- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government how many of the 1,500 new clinical and non-clinical staff, as committed to in its NHS Recovery Plan, will be based in the National Treatment Centre Fife.
Answer
National Treatment Centres (NTCs) require an appropriate mix of new and experienced staff to operate safely and efficiently. Management information provided by NHS Education for Scotland (NES) shows that at 31 March 2023, 93 people were employed in NTC Fife. 23 are new entrants meaning they are undertaking their first role in NHS Scotland. Whilst these figures from NES are classed as management information at this stage, NES will continue to work with data providers to develop these as Official Statistics. The next step in this process will be to release these statistics within the NHS Scotland workforce publication as Experimental Statistics in December 2023. NTC workforce data will be reported every six months thereafter.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Fife, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
The following table outlines the current projected activity for National Treatment Centres during 2023-24 with reference to the position in the NHS Recovery Plan.
NTC projected 2023-24 activity
NTC | Current projection (procedures) | Comparison with NHS Recovery Plan position |
Golden Jubilee Phase 1 | 12,481 | Higher |
Fife | 472 | Higher |
Highland | 1,586 (partial) | Lower – see Note 1 |
Forth Valley | 450 (partial) | Lower – see Note 2 |
Golden Jubilee Phase 2 | 390 (partial) | Lower – see Note 3 |
Notes
1. Part-year figure due to opening during 2023-24: current projection excludes additional Ophthalmology capacity due to commence in Autumn and for which planned activity is in the process of being finalised.
2. Part-year figure due to opening during 2023-24: full-year activity as per NHS Recovery Plan will be achieved from 1 April 2024.
3. Part-year figure due to opening during 2023-24: full-year activity as per NHS Recovery Plan will be achieved from 1 April 2024.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Lothian, and what the revised cost is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19963 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Golden Jubilee Phase 2, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
I refer the member to the answer to question S6W-19965 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Ayrshire and Arran, and what the revised timetable is as of 30 June 2023.
Answer
The following table outlines the opening dates set out in the 2020 NHS Recovery Plan and the current projected opening dates for National Treatment Centres without approved Full Business Cases:
NTC | Opening Date in 2020 Recovery plan | Currently Projected Opening Date |
Ayrshire & Arran | 2025 | To be agreed at FBC |
Tayside | 2025 | To be agreed at FBC |
Lothian | 2025 | To be agreed at FBC |
Lanarkshire | 2026 | To be agreed at FBC |
Grampian | 2025 | To be agreed at FBC |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Fife, and what the revised timetable is as of 30 June 2023.
Answer
The following table outlines the opening dates set out in the 2022 update to the NHS Recovery Plan and the current projected opening dates for National Treatment Centres with approved Full Business Cases:
NTC | Opening Date in 2022 Recovery plan update | Currently Projected Opening Date |
Golden Jubilee Phase 1 | December 2020 | December 2020 |
Fife | Early 2023 | Opened March 2023 |
Highland | Spring 2023 | Opened April 2023 |
Forth Valley | Spring 2023 | End of 2023 |
Golden Jubilee Phase 2 | Late summer 2023 | End of 2023 |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Lanarkshire, and what the revised cost is as of 30 June 2023.
Answer
It is not possible to compare the current proposal with the previous costs at this time. The Full Business Case for NTC-Lanarkshire is still under development and project cost estimates will be revised to reflect the impact of inflation, net zero carbon targets, plot change and updated clinical brief to align with national treatment targets.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Golden Jubilee Phase 1, and what the revised timetable is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19964 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Tayside, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
I refer the member to the answer to question S6W-19985 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Lothian, and what the revised timetable is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19984 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers