- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 6 August 2020
To ask the Scottish Government what the total cost is of vessels 801 and 802 being built at Ferguson Marine, including costs relating to nationalising the yard and any commercial advice to date, and the projected cost to completion.
Answer
The total spend to date on vessels 801 and 802 is approximately £112 million. This includes the direct costs of designing and building the vessels as well as the costs associated with nationalising Ferguson Marine.
With regards to estimated cost to completion, we await a revised schedule and cost which takes into account the impact of Covid-19.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Thursday, 16 July 2020
-
Current Status:
Answered by Jeane Freeman on 6 August 2020
To ask the Scottish Government how many people who have a learning disability have been issued with a Do Not Resucitate (DNR) order since 1 March 2020, also broken down by NHS board area.
Answer
The Scottish Government does not centrally collect information or data relating to the use of Do Not Attempt Cardiopulmonary Resuscitation (DNACPR) forms.
As with all other clinical treatments, decisions about CPR should be based on the individual clinical circumstances and wishes of the patient, recorded appropriately and updated when medical circumstances change. This recording is done in hard copy on a DNACPR form, the existence of which is then recorded on an individual’s Key Information Summary. Such information is only shared for the purposes of direct care and is therefore not centrally collected.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 14 July 2020
-
Current Status:
Answered by Jeane Freeman on 6 August 2020
To ask the Scottish Government, further to the answer to question S5W-29039 by Jeane Freeman on 2 July 2020, when it expects Public Health Scotland to publish this data.
Answer
Public Health Scotland advise that this data is not available retrospectively as requested. Public Health Scotland has started development work to link the delayed discharge and testing datasets, which will provide this information from March 2020 onwards, for the small cohort of patients who experience a delay.
Public Health Scotland is also working towards improving data on the discharge destination of all future hospital discharges.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 5 August 2020
To ask the Scottish Government who it appointed to the programme review board at Ferguson Marine to oversee the delivery of vessels 801 and 802, and whether any of those have commercial experience.
Answer
The membership of the Programme Review Board is set out in the minutes of the meetings contained within the Freedom of Information Release 202000035695 published on 15 June 2020 https://www.gov.scot/publications/foi-202000035695/
The board includes a range of expertise from the maritime sector including naval architecture, ferry procurement and operations. It also includes experience from procurement and project management of large scale public sector contracts generally and representation from the workforce at Ferguson Marine.
A number of these individuals have commercial experience.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 5 August 2020
To ask the Scottish Government whether the turnaround director at Ferguson Marine, Tim Hair, remains in post.
Answer
The Scottish Government can confirm that the position of turnaround director at Ferguson Marine has not changed.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 5 August 2020
To ask the Scottish Government whether the minutes and papers of meetings of the programme review board at Ferguson Marine were published, and, if not, whether it will now do so.
Answer
I refer the member to the answer to question S5W-30803 on 5 August 2020. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 5 August 2020
To ask the Scottish Government how many times the programme review board at Ferguson Marine has met; who attended each meeting and what was discussed.
Answer
The programme review board met six times. On 15 June the minutes of the last five meetings of the Programme Review Board were published in response to a FOI request: https://www.gov.scot/publications/foi-202000035695
The minutes of the first meeting of the programme review board will be proactively released in due course.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Tuesday, 23 June 2020
-
Current Status:
Answered by Clare Haughey on 4 August 2020
To ask the Scottish Government, further to the answer to question S5W-29657 by Clare Haughey on 18 June 2020, for what reason it continues to offer asymptomatic testing to other sectors, but not to offshore workers.
Answer
Testing is available for everyone in Scotland who has symptoms consistent with COVID-19.
The Scottish Government have been working with Oil and Gas UK to understand their concerns and support their safe operation. In addition, Public Health Scotland have been working closely with Oil and Gas UK to provide expert public health advice in relation to offshore installations, and they have produced specific guidance on preventing and managing cases of COVID-19 on offshore installations.
At the current time, Public Health Scotland do not recommend that the Scottish Government supports testing of asymptotic workers prior to travel offshore. There are limitations of testing in the context of a disease with a 14 day incubation period, because it would not remove the risk of people incubating the disease becoming symptomatic while offshore.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 4 August 2020
To ask the Scottish Government who has been appointed as the senior management team at Ferguson Marine, and whether it will provide the salary scale for each postholder.
Answer
The Ferguson Marine senior management team:-
- Programme Director
- Head of Planning
- Head of Business Improvement
- Chief Financial Officer
- Head of Procurement
- Head of Engineering
- Human Resources Director
All appointments were made at market rate in line with the skillset required. Commercial sensitivities prevent the disclosure of salaries scales.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 20 July 2020
-
Current Status:
Answered by Fiona Hyslop on 4 August 2020
To ask the Scottish Government when it expects to complete the construction of vessels 801 and 802 at Ferguson Marine.
Answer
Further to the answer to S5W-29020 on 21 May 2020, S5W-29558 on 9 June 2020 and S5W-30494 on 9 July 2020 Tim Hair, Turnaround Director of Ferguson Marine (Port Glasgow) Limited has been asked to provide an updated report on cost and programme, which will include completion dates, for vessels 801 and 802 to reflect the impact of COVID 19.
As an open and transparent government we will keep Parliament updated and proactively release the report thereafter.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx