Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
If you set a price cap, you then open yourself up to the possibility that multiple bidders will bid at the cap level for the best bits of water, in which case that approach does not work as a tie-breaker, does it?
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
The commercial sector looks after itself and does not necessarily need Government management to do that. Nearly 50 years ago, I was working in my dad’s machine shop and building parts for wind turbines for Howden’s, which were exported. There was no Government intervention at all. The market saw a need and satisfied it. I worry about the Government direction of industry.
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
Okay. On Ronan O’Hara’s point about not having leased all of the water at the same time, is that really so much of a problem, given that you can do it again in the future, once the market is better established? A stallholder sets out their goods and, at the end of the day, not everything is gone and the stuff goes back in the box, but it comes back out the next day and they sell it the next day, possibly at a better price. Was there an imperative to get rid of all the lease options at the same time, or could some options have been retained for future markets?
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
Okay, but were you not taking commercial decisions on behalf of developers by saying, “We’re going to protect you against excessive costs”?
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
I understand that, but if a developer walks away after two or three years and decides that it is not worth it, you have its up-front fee and all the money that has been spent in Scotland already in developing its vision of the supply chain. That money has been spent. The developer hands back the option, and you get to sell it again. If somebody gets the benefit of all of the research that the developer has done, that makes it much easier, and you get a far better vision of the value of that piece of water and a much more accurate price for it.
I do not see why the Government is trying to protect commercial entities against commercial risk. That worries me.
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
Thank you.
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
Good morning. For full disclosure, in case you have not worked this out already from research you have done, I think that using wind for baseload generation is madness, so please consider my comments in that context.
The convener has already asked quite a few questions regarding the price cap, which is what I will ask about now, but I want to go back to the rationale for it, rather than the value of it.
Paragraph 20 of the report says that the price cap was adopted specifically
“to avoid the leasing process operating solely as a price-based competition”,
but it would not have been a price-based competition anyway, because the consideration of any bid would be based on a weighted matrix of a multitude of parameters. Why was the leasing price not simply given a weighting within that matrix and the lease awarded through an open auction?
Public Audit Committee [Draft]
Meeting date: 5 November 2026
David Kirkwood
In the run-up to the process, in 2018, 2020 and 2021, the value of the cap went from £2,000 to £2,500, from £5,000 to £6,000 or £10,000 and then to £100,000. Even now, you still do not know the maximum market value of any of the water, because you set a cap and you have not done a price discovery process. Is that not a bit of a handicap for the next round?
Public Audit Committee [Draft]
Meeting date: 29 October 2026
David Kirkwood
I will concentrate on the governance issues rather than the detail. In the “Key messages” section on page 3, paragraph 2 of the report talks about programme planning and paragraph 3 talks about risk management. Programme planning pops up every time somebody appears before us. It would appear that public sector projects cannot really manage programmes very effectively—that is a frequent criticism. It is interesting that Shirley Laing mentioned the RAID log, because that issue came up when you were last here, Mr Rennick. One thing that concerned me a bit at that time was that you said that a RAID log was not necessary for that particular programme because the risks were all captured in project-level RAID logs. That is not how a programme RAID log works; everything must be escalated to the highest level.
Shirley, is the RAID log that you are using now a programme-level log, or do you use a set of project-level logs?
Public Audit Committee [Draft]
Meeting date: 29 October 2026
David Kirkwood
Are you using traditional red, amber and green ratings?