Public Audit Committee [Draft]
Meeting date: 8 October 2026
David Kirkwood
Yes, and you obviously have some new capabilities, such as the introduction of the new courts, to add into that. That is great. Are you able to email me a link to where I can find the report?
Public Audit Committee [Draft]
Meeting date: 8 October 2026
David Kirkwood
Good morning. Page 9, paragraph 11 of the report says:
“A three-year delivery plan was due for publication in August 2022 but was delayed.”
Was the delivery plan ever published?
Public Audit Committee [Draft]
Meeting date: 8 October 2026
David Kirkwood
Do you know when?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
Thank you.
If all these projects are developed and come online, they will be producing 28GW of capacity at peak, which is obviously not all the time. Scotland consumes about 4.5 or maybe 5GW on a really cold winter’s day, and there is the B6 connector to England, which can transfer maybe 6GW. That leaves 17GW of power, which has to go somewhere. Were any commitments given to the developers about upgrading grid capacity to take that power and, if so, are there any get-out clauses for the developers if that grid capacity is not available?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
Yes, but are there any requirements with regard to the content of the supply chain that is, supposedly, to be developed? I can think of a lot of ways for big companies to say that they are spending a lot of money without it actually costing them anything at all. The commitments to spend £29 billion in Scotland over the next how many years and so on seem to be just monetary commitments. Does it say anywhere what they are spending that money on? Are they building engineering expertise or any kind of manufacturing capacity?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
But is there a defined outcome? Will they have to say, for example, “We’ll have a plant in a certain area that will produce this many turbines per year”? Or will they be able just to say, “We're going to spend this much money, and we’ll define it just as ‘manufacturing’”?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
Nothing at all?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
I will go back to the deputy convener’s discussion on supply chain development. You note in paragraph 38 that supply chain development statements were not considered sufficiently robust to be able to judge decisions correctly. Is there any point to an SCDS at all?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
My question was more about the mechanics of it than the purpose. As far as I understand it, the residue of the £755 million still exists in a bank account somewhere. Why has it not just been transferred to another bank account and hypothecated for national wealth?
Public Audit Committee [Draft]
Meeting date: 1 October 2026
David Kirkwood
So, you are taking it on hope that somebody might take the power that is being generated.