- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the planned new Edinburgh Eye Pavilion, and how this compares to its original targets.
Answer
It is not possible to compare the current proposal with the previous one at this point. The Full Business Case is still under development and the proposed number of patients treated will be revised to reflect the impact of inflation, net zero carbon targets, plot change and updated clinical brief to align with national treatment targets.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Fife, and what the revised cost is as of 30 June 2023.
Answer
This information is available in the Infrastructure Investment Plan 2021-22 to 2025-26: major capital projects progress update - March 2023 - gov.scot (www.gov.scot) the Scottish Government published on 20 June 2023. The plan outlines the progress and current projected costs of NTC Fife as well NTC Golden Jubilee Phase 2, NTC Grampian, NTC Lothian, NTC Highland, NTC Forth Valley and NTC Ayrshire and Arran.
- Asked by: Clare Haughey, MSP for Rutherglen, Scottish National Party
-
Date lodged: Tuesday, 11 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the most recent level of health spending per person is in Scotland, and what information it has on how this compares with spending in (a) England and (b) Wales.
Answer
Based on HM Treasury’s Country and Regional Analysis (2021-22), frontline Health spend per head in Scotland is £3,377, which is £323 (10.6%) higher than in England and £74 (2.2%) higher than in Wales. Proportionally, this equates to almost £1.8 billion more spending on frontline health services in Scotland compared to England, and almost £405 million more compared to Wales – equivalent to around 44,000 and 10,000 nurses, respectively.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government how many of the 1,500 new clinical and non-clinical staff, committed to in its NHS Recovery Plan, will be based in the National Treatment Centre Ayrshire and Arran.
Answer
National Treatment Centres (NTCs) require an appropriate mix of new and experienced staff to operate safely and efficiently. While initial modelling of projected workforce requirements was undertaken to inform earlier phases of our planning for the National Treatment Centre programme, detailed plans relating to the size and composition of the workforce for NTC Ayrshire and Arran will be developed by the Board and submitted to the Scottish Government as part of the wider planning and approval process for the site in question.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Lanarkshire, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
I refer the member to the answer to question S6W-19985 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Highland, and what the revised cost is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19963 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Tayside, and what the revised timetable is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19984 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Lothian, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
I refer the member to the answer to question S6W-19985 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Lothian, and what the revised timetable is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19984 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Russell Findlay, MSP for West Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 14 July 2023
-
Current Status:
Answered by Angela Constance on 7 August 2023
To ask the Scottish Government how many reported incidences of fire-raising of vehicles within the (a) Scottish Prison Service estate and (b) estate of Scotland's two privately operated prisons there have been in each of the last five years.
Answer
I have asked Teresa Medhurst, Chief Executive of the Scottish Prison Service (SPS), to respond. Her response is as follows:
In each five years, there have been a total of 8 incidences of fire-raising of vehicles, shown in the following table:
| Scottish Prison Service estate | Privately Operated prisons |
2018 – 2019 | 1 | 0 |
2019 – 2020 | 1 | 0 |
2020 – 2021 | 4 | 0 |
2021 – 2022 | 0 | 1 |
2022 – 2023 | 0 | 1 |
SPS take incidents such as fire-raising of vehicles belonging to prison staff incredibly seriously. Where such incidents occur, these will be reported to Police Scotland for further investigation.
A series of protective measures are in place within establishments and will compliment any support offered by Police Scotland.