- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government, before an order was placed for Hull 802, whether an alternative option of ordering two smaller vessels to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes was considered, and, if it was the case, for what reason any such alternative option was rejected, and, if it was not the case, for what reason such an alternative option was not considered.
Answer
The proposal for the procurement of what became vessels 801 and 802 was set out in the Vessel Replacement and Deployment Plan (VRDP) Annual Report 2014 vrdp-annual-report-2014.pdf (transport.gov.scot)
The recently published Ferries Plan 2013-2022 had concluded that the level of services then in place on the Uig-Tarbert/Lochmaddy routes met identified community needs. Vessel 802 was earmarked for initial deployment to those services, to bring additional vehicle deck capacity; noting that the deployment plan would be reviewed prior to delivery.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government whether the two vessels which CMAL has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes could have operated from ferry terminals at (a) Uig, (b) Lochmaddy and (c) Tarbert without the reconstruction and dredging operations being carried out at each terminal to allow their use by Hull 802.
Answer
The vessels currently under construction at Cemre could not have served the ports at Uig, Lochmaddy and Tarbert without changes to infrastructure. The works at each of the ports are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government when it last received an update from CMAL on the progress of the two ferries that it has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
Answer
The Scottish Government receives regular updates on all new vessel builds. The contract for the Little Minch vessels was signed on 11 January and all agreements including full Builders Refund Guarentees were put in place recently. The latest update was received from CMAL on 20 February 2023.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government whether there have been any design changes to the two vessels that CMAL has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
Answer
CMAL as procuring authority have confirmed that there have been no changes to the design or specifications for the vessels ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government what the total cost will be of the two vessels that CMAL has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
Answer
The Scottish Government announced up to £115 million funding for the two Little Minch vessels, and associated port works and project costs, in October 2022. The total costs of the vessels are commercially confidential.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 21 February 2023
To ask the Scottish Government what the (a) length, (b) beam and (c) maximum operational draught of MV Hebrides is.
Answer
MV Hebrides is 99 metres in length, 15.8 metres wide and her operational draught, which is the vertical distance between the waterline and the bottom of the vessel’s hull, is 3.3 metres.
Further information is available on CalMac’s website by following the link: https://www.calmac.co.uk/fleet/mv-hebrides
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Jenny Gilruth on 10 February 2023
To ask the Scottish Government what representations it has received from local residents and business owners on future transport options for the Corran Narrows, including the possibility of a fixed link.
Answer
The Scottish Government has received representations from local residents and MSPs regarding transport options for the Corran Narrows, however, Scottish Ministers have no locus in this decision.
Transport links across the Corran Narrows is wholly the responsibility of The Highland Council and as such, any decision to replace ferries or deliver a fixed link and funding of this, would be a matter for the Local Authority.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Jenny Gilruth on 10 February 2023
To ask the Scottish Government what assessment it has undertaken of the potential economic and social benefits of a fixed link across the Corran Narrows.
Answer
The Scottish Government has not undertaken any assessments regarding the social and economic benefits of a fixed link across the Corran Narrows.
The Scottish Government is aware of work carried out by HITRANS on behalf of The Highland Council to consider a range of options for the Corran Narrows. As any decision to deliver a fixed link would be a matter for Local Authority, it would not be for the Scottish Government to undertake a socioeconomic assessment.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Jenny Gilruth on 10 February 2023
To ask the Scottish Government what consultation it has undertaken with local residents and business owners on future transport options for the Corran Narrows, including the possibility of a fixed link.
Answer
Scottish Ministers have no locus in this decision. Transport links across the Corran Narrows are wholly the responsibility of The Highland Council and, as such, any decision to replace ferries or deliver a fixed link (including funding of this) would be a matter for the Local Authority. Therefore, the Scottish Government has not undertaken any specific consultation regarding future transport options for Corran Narrows.
The Scottish Government recently completed a national review of future transport infrastructure. The second Strategic Transport Projects Review (STPR2) was an example of effective collaboration with stakeholders and the public. It included a considerable programme of engagement activities at a national and regional level with participation from local residents and business owners at various points throughout the process, including within the Lochaber area.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Jenny Gilruth on 10 February 2023
To ask the Scottish Government what consideration it has given to the viability of a fixed link across the Corran Narrows.
Answer
The Scottish Government has not undertaken any assessments regarding the viability of a fixed link across the Corran Narrows.
The Scottish Government is aware of work carried out by HITRANS on behalf of The Highland Council to consider a range of options for the Corran Narrows. As any decision to deliver a fixed link would be a matter for the Local Authority, it would not be for the Scottish Government to undertake an assessment of viability.