Official Report 473KB pdf
Good afternoon, everyone, and welcome to what is, believe it or not, the final meeting in 2011 and, indeed, this session of the Transport, Infrastructure and Climate Change Committee. I remind everyone present that all mobile devices should be switched off fully and not just put on silent. I record apologies from Jackson Carlaw.
Yes, briefly. Thank you for your introduction, convener.
Perhaps you could begin by giving us a detailed outline of the key events and progress since our most recent discussion in September last year, and updating us on any problems that have been encountered.
On the legislative side, things have progressed exactly as we had planned. The stage 3 vote took place in December and the Forth Crossing Bill was passed. Royal assent followed in January. The Forth Crossing Act 2011 gave us the powers to start moving forward with land acquisition and all the issues associated with that. Everything is proceeding exactly to plan. We have made the initial notices in preparation for the general vesting declaration to ensure that the land will be available for the project, and we are continuing negotiations for voluntary acquisition of various properties around the project.
You mentioned some concerns that had to be resolved in the development of the tenders. Can you give us some detail on that?
It was about ensuring that the participants fully understood the employer’s requirements and addressed them clearly. That was one of the reasons why we wanted the outline proposals to be submitted to us on 5 November—well in advance of the participants submitting their final proposals. That meant that if we had any concerns on the technical front, they could be resolved and clarified with the participants well in advance of their submitting their final tender. We were conscious that we had a relatively short period of time for tender evaluation, therefore we did not want to have any surprises when we delved into the tender submissions.
You also said that the two bidders had agreed the terms and conditions of the contract.
That is correct.
Presumably the terms and conditions are the same regardless of which bidder is successful.
That is correct.
Will the information about the terms and conditions be made available for Parliament to scrutinise before we go into dissolution?
The contract itself will not be, but the original concept that was approved by Parliament has not changed and we are moving forward on the same basis as was originally intended. It is really the fine tuning and the wording that has been discussed with the participants over the contract review period.
One of the issues that has been controversial—it is the subject of a parliamentary motion at the moment—is the indication from the Government that it intends to sign the contract when Parliament is dissolved, before the new Parliament is sworn in. If that is the situation, are we able to get any information at all about, for example, what costs a new Government would face if it chose to change the timetable to delay the construction of the project?
I do not think that that is the intention. The information that we have received is that it is intended that an announcement of the intention to award the contract will be made prior to the dissolution of Parliament.
There is a written question awaiting an answer by a week today. Is it correct that the detail of what an incoming Government would face will not be available for parliamentarians to scrutinise before we go into dissolution?
I am not quite sure how to answer your question. Nothing has changed significantly, therefore the announcement that will be made is that the intention is to award a contract on the terms that Parliament has scrutinised and agreed.
Can you tell us how much financial penalty a new Government would face if it decided not to proceed after the election?
I cannot give a specific answer. The terms and conditions of the contract would allow a termination for convenience, which is effectively what would be happening, and those terms and conditions would have to be evaluated depending on the precise timing and events of that circumstance.
So no information can be put in the public domain or provided to Parliament at the moment to inform a later decision.
We would need to take advice on that. We would need to respond to you separately on that point.
That would be appreciated. Thank you.
Would the detail on that depend slightly on what the decision was? For example, would it vary according to how long the construction might be delayed and what part of the construction might be delayed? It might be impossible to give just one answer, given the multitude of possibilities depending on what anyone wanted to do at that time.
You have summarised the situation rather better than I did. You are absolutely correct to say that, because the contract is so large, the possibilities for what could arise are multitudinous.
Given that the committee exists for only one more week, it would be much appreciated if you urgently provided us with more written information about the range of possibilities in that respect.
It is important that we continue to update the committee on a quarterly basis in exactly the same way as we have been doing up to now. The precise key events that you refer to will depend on which of the bidders is successful, because each of them has its own programme for mobilising the project. One of our first activities will be to sit down with the winning bidder and establish in detail the mobilisation process and how it will work, and it will be important to give the incoming committee a view on that in the near future and explain to it exactly how mobilisation will take place and what the key activities will be.
As you will be aware, the committee was very clear in its report on the Forth Crossing Bill about the importance of good public transport. What stage has the development of the cross-Forth public transport strategy that was recommended by the committee reached?
It is probably better if I answer that question. We have always seen the public transport strategy—which, as you know, was published in January 2010—as a working document to take us through the next six months or year or whatever. The strategy focuses not only on the Forth replacement crossing but on cross-Forth travel, and we are working on the issue with the local authorities involved—West Lothian Council, Fife Council and the City of Edinburgh Council—and the regional transport partnership, the south east of Scotland transport partnership. We have had a number of meetings over the past few months; indeed, on 13 December we had a workshop at which we agreed a way forward. I stress the use of the word “we” in that respect. We very much have collective working, because we realise that the Forth replacement crossing will have many benefits for public transport.
You mentioned the various people who have been around the table, although I am surprised to hear that the local authorities have not been involved. I have to tell you, though, that I do not think that that response is any better than the one we received when we took evidence on the bill. It just seems to be, “We will come up with a strategy.” Will you elaborate on that? The committee would like to know more than just that you will come up with a refreshed strategy. Are the partners at an early stage in that regard? Is there an indication of what will be involved in the refreshed strategy? Has it been accepted that the strategy was poor?
I do not think that the public transport strategy is poor. It contains a number of interventions, some of which are included in the contract, such as the Fife ITS, which will have bus-lane or hard-shoulder running. Equally, in the south, to Newbridge, such measures will be constructed. We are working with Fife Council, which has submitted a planning application for Halbeath park and ride and is working on Rosyth. There are nine interventions in the existing strategy and we are working on four or five of them. We will have to work on some of the interventions in future, because funding is not available, but there are schemes that we want to take forward.
Stewart Turner mentioned a meeting that was just with bus operators, but the other meetings that we have had on the public transport strategy have been very much with all the local authorities and SEStran, which have been positive about the proposals that we have taken forward as part of the project.
I understand that it is early days and that all sorts of meetings and partnerships are happening. Mr Turner talked about monitoring how things are developed. How will that be done? What involvement will the partners have? How will you know that it is working? What mechanisms exist or will be put in place to measure success or identify concerns and a need to change?
A key aspect of the Forth replacement crossing project is monitoring of the current situation and the situation when the bridge is completed in 2016, to see how effective the ITS is, for example, and how buses are encouraged to run through the measures that I have mentioned.
The committee stated clearly in its report that we wanted to see public transport in place in advance of the opening of the new bridge and quite a bit of marketing and support to ensure that people transferred to public transport in greater numbers in order to avoid the temptation to use the new bridge. You have talked about aspects around the area of the bridge, but there was discussion previously about a corridor from the bridge into Edinburgh. What work has been done on that and what work has been done on early action to get people on to public transport?
Some of that is about the timing of the different contracts. The bridge will obviously be the last part of the project to open, which will be in 2016. However, the Fife ITS contract will be awarded this summer and the work will be completed by mid-2012 or thereabouts. It will provide an early facility for bus hard-shoulder running from the Halbeath area down to Ferrytoll. So, that is one facility that will be delivered early doors.
The Fife ITS, which will run from just south of Halbeath, is clearly important for park and ride at Halbeath, which is one of the reasons why it will be placed there. Fife Council has submitted a planning application for it and the 12-week pre-consultation process is complete. There were no objections as such, but a few people commented on it. The council is confident that the project will go through its planning procedures relatively smoothly. I am sure that we all hope that it does.
Staying with the subject of recommendations in the committee’s report of a year ago, what progress have you made in developing plans to encourage modal shift to public transport for cross-Forth journeys?
The fact that we are sitting round the table at least moves us in the right direction. I cannot give you any evidence to say that there is any difference between the situation a year ago and the situation now, unless that evidence exists elsewhere. However, we recognise that we have to encourage modal shift. It is important that people use public transport not only on the Forth but throughout Scotland, and part of the group’s task is to ensure that there is modal shift. It is difficult to give you definitive examples at the moment, but we acknowledge the importance of ensuring that modal shift happens.
Not much progress then, eh?
There is not a great deal, but the bridge will open in 2016 and the Fife ITS will be ready in about 18 months’ time. Those are our targets. We have to ensure that people know what is happening. If we tell them too soon, they might forget, so we have to ensure that we give them constant information, although we have to decide through which part of the media we will deliver that. However, I take your point and we will ensure that it happens.
I am sure that the convener would take the point that it is never too soon to achieve modal shift. There are probably good reasons for it whether or not we build a Forth crossing.
I am sure that the bus operators are more than happy to get as much modal shift as they can. The mere fact that we now have them involved will ensure that we move forward.
However, by definition, the people whom we are really trying to get are those who drive cars and perhaps do not think about using public transport at the moment.
That is true. Those are the people we have to get to.
The bridge provides an opportunity for everything that Charlie Gordon alludes to to happen. Once the new bridge is in place and the existing bridge is freed up, people will see that there is a dedicated public transport corridor. The bus lanes that we have just spoken about will provide opportunities. There will also be opportunities with the development of areas around the Forth estuary, such as Winchburgh and Dunfermline, where we have heard that Amazon is to open a big facility. More and more people will come to the area as development prospers and, we hope, the economic climate improves.
Right. I will move on. In correspondence, Transport Scotland told us about what cyclists and pedestrians would do if the existing Forth bridge were closed. They could use the bridges at Kincardine, which is quite far away; they could try to use the bus, but it is usually not possible to get a bike on the bus; or they could use Dalmeny station, which is more than a mile away from the Forth road bridge. Are those provisions to maintain cross-Forth pedestrian and cycle traffic during periods when the current bridge is closed realistic and appropriate?
I obtained some data from FETA about how often the bridge is closed to pedestrians and cyclists because of high winds and also got a feel for the amount of cyclist and pedestrian traffic that uses the bridge. From April to December last year, the bridge was closed to pedestrians and cyclists for only 52 hours; in the whole of 2009-10, it was closed for only 56 hours; in the year before that, it was closed for 154 hours; and, in 2007-08, it was closed for around 225 hours. The figure has, surprisingly, declined over the past couple of years. That gives you a feel for the amount of time for which the walkways and cycleways are closed.
I thank Mr Shackman for that multifaceted answer. You have told us the number of hours for which the bridge has been closed, but if it is always closed when one particular individual is trying to cross, that might add up to a big negative.
I appreciate that.
I read into what you have said the suggestion that the weather has got better and is going to stay better for the foreseeable future, that it is FETA’s responsibility anyway and that, in the great scheme of things, we are not talking about a lot of people.
The undertaking that was given as part of the bill process, which has been widely publicised, was that a decision on FETA’s future would be made by 2013. That means that whatever authority, group of authorities or contractor is chosen to look after either the Forth road bridge or the Forth replacement crossing can easily be put in place well before construction is completed. It is not for me to say how that is going to go forward at this time. Nevertheless, I hear what you say. As I said the last time that we met, my personal opinion is the same as yours—that it seems sensible for there to be only one authority.
You will agree that, if FETA is merged with Transport Scotland, Transport Scotland will have the responsibility for deciding what arrangements to make for cyclists and pedestrians when bad weather shuts the Forth road bridge.
That is something that could be taken forward. You are right. Once the authority or group of authorities with responsibility for maintenance is sorted out, in due course, a decision can be made on how pedestrians and cyclists can be taken across the Forth if the bridge or bridges are closed because of strong winds.
I will follow up on Charlie Gordon’s question. I was a little bit taken aback by your comparisons with other bridges in the UK, which, of course, do not all have a spare. Would it not be a double insult to cyclists or pedestrians when one bridge was closed and the other bridge was deliberately closed to them at all times? Is there not a case for saying that if the Government is serious about supporting an increase in sustainable and active travel, it should provide the facility for such travel to take place?
The best comparison is with the two Severn bridges. The roads on both bridges are motorways, but the original Severn bridge has a footpath/cycleway facility just outside the boundary of the motorway. There is no formal structure in place for pedestrians and cyclists if that is closed, so in that situation pedestrians and cyclists do not have a formal route to take or means of crossing the Severn bridges. That is quite a good parallel with our situation.
There has previously been talk about the provision of some sort of vehicle to transport people with their bikes. As Charlie Gordon said, most buses do not provide such a facility, but it has been suggested that that would be available when the existing bridge was closed.
That option could be examined when the future maintenance authority is known. I hear what you say.
One issue that we spent a great deal of time discussing with you during previous evidence sessions was community engagement. The feedback that we got from a number of communities was that community engagement was poor, to say the least, and that there was disquiet about how little true consultation had taken place and about the impact that communities felt they were having, which was none.
One fundamental change that came out of the Forth Crossing Bill Committee’s evidence sessions was the development of a community council forum, which is essentially an opportunity for the local community councils to have a good view of what is going on in the project, to have a say in what is going on and to get information about events, concerns and the like. We are currently trying to set up the forum.
I have a number of follow-up questions. I am surprised that a forum is taking so long to set up. Forums are really not that difficult to set up—we are not talking about a wide geographic area. Why it is taking you so long to set up a forum? Also, what evidence do you have that the communities want a forum as the way in which they should be consulted? Did Transport Scotland decide that that is the vehicle to use?
The forum was instigated through the bill process as a means of getting buy-in from all the community councils. It is not that long since the bill was passed, and we are still trying to get details on the availability of people on the community councils—we have had a little bit of difficulty in trying to get a convenient time for some people. There has been a fair bit of correspondence with all the community councils concerned.
I am not entirely convinced by that argument, but I will move on.
The terms of engagement for the community council forum are being drafted. At the workshop, we want to talk about how the forum will want to be informed. We want to know whether people will want to meet monthly as one group or separately at weekly or other intervals.
I certainly hope that it is in a very, very early stage. If people get to discuss a near-complete draft, we are back to the giving of information rather than true engagement.
To a large extent, what will be encompassed in the document is already in the code of construction practice. All the media and means of communication should therefore not be a surprise to anyone. You are right that the community councils need to buy into the document to ensure that it fits the bill, if you like.
I will briefly follow up Shirley-Anne Somerville’s question before I bring in Margaret Smith.
One key thing is to get together representatives from all the community councils and to have a reasonable amount of time for the meeting. Some people prefer to meet in the evening and others prefer to meet during the day, causing an immediate pressure. They say, “I want to come to that meeting, but I can come only in the evening,” or, “I want to come to the meeting, but I can come only during the day.” That is part of the problem.
You can go only during the day?
Yes, which some people wanted. We want to hold the meeting during the day, because it needs to be of a reasonable length and it would be more appropriate to hold a three-hour, or thereabouts, session during the day.
Have you asked whether you can go to existing community council meetings when it is convenient for the community councils?
We attend their meetings whenever they want us to. We have seen quite a few of them.
I apologise for being slightly late. I want to clarify a couple of things that you said about the forthcoming brochure. You said first that it would be ready in the near future, and then that it was at an early stage, because input was needed. Which is it?
It will be a big document and it is being drafted at the moment. We will consult communities at the end of March, when we hold the workshop. We hope to formalise the document some time after that. I hope that we will be able to publish it around May, well before any real construction activities occur on site. It is being done at an appropriate time. I assure you that the appropriate people will be consulted on it. We must also engage with the successful contractor and get it to buy into the document. That is one reason why the document is not yet finished.
Is that, rather than the fact that you cannot get some community councillors into a room, not likely to be the real reason?
It is the combination of the two.
There are a couple of issues. There seems to be delay in working out the proposals for mitigation involving Newton. Those were put to the community council at the end of the year, but we do not know what is happening.
We are still waiting for Newton community council to get back to us. We have indications that it is content with the proposals that we put to it way back at the end of last year, but we are waiting for a formal response from it. The community council has been having discussions.
So you have not received a formal response from Newton community council to the proposals that were put to it and are experiencing difficulty getting community councillors together to talk about community engagement going forward. You seem to be taking a long time to deal with some of this stuff. However, the tenders for the contract were submitted on 28 January and, I believe from colleagues, two months later you are about to sign off a contract. There seems to be a disconnect. You seem to have been able to deal with the major contract for the programme in two months but unable since November to get a response from a community council or to get six community councillors into a room. Why should I have faith that the contract will be worth anything?
I am not trying to belittle the need for good communications. We will make every effort to ensure that the document is published at the appropriate time, once we have consulted the right people.
Do you accept that, as an Edinburgh MSP, I am decidedly twitchy about the idea that a contract for the biggest public infrastructure project ever in Scotland can go through in a few months, especially given what we have experienced with the tram project, while progress does not seem to be being made on the community engagement parts of the project? Shirley-Anne Somerville is absolutely right to say that that was a major part of the problem that the people whom we represent had with the project.
I am not going to talk about the Edinburgh tram project, which has nothing to do with this project. I can only talk about this project, and I assure you that the tender process that we have been through has been very thorough. As I just said, we had a chance to look at the proposals in the early stage of the dialogue process, which gives us a lot of comfort that the final tenders are as robust as David Climie said.
We discussed the tender process at the start of the meeting but the subject has been brought up again. An accusation has been made that the tender process was rushed. Has the date for the signing of the tenders been in the public domain as part of the timetable for the tenders’ progress? Have we known what the timetable was and the various steps in it?
Absolutely. The intention was always to award the contract in April 2011. A clear timeline was established for the whole process, from the dialogue through the evaluation of the tenders to the award of the contract, and it has been in the public domain for a significant amount of time. The objective was always to sign the contract in April 2011. In fact, that was talked about during the stage 3 debate in Parliament.
Were any concerns raised at that point about the timings?
Not as far as I am aware.
Concerns were certainly raised during the parliamentary debate, but that is a matter of record.
We are committed to providing a model. In fact, I think that three models of the project will be provided. One will be a plan area of the Forth to show how the project fits into the area. A couple of other models will be made of the bridge itself, one showing the towers and one showing the whole bridge from bank to bank. Those will be provided by the contact and education centre when it opens in 2012. The models will be produced by the contractor; that is written into the contractor’s requirements. Once the final detailed designs are made, the contractor will provide the models. Obviously, Transport Scotland and our consultants will monitor the development of the models, but there are specific requirements in the construction contract in that regard.
Are the communities who have requested models content with not seeing them until next year?
We cannot provide the models before the design is finalised. It is a chicken-and-egg situation. We have to make sure that the contractor’s design is finished before we produce the models. As soon as we can produce the models, they will be done.
We might have talked about some of this already, but are there any further details about how the code of construction practice better meets the needs of local residents?
Which aspects are you referring to or interested in?
A general overview would be helpful. If there are a lot of details, that would be good.
We wrote a list of a lot of the changes that were made to the code of construction practice and all the undertakings that were made following the bill process in relation to noise monitoring and air-quality installations in the local area, to give the communities comfort that appropriate measures would be taken throughout construction to address their concerns regarding dust, noise or traffic—whatever the particular environmental impact was.
Thank you. You also talked about the updated brochure and the models that will be made available. What progress has been made in making arrangements for local residents and businesses to report any breaches of the code, and to learn about the project as it enters its construction phase?
We have undertaken—it is in the code of construction practice—to make a 24-hour hotline available for anyone who has complaints about the project. People will be able to phone the hotline for whatever reason they want, whether to make a complaint or offer a compliment—we hope—about how the project is going, or just for general information and education. A dedicated e-mail address will also be available.
I presume that once you get the forum set up, you will go through with the community councils the step-by-step guide that you will have.
That is correct.
I will focus further on traffic management during the construction phase. You have mentioned the code of construction practice with regard to minimising the impact of construction traffic on local traffic and residents in the streets. What changes have been made to make those elements more enforceable?
I am not sure that there have been many changes to make them more enforceable. We have been really quite strong in terms of how many restrictions we have placed on the main contractor with regard to the areas to which it cannot have access, which include the general streets in the built-up areas of South Queensferry. We do not want any construction traffic in those areas, and we want to have the means to ensure that if people from the contractor’s workforce park where they are not supposed to park, the cars will be removed and the people will have sanctions placed on them.
So, is there scope—or, indeed, any further plan—to improve on the current arrangements if necessary?
The traffic management working group is the be-all and end-all for all the project’s traffic management arrangements and will have very regular meetings as the contractor becomes more and more involved in the construction process. All the plans will have to go through that group. Moreover, the contract contains restrictions on when the contractor can and cannot carry out works, in particular on the main road network, to ensure that the impact on traffic is minimised as far as possible. For example, it would be unlikely that the contractor would be allowed to restrict the A90 or M90 to one lane during the day. I am not saying that such a thing is impossible; there might be a very good reason why it is better to carry out such work on a particular occasion. A short, sharp shock, if you like, is sometimes better than a long period of road works. Indeed, such works might not be safe and it might simply be quicker to close a section of road than to put traffic management on it.
Will there be assurances of uninterrupted access to the current Forth road bridge for pedestrians and cyclists during the new crossing’s construction?
As far as I am aware, there is no reason to stop pedestrians and cyclists from crossing the bridge. The paths and cycleways that link to the bridge will be maintained; they might not be on the existing alignment and alternative routes might have to be put in place, but there are certainly no plans to stop cyclists and pedestrians crossing the Forth road bridge.
You said that you might have to close a stretch of road because of, say, a wide load, but your response seems to indicate that that would not affect pedestrians and cyclists and that their route to the current Forth road bridge would be unimpeded.
As far as I know, there are no plans to stop pedestrians and cyclists crossing.
We know that the construction of a project of such a scale will result in a great deal of carbon emissions: indeed, at the outset, Transport Scotland estimated that around 120,000 tonnes of CO2 would be emitted, but acknowledged that it will be able to refine that figure as detailed proposals come forward. On a number of occasions, Transport Scotland has tried to reassure the committee that it would get that information and most recently assured us that the tendering process would provide it. We know now that the bids were submitted on 28 January. Have contractors provided estimates of greenhouse gas emissions for the project’s construction and, if so, when will those be made public?
Contractors have provided the requested information. At this point, the figures are estimates, because the contractors have outline designs and outline procurement proposals. Contractors have had to justify their estimates on the basis of those outline proposals. As we described at the previous session at which we appeared, those estimates formed part of the quality evaluation of the tenders, so they were taken into account in the overall scoring of tenders.
Is it your initial assessment that the estimates are robust and that contractors have not overestimated or underestimated, so they will not fall foul of problems?
We have reviewed whether the estimates are in line with our expectations and whether they align with what contractors have told us about procurement, and the answer is yes: we are satisfied that the basis of the calculations is sound and that contractors are coming up with answers that are similar to the range that we expected from the specimen design.
Do the figures cover the whole crossing project or only construction of the bridge?
The figures cover just the main crossing—just the bridge—because that will probably have the greatest impact in terms of potential transport and so on.
So, the estimates for the two bids do not differ significantly.
The estimates differ, but they are both within the range that was expected when we developed our initial evaluation criteria.
Does the difference between the estimates relate to the methodology for the calculations or to how the contractors intend to pursue the construction project?
The differences are in how the contractors would pursue construction, because the methodology was laid out as part of the tender documents—they set out exactly how the calculation had to be done.
The Government has said that it expects the VAT that is due on the project to increase by approximately £23 million because of the recent change in the VAT rate. Will that estimated VAT increase affect the projected outturn cost of the project?
We have reviewed the impact of the extra VAT, which I confirm will be about £23 million, as you said. We have also considered our overall estimates. I confirm that the additional VAT can be accommodated in the published range of outturn costs.
I presume that there is a limit on future changes to the VAT rate that could take place and allow you to retain that confidence.
Absolutely.
Do you have any idea what that limit is?
I cannot speculate, but I can say that the increase of 2.5 percentage points was accommodated. I cannot comment on future impacts.
I have been asked to raise two construction issues. The existing road bridge has lay-bys to allow large loads to be parked and inspected before being escorted over the bridge. Will the new bridge have the same facility?
Heavy vehicle lay-bys are incorporated into two slip roads on the South Queensferry junction, so any vehicles that need to be inspected before they cross the Forth will be held in those locations. A facility is built into the contract for that.
The ship impact defences relate to the fact that, as knowledge develops, design codes change. When the original Forth road bridge was designed in the early 1960s, less was known about ship impact effects. A retrofit was applied later, as were other measures to upgrade and strengthen the bridge.
As there are no more questions, I thank the witnesses for the time that they have spent answering questions, and I wish them well in answering our successor committee’s questions in the near future.
Previous
Attendance