- Asked by: Miles Briggs, MSP for Lothian, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 10 September 2025
-
Current Status:
Answered by Ivan McKee on 18 September 2025
To ask the Scottish Government, further to the answer to question S6W-38180 by Ivan McKee on 9 June 2025 regarding the current model of the Visitor Levy (Scotland) Act 2024, whether it will (a) provide an update on the progress of the discussions with the tourism sector regarding the model, including any proposed alternatives and (b) confirm what changes have been agreed to the model, and what the timeline for the implementation of these will be.
Answer
The Scottish Government has engaged extensively with the tourism sector throughout the development of the Visitor Levy (Scotland) Act 2024, including through a national consultation and the establishment of an Expert Group chaired by VisitScotland.
Ministers are aware that some areas of Scotland are seeking greater flexibility in how the levy is applied and administered. Consequently, we are now considering how to extend further powers to local authorities, in the future, including the option to introduce a single flat rate or tiered flat rate model alongside the existing percentage-based approach. This follows stakeholder feedback and would preserve local discretion. Any future changes will be shaped by consultation and evidence and I will update Parliament as officials progress this work.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 10 September 2025
-
Current Status:
Answered by Fiona Hyslop on 18 September 2025
To ask the Scottish Government, in light of the original commitment of the Aberdeen to Central Belt Enhancement Project to spend £200 million by 2026 to reduce journey times between Aberdeen and the central belt by 20 minutes, whether it will confirm (a) how much has been spent by the project so far, and on what specific areas of work, (b) what the projected final cost of the project is and (c) by what date (i) work on the project will be completed and (ii) the reduced journey times will be fully operational.
Answer
To 19/7/2025, £24.5m has been spent on schemes to reduce journey times between Aberdeen on the central Belt.
This includes £6.8m on the project to improve rail line speeds in the Barnhill area between Perth and Dundee. This was a nine-month programme of alignment work to replace a curved section of track by installing a new single line and also remodelling the junction at Barnhill by replacing switches and crossings.
The remainder of the spend has been on design development of a package of enhancements to improve capacity and journey time including: Signalling works, enhancements at Aberdeen, Montrose, Arbroath and Dundee stations, and freight loops.
The estimated cost of constructing all of the interventions necessary to deliver the project outputs sought by the project reference group is estimated at £242 million.
Delivery timescales for the project remain under review. It is planned that project delivery and thus benefit delivery will be staged to align with planned Network Rail renewals and other enhancement schemes such as Fife Electrification and replacement of ScotRail’s suburban fleet.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 25 September 2025
To ask the Scottish Government how many free personal care hours were assessed by local authorities to be needed, but were subsequently not delivered, in 2024-25.
Answer
Taken in the Chamber on 25 September 2025
- Asked by: Jackie Dunbar, MSP for Aberdeen Donside, Scottish National Party
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 25 September 2025
To ask the Scottish Government whether it will provide an update on the steps that it is taking to increase service capacity in GP practices within NHS Grampian.
Answer
Taken in the Chamber on 25 September 2025
- Asked by: Roz McCall, MSP for Mid Scotland and Fife, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 25 September 2025
To ask the Scottish Government what its response is to the latest Homelessness in Scotland statistics.
Answer
Taken in the Chamber on 25 September 2025
-
Current Status:
Withdrawn
- Asked by: Maggie Chapman, MSP for North East Scotland, Scottish Green Party
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 25 September 2025
To ask the Scottish Government whether it will provide an update on any discussions that it has had with Police Scotland about the policing of protests outside hotels and other accommodation for people seeking asylum.
Answer
Taken in the Chamber on 25 September 2025
- Asked by: Clare Haughey, MSP for Rutherglen, Scottish National Party
-
Submitting member has a registered interest.
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 25 September 2025
To ask the Scottish Government how it supports youth employment in the Rutherglen constituency, including through employability services.
Answer
Taken in the Chamber on 25 September 2025
- Asked by: Liam McArthur, MSP for Orkney Islands, Scottish Liberal Democrats
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 25 September 2025
To ask the Scottish Government what discussions it has had with NHS Orkney regarding reported delays in ophthalmology appointments for patients.
Answer
Taken in the Chamber on 25 September 2025
- Asked by: Stuart McMillan, MSP for Greenock and Inverclyde, Scottish National Party
-
Date lodged: Wednesday, 17 September 2025
-
Current Status:
Taken in the Chamber on 24 September 2025
To ask the Scottish Government what recent discussions it has had with the UK Government regarding the next UK Budget, which will be delivered on 26 November.
Answer
Taken in the Chamber on 24 September 2025