2012-2013 | 606 | -4 |
2013-2014 | 609 | 0 |
2014-2015 | 603 | -3 |
2015-2016 | 588 | -15 |
2016-2017 | 558 | -30 |
2017-2018 | 556 | -2 |
2018-2019 | 543 | -13 |
2019-2020 | 544 | +1 |
2020-2021 | 544 | 0 |
2021-2022 | 544 | 0 |
- Asked by: Martin Whitfield, MSP for South Scotland, Scottish Labour
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Shirley-Anne Somerville on 7 February 2023
To ask the Scottish Government what requirements there are to undertake a Children’s Rights and Wellbeing Impact Assessment (CRWIA) as part of designing and planning new schools.
Answer
Child Rights and Wellbeing Impact Assessment (CRWIA) is a process through which authorities can identify, research, analyse and record the anticipated impact of any proposed measure – including new schools - on children’s human rights and wellbeing.
The CRWIA provides a template to help assess the impact of the measure on the Articles of the UNCRC, and consider how implementation of it can help progress the realisation of children’s rights, and support and promote the wellbeing of children and young people in Scotland.
The Learning Estate Strategy 2019 which underpins the Learning Estate Investment Programme incorporates a requirement to consult in its guiding principles. The subsequent CRWIA guidance Nov 2021 states that the CRWIA template “is a tool that can help inform and meet these duties”. The Learning Estate Investment Programme will signpost the CRWIA guidance and templates as part of the shared learning event programme.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Neil Gray on 7 February 2023
To ask the Scottish Government in what ways the Architecture and Design Scotland report, Designing for a Changing Climate: Carbon Conscious Places, has made a material difference in the way in which (a) it and (b) local authorities approach (i) local architectural projects and (ii) planning decisions.
Answer
The Architecture and Design Scotland report, Designing for a Changing Climate: Carbon Conscious Places , offers examples of good practice to support a whole place approach to responding to the climate imperative, carbon targets and local places.
The key findings of the report were disseminated widely through a public online launch, presentations to Young Planners Scotland conference, the Scotland's Climate Assembly, and promoted through articles in professional journals. The launch of the report was covered on BBC and STV TV, reaching a wide audience.
The report is included as a reference document within the Scottish Government Update to the Climate Change Plan (2020) and has informed the offer from the Key Agencies Group to local authorities for support with developing the new style of Local Development Plans. The publication webpage was viewed over 3,000 times between October 2020 and January 2023.
The impact on approaches, projects and decisions has not yet been formally evaluated.
- Asked by: Craig Hoy, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 26 January 2023
-
Current Status:
Answered by Maree Todd on 7 February 2023
To ask the Scottish Government what percentage of people with diabetes have achieved optimal glycaemic control, defined as <58mmol/mol in adults and <48mmol/mol in children, at one year post diagnosis in each year since 2007.
Answer
The information requested is not held centrally.
- Asked by: Craig Hoy, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 26 January 2023
-
Current Status:
Answered by Humza Yousaf on 7 February 2023
To ask the Scottish Government, further to the answer to question S6W-13437 by Humza Yousaf on 24 January 2023, (a) how much it has spent and (b) what quantifiable effect any spending has had on assisting to bridge the gap between service demand and capacity within the health and care system in relation to (i) online training provision within the Scotland Deanery, (ii) train-the-trainer for “simulation” training across a number of specialties and in specific procedures, such as in cystoscopy, (iii) virtual reality pilots for communications training in handling stressful situations in pre-hospital emergency care and mental health tribunals, (iv) mental health simulation training, (v) virtual reality simulators, including six endoscopy simulators in six different health boards, alongside a national introductory course covering cancer diagnosis and (vi) a national urology simulator and learning programme.
Answer
The Scottish Budget provided baseline funding of over £492 million to NHS Education for Scotland in 2022-2023, it is for NHS Board to determine how they use this funding. In addition to this, further funding has been made available to NHS Education for Scotland to support specific programmes of work including:
£22.3 million is provided towards the improvement of Mental Health Training and £3.7 million for the NHS Scotland Academy which offers accelerated training programmes to those working, and soon to be working, across many roles within Health and Social Care. Much of the training and education activity delivered by NHS Education for Scotland is supported and enhanced through digital solutions.
We continually monitor the sufficiency of education and training support across NHS Scotland as we work to deliver a sustainable Health and Social Care workforce and implement improvements in patient care. As part of this, The Scottish Government has regular strategic engagement with NHS Education for Scotland regarding its priorities. The Scottish Government also has a number of other mechanisms to oversee and review each Board’s performance. The Annual Reviews held by Ministers remain an important part of the accountability process as do Board Annual Operating plans, building on the local governance arrangements which form part of Board structures.