- Asked by: Kenneth Gibson, MSP for Cunninghame North, Scottish National Party
-
Date lodged: Thursday, 20 July 2023
-
Current Status:
Answered by Angela Constance on 7 August 2023
To ask the Scottish Government what percentage of reported cybercrimes were successfully prosecuted in the last year for which figures are available.
Answer
There is no agreed upon definition of cyber-crime and a range of different types of crime may be either cyber-dependent or cyber-enabled. The table below shows people prosecuted and convicted in Scottish courts in 2020-21 where the main charge is under either the Computer Misuse Act 1990 or Section 127 of the Communications Act 2003, the only charges that are identifiable as cyber-crimes in Criminal Proceedings in Scotland data. Note that data for 2020-21 are effected by the pandemic and subsequent court closures and should not be considered indicative of long term trends.
Act | People prosecuted | People convicted | Conviction rate |
Computer Misuse Act 1990 | 1 | 1 | 100% |
Communications Act 2003, Section 127 | 387 | 363 | 94% |
Total | 388 | 364 | 94% |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Fife, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
The following table outlines the current projected activity for National Treatment Centres during 2023-24 with reference to the position in the NHS Recovery Plan.
NTC projected 2023-24 activity
NTC | Current projection (procedures) | Comparison with NHS Recovery Plan position |
Golden Jubilee Phase 1 | 12,481 | Higher |
Fife | 472 | Higher |
Highland | 1,586 (partial) | Lower – see Note 1 |
Forth Valley | 450 (partial) | Lower – see Note 2 |
Golden Jubilee Phase 2 | 390 (partial) | Lower – see Note 3 |
Notes
1. Part-year figure due to opening during 2023-24: current projection excludes additional Ophthalmology capacity due to commence in Autumn and for which planned activity is in the process of being finalised.
2. Part-year figure due to opening during 2023-24: full-year activity as per NHS Recovery Plan will be achieved from 1 April 2024.
3. Part-year figure due to opening during 2023-24: full-year activity as per NHS Recovery Plan will be achieved from 1 April 2024.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Fife, and what the revised timetable is as of 30 June 2023.
Answer
The following table outlines the opening dates set out in the 2022 update to the NHS Recovery Plan and the current projected opening dates for National Treatment Centres with approved Full Business Cases:
NTC | Opening Date in 2022 Recovery plan update | Currently Projected Opening Date |
Golden Jubilee Phase 1 | December 2020 | December 2020 |
Fife | Early 2023 | Opened March 2023 |
Highland | Spring 2023 | Opened April 2023 |
Forth Valley | Spring 2023 | End of 2023 |
Golden Jubilee Phase 2 | Late summer 2023 | End of 2023 |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Fife, and what the revised cost is as of 30 June 2023.
Answer
This information is available in the Infrastructure Investment Plan 2021-22 to 2025-26: major capital projects progress update - March 2023 - gov.scot (www.gov.scot) the Scottish Government published on 20 June 2023. The plan outlines the progress and current projected costs of NTC Fife as well NTC Golden Jubilee Phase 2, NTC Grampian, NTC Lothian, NTC Highland, NTC Forth Valley and NTC Ayrshire and Arran.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the revised number of patients is that will be treated in the National Treatment Centre Ayrshire and Arran, and how this compares to the targets set out in its NHS Recovery Plan.
Answer
The Full Business Cases (FBC) for NTCs in Ayrshire & Arran, Tayside, Lothian, Lanarkshire and Grampian remain under development. The proposed number of patients treated will be revised to align with national treatment targets once FBCs are finalised.
NTC | 23/24 Activity in Recovery plan | Currently Projected activity |
Ayrshire & Arran | N/A | To be agreed at FBC |
Tayside | N/A | To be agreed at FBC |
Lothian | N/A | To be agreed at FBC |
Lanarkshire | N/A | To be agreed at FBC |
Grampian | N/A | To be agreed at FBC |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned National Treatment Centre Ayrshire and Arran, and what the revised timetable is as of 30 June 2023.
Answer
The following table outlines the opening dates set out in the 2020 NHS Recovery Plan and the current projected opening dates for National Treatment Centres without approved Full Business Cases:
NTC | Opening Date in 2020 Recovery plan | Currently Projected Opening Date |
Ayrshire & Arran | 2025 | To be agreed at FBC |
Tayside | 2025 | To be agreed at FBC |
Lothian | 2025 | To be agreed at FBC |
Lanarkshire | 2026 | To be agreed at FBC |
Grampian | 2025 | To be agreed at FBC |
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original timetable was for the (a) completion and (b) opening of the planned new Edinburgh Eye Pavilion, and what the revised timetable is as of 30 June 2023.
Answer
It is not possible to compare the current proposal with the previous one at this point. The Full Business Case is still under development and project timetable will be revised to reflect the impact of inflation, net zero carbon targets, plot change and updated clinical brief to align with national treatment targets.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Monday, 17 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the original cost was for the planned National Treatment Centre Tayside, and what the revised cost is as of 30 June 2023.
Answer
I refer the member to the answer to question S6W-19963 on 7 August 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
- Asked by: Stephanie Callaghan, MSP for Uddingston and Bellshill, Scottish National Party
-
Date lodged: Tuesday, 11 July 2023
-
Current Status:
Answered by Jenny Gilruth on 7 August 2023
To ask the Scottish Government what information it holds on the latest known levels of people in the 25- to 64-year-old population who have been educated to tertiary level in Scotland, and on how this compares to the levels in (a) England and (b) Wales.
Answer
Information on the share of population 25 to 64 years old with tertiary education is published by the Organisation for Economic Co-operation and Development (OECD) and is available here.
| 2020 | 2021 | 2022 |
Scotland | 55.7 | 55.2 | 57.9 |
Wales | 43.4 | 44.3 | 46.3 |
Northern Ireland | 44.1 | 48.8 | 42.3 |
North East England | 38.1 | 39.7 | 39.3 |
North West England | 44.0 | 44.0 | 47.0 |
Yorkshire and The Humber | 41.4 | 44.4 | 45.0 |
East Midlands | 43.8 | 42.6 | 43.8 |
West Midlands | 43.1 | 44.2 | 45.1 |
East of England | 44.6 | 45.2 | 47.1 |
Greater London | 68.4 | 69.8 | 69.9 |
South East England | 51.8 | 51.6 | 54.1 |
South West England | 47.2 | 48.0 | 48.4 |
United Kingdom | 49.4 | 50.1 | .. |
Source: OECD Regional Education, July 2023
.. Not currently available
- Asked by: Clare Haughey, MSP for Rutherglen, Scottish National Party
-
Date lodged: Tuesday, 11 July 2023
-
Current Status:
Answered by Michael Matheson on 7 August 2023
To ask the Scottish Government what the most recent level of health spending per person is in Scotland, and what information it has on how this compares with spending in (a) England and (b) Wales.
Answer
Based on HM Treasury’s Country and Regional Analysis (2021-22), frontline Health spend per head in Scotland is £3,377, which is £323 (10.6%) higher than in England and £74 (2.2%) higher than in Wales. Proportionally, this equates to almost £1.8 billion more spending on frontline health services in Scotland compared to England, and almost £405 million more compared to Wales – equivalent to around 44,000 and 10,000 nurses, respectively.